On this page
- Step 1: Reconcile the estimate to the signed contract
- Step 2: Separate the fee from the cost
- Step 3: Load cost by cost code and cost type
- Step 4: Give general conditions their own lines
- Step 5: Set contingency as a separate line
- Step 6: Check the totals, then lock the original
- Step 7: Control changes with two kinds of entry
- Step 8: Map it to the schedule of values and the cash plan
- Worked example: a $4.85 million lump-sum job
- Common mistakes
- How os.construction handles it
- FAQ
To set up a construction project budget, reconcile the awarded estimate to the signed contract, take out the fee, load the remaining cost into the budget by cost code and cost type, give general conditions and contingency their own lines, confirm the budget plus fee equals the contract, and lock it as the original budget. After that, change it only through recorded budget changes for owner changes and recorded transfers between lines, so the original stays intact and every movement has a reason.
The estimate was built to win the job. The budget is built to run it. The difference is mostly structure: an estimate can carry a lump-sum line for a subcontractor quote, an allowance someone negotiated on bid day, and markups stacked at the bottom. A budget has to sit on the cost codes and cost types your field and accounting teams will actually code to, or the monthly comparison of budget to cost never lines up.
Step 1: Reconcile the estimate to the signed contract
Start from the final estimate and list every change made between bid day and contract signing: scope clarifications, accepted alternates, value engineering, negotiated exclusions, allowances and price adjustments. The budget should match the contract you signed, not the bid you submitted. If the estimate and contract don’t reconcile, stop and find the difference before loading anything.
Step 2: Separate the fee from the cost
Take fee, or profit and any company overhead markup, out of the cost lines. What’s left is the cost budget:
cost budget = contract amount − fee
If fee sits inside cost lines, it gets spent to cover overruns without anyone deciding to. On GMP or cost-plus work, the contract defines the fee and what counts as cost, so set the budget up to match those definitions. Markup vs margin explains why the fee percentage depends on which base you use.
Step 3: Load cost by cost code and cost type
Break each estimate item into the codes and types you’ll track: labor, material, equipment, subcontract and other. A subcontract quote usually becomes one subcontract line under the right code. Self-performed work splits into labor, material and equipment so productivity and material overruns can be seen separately. If you need a code structure first, how to set up construction cost codes covers it.
Keep the level of detail to what you’ll manage. A line nobody will ever forecast is just a line that collects miscoded cost.
Step 4: Give general conditions their own lines
Site supervision, project management, temporary facilities, trailers, equipment, cleanup and similar time-based costs belong in general conditions lines, budgeted from the schedule duration and staffing plan. They are the lines most affected by delay, so they need to be visible on their own. How to calculate general conditions costs and the general conditions calculator cover the build-up.
Step 5: Set contingency as a separate line
Put contingency on its own line with a note on what it is for and who can approve using it. Don’t spread it across trade lines to make them look comfortable. On GMP work the contract may distinguish contractor contingency from owner contingency and set rules for each, so record which is which.
Step 6: Check the totals, then lock the original
Before locking, confirm:
sum of budget lines + fee = contract amount
Then lock the original budget. From this point it’s the baseline every report compares against: committed cost, actual cost, the cost-to-complete forecast and the estimate at completion.
Step 7: Control changes with two kinds of entry
After the original is locked, the budget changes only two ways:
- Budget changes for approved owner change orders, which add cost budget and contract value together.
- Transfers between lines, such as moving a buyout saving to contingency or drawing contingency to cover an overrun. A transfer moves money between lines without changing the total.
Both should carry a date, an amount, the lines affected and a reason. Pending changes belong in a separate projected column, not in the revised budget. Over time, the transfers tell the story of the job.
Step 8: Map it to the schedule of values and the cash plan
The schedule of values divides the contract, including fee, into billing lines. Map each budget line to a schedule of values line so billing and cost can be compared by area of work. Then use the budget’s timing to build the job’s cash flow projection. If you’ll measure progress with earned value, the budget is also the basis for planned value; the earned value explainer and the earned value calculator show how.
Worked example: a $4.85 million lump-sum job
The signed contract is $4,850,000, matching the final estimate after two accepted alternates. The estimate summarized to:
| Budget line | Cost type | Original budget |
|---|---|---|
| Sitework | Subcontract | $410,000 |
| Structural steel | Subcontract | $520,000 |
| Framing and drywall | Subcontract | $640,000 |
| Mechanical, electrical and plumbing | Subcontract | $1,540,000 |
| Finishes | Subcontract | $500,000 |
| Concrete | Labor | $248,000 |
| Concrete | Material | $186,000 |
| Concrete | Equipment | $42,000 |
| General conditions | Various | $312,000 |
| Insurance, bond and permits | Other | $74,000 |
| Contingency | Other | $120,000 |
| Cost budget | $4,592,000 | |
| Fee (not a cost line) | $258,000 | |
| Contract | $4,850,000 |
subcontracts = $410,000 + $520,000 + $640,000 + $1,540,000 + $500,000 = $3,610,000
self-performed concrete = $248,000 + $186,000 + $42,000 = $476,000
cost budget = $3,610,000 + $476,000 + $312,000 + $74,000 + $120,000 = $4,592,000
check: $4,592,000 + $258,000 = $4,850,000
The fee is $258,000 ÷ $4,850,000 = 5.3% of the contract, or $258,000 ÷ $4,592,000 = 5.6% markup on cost.
Month 2: a buyout saving. Framing and drywall is bought out at $622,000 against its $640,000 budget. The project manager records a transfer of $18,000 from framing and drywall to contingency. Contingency is now $138,000; the cost budget is still $4,592,000. How to run a construction buyout covers the log behind that decision.
Month 4: an owner change order. The owner approves a $64,000 change order priced at $58,000 of cost plus $6,000 of fee. A budget change adds $58,000 to the affected lines.
revised contract = $4,850,000 + $64,000 = $4,914,000
revised cost budget = $4,592,000 + $58,000 = $4,650,000
check: $4,650,000 + $258,000 + $6,000 = $4,914,000
The original budget still reads $4,592,000. Anyone comparing the two can see that $58,000 came from an owner change and that $18,000 moved from a trade line into contingency, each with a date and a reason. How to price a change order covers the pricing side.
Common mistakes
- Loading the bid, not the contract, so the budget misses negotiated changes from day one.
- Burying fee in cost lines, where it gets spent covering overruns.
- Spreading contingency across trade lines so nobody can see how much is left.
- Too much detail, with lines nobody forecasts and cost scattered across them.
- Editing the original budget instead of recording a change or transfer.
- Counting pending change orders in the revised budget.
- A budget that doesn’t map to the schedule of values, so billing and cost can’t be compared by area.
How os.construction handles it
The Budget tool holds the original budget per cost code and cost type, entered as an amount or as quantity times unit cost. Revised budget adds net transfers, recorded as Modifications with from and to lines and a note, and approved budget changes. Pending changes sit in a separate projected column, and committed and direct costs come from the commitments and direct cost tools, so a cost code with cost but no budget line still shows up. You can take snapshots, compare variance and lock the budget. The budget, commitments and cost explainer shows how the columns relate, and the free job cost report template is a starting point if you track it in a spreadsheet. For company-level reporting, see construction accounting software.
FAQ
How do you set up a construction project budget?
Start from the estimate as awarded and reconcile it to the signed contract. Take out the fee, then load each cost into the budget by cost code and cost type, matching how cost will be recorded. Give general conditions and contingency their own lines, check the budget plus fee equals the contract, lock it as the original budget, and from then on change it only through recorded budget changes and transfers.
What is the difference between the original budget and the revised budget?
The original budget is the cost plan at contract award, and it should not change. The revised budget adds approved changes, such as owner change orders, and reflects transfers between lines. Keeping both lets you see how the job moved from what was bid to what is being built.
Should profit or fee be in the project budget?
Usually not as a cost line. The budget is what you expect the work to cost; fee is the difference between that and the contract. Keeping fee out of the cost lines stops it being spent quietly to cover overruns. Some companies track it as a separate non-cost line so the budget still ties to the contract.
Is the project budget the same as the schedule of values?
No. The schedule of values divides the contract amount, including fee, into billing lines the owner approves. The budget divides expected cost into the cost codes you track. They should be reconcilable, and many companies map each budget line to a schedule of values line, but they serve different readers.
How should contingency be set up in a project budget?
As its own line, not spread across other lines. Record what it is for, who can approve drawing on it, and, on GMP or cost-plus contracts, what the contract says about its use. Move money out of contingency with a recorded transfer to the line that needs it, so the drawdown stays visible.
Share this article