How to calculate general conditions costs: build them from the schedule, not a percentage

General conditions are mostly the cost of time on site: staff, the field office, temporary facilities and cleanup. Estimate them from the schedule by pricing staff and site costs per month, adding one-time and quantity-driven items, and checking the contract for what belongs in the fee. Here is each step and a worked 12-month example.

Charley Forey5 min readEstimatingJob costContracts
On this page
  1. Step 1: Read the contract first
  2. Step 2: Get the duration and phases from the schedule
  3. Step 3: Price staff at burdened monthly rates
  4. Step 4: Price time-related site costs per month
  5. Step 5: Add one-time and quantity-driven items
  6. Step 6: Check the total
  7. Step 7: Budget it so you can track it monthly
  8. Worked example: a 12-month building
  9. Common mistakes
  10. How os.construction handles it
  11. FAQ

To calculate general conditions costs, start from the project schedule: build a staffing plan by month and price it at burdened rates, price the field office, temporary utilities, vehicles and other time-related site costs per month, then add one-time items (mobilization, fencing, final cleaning) and items that scale with the work (dumpsters, cleanup labor). Check the contract for what’s reimbursable and what belongs in the fee, and compare the total with your own past jobs.

General conditions are the cost of running the jobsite, separate from the trade work. Most of that cost is time: the superintendent, the trailer and the temporary power keep running every month the job is open. That’s why a percentage of trade cost is a poor way to estimate them, and why a schedule slip shows up so quickly in a job’s margin fade.

Step 1: Read the contract first

The contract decides how general conditions are paid and what goes in them. Look for:

  • What counts as reimbursable cost on a GMP or cost-plus job, and what is covered by the fee instead.
  • Whether the owner wants general conditions as a lump sum, a fixed monthly amount or cost reimbursed, and whether there’s a cap.
  • Staff rates, if the owner has to approve them in advance.
  • What the owner provides, such as temporary power or a builder’s risk policy.

On a lump sum job it’s your risk either way, but the owner may still ask for a breakdown on the schedule of values.

Step 2: Get the duration and phases from the schedule

Pull the construction duration from the schedule, then split it into phases: mobilization, structure, enclosure and rough-in, finishes, and closeout. Staffing changes by phase. A superintendent stays for the whole job; an assistant superintendent may only be needed through the peak months; a project engineer usually runs from buyout through closeout.

Step 3: Price staff at burdened monthly rates

For each role, multiply the burdened monthly cost by the share of their time charged to this job and the number of months. Burdened means salary plus payroll taxes, insurance, benefits and any vehicle or phone allowance the company pays. The labor burden calculator works out the percentage from your own costs.

staff cost = burdened monthly cost × share of time on this job × months

Staff is usually the biggest piece of general conditions, so this is where accuracy matters most.

List everything that runs by the month: field office rental, temporary toilets, phones and internet, office supplies, temporary power and water, and vehicles. Multiply the monthly cost by the months each one is needed, which isn’t always the full duration.

Step 5: Add one-time and quantity-driven items

One-time items are priced once: trailer delivery, setup and removal, fencing installed and removed, signage, final cleaning and demobilization.

Quantity-driven items scale with the amount of work, not the calendar: dumpster hauls, daily cleanup labor, hoisting and temporary protection. Estimate them from the trade activity in each phase.

Step 6: Check the total

Divide the total by the months to get a monthly figure, and divide it by the trade cost to get a percentage. Compare both with your own completed jobs of a similar size and type. If the percentage is far off, find out why before the bid goes in; usually a role, a duration or an owner-provided item explains it.

Step 7: Budget it so you can track it monthly

Set general conditions up on their own cost codes by item, not in one lump. Then cost to date can be compared with the plan month by month, and if the job is delayed you have the record that supports a request for extended general conditions.

Worked example: a 12-month building

Illustrative numbersMade-up rates and quantities for a 12-month job with $9.2 million of trade cost. Use your own burdened rates and suppliers’ prices.

Staff

Role Calculation Amount
Project manager, half time, 13 months $16,000 × 50% × 13 $104,000
Superintendent, 12 months $15,000 × 12 $180,000
Assistant superintendent, peak 5 months $11,000 × 5 $55,000
Project engineer, 11 months $9,500 × 11 $104,500
Staff total $443,500

Time-related site costs

Item Per month
Field office trailer rental $1,200
Temporary toilets $600
Phones, internet and office supplies $700
Temporary power and water $1,500
Superintendent’s truck $1,300
Per month $5,300
12 months $63,600

One-time and quantity-driven items

Item Calculation Amount
Trailer delivery, setup and removal lump sum $6,500
Perimeter fencing, install and remove lump sum $14,000
Signage lump sum $1,500
Final cleaning lump sum $9,500
One-time subtotal $31,500
Dumpster hauls 48 × $650 $31,200
Daily cleanup labor 40 weeks × 16 h × $52 burdened $33,280
Quantity-driven subtotal $64,480

Total

Bucket Amount Share
Staff $443,500 73.5%
Time-related site costs $63,600 10.5%
One-time items $31,500 5.2%
Quantity-driven items $64,480 10.7%
General conditions $603,080 100%

$603,080 is 6.6% of the $9.2 million trade cost. That percentage is only useful as a comparison with your own history; the estimate itself came from the schedule.

The number to keep is the monthly burn rate of the time-related costs once the assistant superintendent has left: superintendent $15,000, half the project manager $8,000, project engineer $9,500 and site costs $5,300, or $37,800 a month. If the job slips one month, that’s roughly what the extra month costs, before any extra cleanup or equipment.

Where 603,080 dollars of general conditions goesA single bar split into four parts: staff 443,500 dollars or 73.5 percent, time-related site costs 63,600 or 10.5 percent, one-time items 31,500 or 5.2 percent, and quantity-driven items 64,480 or 10.7 percent.STAFF 443,500 (73.5%)TIME 63,600ONE-TIME 31,500QUANTITY 64,480GENERAL CONDITIONS 603,080TIME-DRIVEN: 84%
Staff and monthly site costs, the parts that run with the calendar, are 84% of the total. Illustrative.

Common mistakes

  • Estimating general conditions as a percentage of cost. The percentage doesn’t know the schedule.
  • Unburdened staff rates. Salary alone leaves out taxes, insurance and benefits.
  • Every role for the full duration, or the reverse, forgetting the project manager and engineer during closeout.
  • Mixing in home-office overhead. Executives and accounting staff belong in the fee or markup, unless the contract says otherwise.
  • One lump-sum cost code. You can’t track a burn rate, or support extended general conditions, from a single line.
  • Pricing a schedule-extending change without its time. A change that adds a month adds a month of general conditions; see how to price a change order.

General information, not legal or accounting advice. Your contract and the law where the project sits decide what is reimbursable and whether delay costs are recoverable.

How os.construction handles it

You can code general conditions to their own cost codes in the Budget, so cost to date, commitments and the forecast for staff, field office and temporary facilities show separately from trade work, and the PM can override the forecast to complete on each line as the schedule moves. The schedule shows the duration they depend on. See Cost codes and budgets.

FAQ

What is included in general conditions costs?

The contractor's jobsite overhead for one project: project staff such as the superintendent, project manager and project engineers to the extent charged to the job, the field office, temporary facilities and utilities, cleanup and dumpsters, safety and small tools, and job-specific costs the contract allows, such as permits or testing. Home-office overhead is normally recovered through the fee or markup instead.

How do you estimate general conditions?

Start from the schedule. Build a staffing plan by month and price staff at burdened rates, price time-related site costs per month for the months they're needed, add one-time items such as mobilization and fencing, and add items that scale with the work, such as dumpsters and cleanup labor. Then check the contract for what it treats as reimbursable, fee or excluded.

Are general conditions a percentage of construction cost?

They're often reported that way, but estimating them as a percentage is risky because general conditions are driven mainly by duration. A job that runs two months longer costs two more months of staff and site costs whatever the trade cost is. Use the percentage only as a check against your own past jobs.

What is the difference between general conditions and general requirements?

Usage varies by company and contract. Where both terms are used, general conditions usually means time-driven items such as site staff and the field office, and general requirements means Division 01 work items such as temporary facilities, cleanup and hoisting. The contract's definitions decide what is reimbursable.

What are extended general conditions?

The time-related general conditions for the extra duration when a project is delayed, often claimed in a delay claim or included in a time-extension change order. Whether they are recoverable depends on the contract, including any no-damages-for-delay clause, and the cause of the delay. Tracking general conditions by month is what makes the number supportable.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Keep readingAll articles →
Job cost

Direct vs indirect costs in construction: job cost, general conditions and overhead

Direct costs can be traced to a specific job or piece of work. Indirect costs support the work without belonging to one item: the job's general conditions and the company's overhead. Here is how to draw the line, how each gets recovered, a worked estimate and the coding mistakes that distort margins.

5 min read

Estimating

How to calculate construction overhead and markup for a bid

Your markup has one job: recover company overhead and leave the profit you planned. To set it, you need an annual overhead budget, a realistic revenue volume, a profit target, and the margin-to-markup conversion most estimators get wrong. Here's the method step by step, with a worked bid and what happens to the number when volume drops.

5 min read

Job cost

Construction job costing: how to set up cost codes

A cost code list decides what your job cost report can tell you. Too coarse and overruns hide; too fine and the field codes everything to the first line on the list. Here's how to structure codes and cost types, when to follow CSI MasterFormat and when to build your own, a worked tenant improvement budget, and the rules that keep coding clean.