On this page
- Step 1: Read the contract first
- Step 2: Get the duration and phases from the schedule
- Step 3: Price staff at burdened monthly rates
- Step 4: Price time-related site costs per month
- Step 5: Add one-time and quantity-driven items
- Step 6: Check the total
- Step 7: Budget it so you can track it monthly
- Worked example: a 12-month building
- Common mistakes
- How os.construction handles it
- FAQ
To calculate general conditions costs, start from the project schedule: build a staffing plan by month and price it at burdened rates, price the field office, temporary utilities, vehicles and other time-related site costs per month, then add one-time items (mobilization, fencing, final cleaning) and items that scale with the work (dumpsters, cleanup labor). Check the contract for what’s reimbursable and what belongs in the fee, and compare the total with your own past jobs.
General conditions are the cost of running the jobsite, separate from the trade work. Most of that cost is time: the superintendent, the trailer and the temporary power keep running every month the job is open. That’s why a percentage of trade cost is a poor way to estimate them, and why a schedule slip shows up so quickly in a job’s margin fade.
Step 1: Read the contract first
The contract decides how general conditions are paid and what goes in them. Look for:
- What counts as reimbursable cost on a GMP or cost-plus job, and what is covered by the fee instead.
- Whether the owner wants general conditions as a lump sum, a fixed monthly amount or cost reimbursed, and whether there’s a cap.
- Staff rates, if the owner has to approve them in advance.
- What the owner provides, such as temporary power or a builder’s risk policy.
On a lump sum job it’s your risk either way, but the owner may still ask for a breakdown on the schedule of values.
Step 2: Get the duration and phases from the schedule
Pull the construction duration from the schedule, then split it into phases: mobilization, structure, enclosure and rough-in, finishes, and closeout. Staffing changes by phase. A superintendent stays for the whole job; an assistant superintendent may only be needed through the peak months; a project engineer usually runs from buyout through closeout.
Step 3: Price staff at burdened monthly rates
For each role, multiply the burdened monthly cost by the share of their time charged to this job and the number of months. Burdened means salary plus payroll taxes, insurance, benefits and any vehicle or phone allowance the company pays. The labor burden calculator works out the percentage from your own costs.
staff cost = burdened monthly cost × share of time on this job × months
Staff is usually the biggest piece of general conditions, so this is where accuracy matters most.
Step 4: Price time-related site costs per month
List everything that runs by the month: field office rental, temporary toilets, phones and internet, office supplies, temporary power and water, and vehicles. Multiply the monthly cost by the months each one is needed, which isn’t always the full duration.
Step 5: Add one-time and quantity-driven items
One-time items are priced once: trailer delivery, setup and removal, fencing installed and removed, signage, final cleaning and demobilization.
Quantity-driven items scale with the amount of work, not the calendar: dumpster hauls, daily cleanup labor, hoisting and temporary protection. Estimate them from the trade activity in each phase.
Step 6: Check the total
Divide the total by the months to get a monthly figure, and divide it by the trade cost to get a percentage. Compare both with your own completed jobs of a similar size and type. If the percentage is far off, find out why before the bid goes in; usually a role, a duration or an owner-provided item explains it.
Step 7: Budget it so you can track it monthly
Set general conditions up on their own cost codes by item, not in one lump. Then cost to date can be compared with the plan month by month, and if the job is delayed you have the record that supports a request for extended general conditions.
Worked example: a 12-month building
Staff
| Role | Calculation | Amount |
|---|---|---|
| Project manager, half time, 13 months | $16,000 × 50% × 13 | $104,000 |
| Superintendent, 12 months | $15,000 × 12 | $180,000 |
| Assistant superintendent, peak 5 months | $11,000 × 5 | $55,000 |
| Project engineer, 11 months | $9,500 × 11 | $104,500 |
| Staff total | $443,500 |
Time-related site costs
| Item | Per month |
|---|---|
| Field office trailer rental | $1,200 |
| Temporary toilets | $600 |
| Phones, internet and office supplies | $700 |
| Temporary power and water | $1,500 |
| Superintendent’s truck | $1,300 |
| Per month | $5,300 |
| 12 months | $63,600 |
One-time and quantity-driven items
| Item | Calculation | Amount |
|---|---|---|
| Trailer delivery, setup and removal | lump sum | $6,500 |
| Perimeter fencing, install and remove | lump sum | $14,000 |
| Signage | lump sum | $1,500 |
| Final cleaning | lump sum | $9,500 |
| One-time subtotal | $31,500 | |
| Dumpster hauls | 48 × $650 | $31,200 |
| Daily cleanup labor | 40 weeks × 16 h × $52 burdened | $33,280 |
| Quantity-driven subtotal | $64,480 |
Total
| Bucket | Amount | Share |
|---|---|---|
| Staff | $443,500 | 73.5% |
| Time-related site costs | $63,600 | 10.5% |
| One-time items | $31,500 | 5.2% |
| Quantity-driven items | $64,480 | 10.7% |
| General conditions | $603,080 | 100% |
$603,080 is 6.6% of the $9.2 million trade cost. That percentage is only useful as a comparison with your own history; the estimate itself came from the schedule.
The number to keep is the monthly burn rate of the time-related costs once the assistant superintendent has left: superintendent $15,000, half the project manager $8,000, project engineer $9,500 and site costs $5,300, or $37,800 a month. If the job slips one month, that’s roughly what the extra month costs, before any extra cleanup or equipment.
Common mistakes
- Estimating general conditions as a percentage of cost. The percentage doesn’t know the schedule.
- Unburdened staff rates. Salary alone leaves out taxes, insurance and benefits.
- Every role for the full duration, or the reverse, forgetting the project manager and engineer during closeout.
- Mixing in home-office overhead. Executives and accounting staff belong in the fee or markup, unless the contract says otherwise.
- One lump-sum cost code. You can’t track a burn rate, or support extended general conditions, from a single line.
- Pricing a schedule-extending change without its time. A change that adds a month adds a month of general conditions; see how to price a change order.
General information, not legal or accounting advice. Your contract and the law where the project sits decide what is reimbursable and whether delay costs are recoverable.
How os.construction handles it
You can code general conditions to their own cost codes in the Budget, so cost to date, commitments and the forecast for staff, field office and temporary facilities show separately from trade work, and the PM can override the forecast to complete on each line as the schedule moves. The schedule shows the duration they depend on. See Cost codes and budgets.
FAQ
What is included in general conditions costs?
The contractor's jobsite overhead for one project: project staff such as the superintendent, project manager and project engineers to the extent charged to the job, the field office, temporary facilities and utilities, cleanup and dumpsters, safety and small tools, and job-specific costs the contract allows, such as permits or testing. Home-office overhead is normally recovered through the fee or markup instead.
How do you estimate general conditions?
Start from the schedule. Build a staffing plan by month and price staff at burdened rates, price time-related site costs per month for the months they're needed, add one-time items such as mobilization and fencing, and add items that scale with the work, such as dumpsters and cleanup labor. Then check the contract for what it treats as reimbursable, fee or excluded.
Are general conditions a percentage of construction cost?
They're often reported that way, but estimating them as a percentage is risky because general conditions are driven mainly by duration. A job that runs two months longer costs two more months of staff and site costs whatever the trade cost is. Use the percentage only as a check against your own past jobs.
What is the difference between general conditions and general requirements?
Usage varies by company and contract. Where both terms are used, general conditions usually means time-driven items such as site staff and the field office, and general requirements means Division 01 work items such as temporary facilities, cleanup and hoisting. The contract's definitions decide what is reimbursable.
What are extended general conditions?
The time-related general conditions for the extra duration when a project is delayed, often claimed in a delay claim or included in a time-extension change order. Whether they are recoverable depends on the contract, including any no-damages-for-delay clause, and the cause of the delay. Tracking general conditions by month is what makes the number supportable.
Share this article