A general contractor (GC) is the company that holds the prime construction contract with the owner and is responsible for building the whole project. It prices the work, hires and coordinates subcontractors and suppliers, often self-performs some trades, runs the schedule and the site, and answers to the owner for the result. In the UK the same role is usually called the main contractor.
The term describes a contract position more than a type of company. The same firm can be a GC on one job, a CM at risk on the next and a design-builder on a third. What makes it the general contractor is that it signs the construction contract with the owner and carries the risk of delivering the work for the agreed price and time.
How it works
- Procurement. On design-bid-build work the owner bids finished drawings and awards to a GC, often on price. On negotiated work the GC is selected earlier and provides preconstruction services.
- Prime contract. The owner and GC sign an agreement, often an AIA A101 or A102 with A201 general conditions, or the owner’s own form. Price may be lump sum, cost plus a fee, or a GMP.
- Buyout. The GC lets subcontracts and purchase orders for the trades it doesn’t self-perform, flowing down the prime contract terms that apply to each trade.
- Construction. The GC manages the schedule, site logistics, safety, quality, RFIs, submittals and changes, and keeps daily records.
- Billing and payment. Each month the GC bills the owner against the schedule of values and pays its trades, holding retainage where the contract allows.
- Closeout. Punch list, inspections, warranties, O&M manuals and final payment.
The GC’s own site management costs, such as the superintendent, trailer and temporary utilities, are usually carried as general conditions, and its profit and home office overhead as a fee or markup.
General contractor vs other roles
| Role | Contract with owner | When it joins | Who holds design | Price basis |
|---|---|---|---|---|
| General contractor | Construction contract | After design (hard bid) or earlier if negotiated | Owner’s architect | Lump sum, cost plus or GMP |
| CM at risk | Preconstruction then construction (GMP) | During design | Owner’s architect | Cost plus fee with GMP |
| CM as agent | Advisory services only | Any time | Owner’s architect | Fee; owner holds trade contracts |
| Design-builder | One contract for design and construction | Early | Design-builder | Lump sum, GMP or cost plus |
| Subcontractor | None; contracts with the GC | At buyout | Not its role, except delegated design | Usually lump sum or unit price |
For a closer comparison of the GC and construction manager roles, with a worked example, see general contractor vs construction manager.
Main contractor and principal contractor (UK)
In the UK, main contractor is the everyday term for the firm holding the building contract, often under a JCT or NEC form. Principal contractor has a narrower legal meaning. Under the Construction (Design and Management) Regulations 2015 (CDM 2015), the principal contractor is appointed by the client to plan, manage and coordinate health and safety in the construction phase, and one is required on any project with more than one contractor. The main contractor usually takes that appointment, but the two terms aren’t interchangeable.
Why it matters
The GC sits in the middle of every money flow and every risk on the job. It is paid by the owner and pays everyone else, so cash timing, retainage and pay-when-paid terms decide whether it is financing the project. It is answerable for its subcontractors’ work, so a gap between what the prime contract requires and what the subcontracts say becomes the GC’s cost. And because its margin is thin compared with the volume it handles, small leaks in change management or buyout show up directly in profit.
Worked example
Illustrative: an owner awards a $14.2 million lump-sum contract for a three-story office building to a GC. The GC self-performs concrete and carpentry, about $2.1 million of the work, and lets 22 subcontracts and purchase orders for the rest. Its estimate carries $1.05 million of general conditions and a 4.5% fee. During the job a mechanical subcontractor’s scope turns out to exclude controls wiring that the prime contract requires. The owner holds the GC to the full scope, so the GC buys the wiring from an electrician for $68,000 and absorbs it, because the gap was between its own subcontracts rather than in the owner’s drawings.
Common mistakes
- Subcontract scopes that don’t add up to the prime contract scope.
- Flow-down clauses that leave out schedule, warranty or insurance terms the owner imposed.
- Front-loading the owner’s schedule of values without tracking what that does to over and under billing.
- Paying trades before the owner pays, without the contract terms to support it.
- Using “principal contractor” in UK documents as if it simply meant main contractor.
This is general information, not legal advice. Licensing, contract terms and payment rules vary by state, country and contract form.
How os.construction handles it
In the app today, a GC can keep the prime contract, owner change orders and payment applications on the owner side, and commitments (subcontracts and purchase orders with their own schedules of values) on the trade side, all against the same cost codes. That lets the team see what is billed to the owner, what is committed to trades and what has been spent on one record. See budget, commitments and cost for how those numbers tie together.
FAQ
What does a general contractor do?
A general contractor signs the prime contract with the owner and takes responsibility for delivering the work it describes. In practice it estimates and prices the job, hires and coordinates subcontractors and suppliers, runs the schedule, manages the site, safety and quality, handles RFIs, submittals and changes, bills the owner monthly and pays its trades. Some GCs also self-perform trades such as concrete or carpentry.
What is the difference between a general contractor and a subcontractor?
The general contractor contracts directly with the owner for the whole project. A subcontractor contracts with the general contractor, not the owner, for a part of the work such as electrical or drywall. The GC is answerable to the owner for its subcontractors' work, and the subcontract usually passes down the prime contract's relevant terms through flow-down clauses.
Is a general contractor the same as a construction manager?
Not exactly. A construction manager at risk joins during design, provides preconstruction services and then builds the job under a guaranteed maximum price, so it ends up in a GC-like role. A construction manager as agent advises the owner without holding the trade contracts. A traditional general contractor is usually hired after design, often by competitive bid.
What is a main contractor in the UK?
Main contractor is the usual UK term for the firm that holds the building contract with the client, which in the US would be the general contractor. The UK also uses principal contractor, but under the Construction (Design and Management) Regulations 2015 that is a specific health and safety duty holder appointed by the client to control the construction phase, which is often, though not always, the main contractor.
Does a general contractor need a license?
In many US states, yes, and the rules vary widely by state and sometimes by city. California, for example, licenses a Class B general building contractor, whose work must involve at least two unrelated building trades. Check the licensing board where the project is located before you bid.