Project delivery method selector
Design-bid-build, construction manager at risk, design-build or integrated project delivery? Answer eleven questions about your project and owner, see how each answer moves each method, compare them side by side and download a decision memo.
Sample answers: a private, complex project at schematic design with critical schedule pressure, a GMP in mind and an owner who wants to keep its own architect.
How this is calculated
The selector is a points model, not a black box. Each of the eleven answers adds or subtracts points for each method, based on how the methods allocate design responsibility, price timing, schedule overlap and risk. The weights are editorial judgment drawn from the sources below; they are shown in full in the points table so you can disagree with any of them.
Points(method) = Σ points of your answer to each question
Fit(method) = (points − lowest possible) ÷ (highest possible − lowest possible) × 100
Not permitted = a public owner limited to low-bid award: CMAR, DB and IPD are flagged
and sorted last until you confirm legal authority
Close call = top two within 10 fit pointsWhat moves the answer most
Procurement authority comes first: a public owner limited to low-bid award can usually only use design-bid-build. After that, design completeness and schedule pressure separate design-bid-build from the rest, price timing separates CM at risk (a GMP during design) from design-build (an early price with design risk transferred) and IPD (a shared target cost), and owner staff and willingness to share risk decide whether IPD is realistic. Our guide to delivery methods walks through each one, and the glossary covers design-build, design-bid-build and preconstruction.
How to choose a delivery method with this selector
- Answer the eleven questions. Pick the answer closest to your project for each question: who the owner is, how far the design is, schedule pressure, when you need a price, design control, complexity, owner staff, single responsibility, shared risk, price competition and scope stability.
- Read the ranking. Each method gets a fit score from 0 to 100. A method the owner may not be allowed to use is flagged and sorted last.
- Check the reasoning. Open the points table to see exactly which answer moved which method, and by how much. Change an answer and watch the ranking move.
- Compare the methods. Use the comparison table for how each method handles contracts, selection, price timing and design responsibility.
- Download the decision memo. Add the project and your name, then download the memo as a Word file or Markdown, or print it, for the owner, the board or the procurement file.
Delivery method questions
What are the main project delivery methods?
Design-bid-build (the owner hires a designer, then bids the finished design to contractors), construction manager at risk (the owner hires a designer and, during design, a CM who later commits to a guaranteed maximum price), design-build (one contract for design and construction) and integrated project delivery (owner, designer and builder sign one agreement and share risk and reward). Variations include progressive design-build, bridging and multiple-prime contracting.
Which delivery method is fastest?
Methods that let construction start before design is finished: design-build, CM at risk and IPD. Design-bid-build runs design, bidding and construction in sequence, so it is usually the slowest from start to finish, though each phase is simple.
Which method gives the lowest price?
Design-bid-build gives the most direct price competition, because every bidder prices the same complete design. That does not always mean the lowest final cost: gaps in the design come back as change orders. CMAR and design-build trade some price competition for builder input during design.
What is the difference between CM at risk and design-build?
In CM at risk the owner holds two contracts, one with the architect and one with the CM, and the architect’s design is the owner’s responsibility. In design-build the owner holds one contract, and the design-builder is responsible for both the design and the construction.
Can public owners use design-build or CM at risk?
Only where a statute, charter or regulation authorizes it. Federal agencies can use two-phase design-build selection under FAR Subpart 36.3, and GSA uses construction manager as constructor under GSAM Subpart 536.71. States and local governments each have their own rules, and many limit alternative delivery to certain project types or sizes. Check your authority before you choose.
What does it take to make IPD work?
An experienced owner who participates in the team, a multi-party agreement with shared savings and overruns against a target cost, open-book accounting, and key parties brought on at the start. Without shared risk and reward it is collaboration under another method, not IPD.
Is this tool’s recommendation authoritative?
No. It is a transparent points model that organizes the main trade-offs. The points table shows every weight so you can disagree with it. Legal authority, lender and surety requirements and your own team’s experience can override any score.
Sources
Checked Nov 21, 2026. Public procurement authority varies by state, agency and project type. This tool does not determine what any owner is legally permitted to use.
- What Is Design-Build?, Design-Build Institute of America (checked Nov 21, 2026).Used for: design-build as a single contract for design and construction; progressive and two-step best value variations.
- FAR 36.104: Policy (construction and architect-engineer contracts), Acquisition.gov (checked Nov 21, 2026).Used for: federal use of design-bid-build or two-phase design-build selection.
- FAR 36.301: Use of two-phase design-build selection procedures, Acquisition.gov (checked Nov 21, 2026).Used for: when federal agencies use two-phase design-build: three or more offers expected, design work by offerors, defined requirements, time constraints and agency capacity.
- GSAM Subpart 536.71: Construction-Manager-as-Constructor Contracting, Acquisition.gov (checked Nov 21, 2026).Used for: federal CM-as-constructor: design-phase services at a firm fixed price with a construction option at a guaranteed maximum price.
- Integrated Project Delivery: A Guide (2007), AIA and AIA California Council (checked Nov 21, 2026).Used for: IPD principles: early involvement of key participants, shared risk and reward, multi-party agreements.
When the spreadsheet version stops scaling
Whatever the method, the contract and the money stay on one record.
Delivery method decides who signs what. In os.construction the prime contract, its billing method and its schedule of values sit on the same project as the budget, commitments and change orders, so a GMP, a lump sum or a cost-plus job is tracked the same way.
- Prime contracts with progress, GMP, cost-plus, unit price, T&M and milestone billing methods in Accounting (live).
- GMP pay apps checked against the GMP before they can be certified (live).
- Bidding with award review and buyout against a captured budget snapshot (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →