Notice to proceed generator

Fill in the contract, pick a full or limited notice, and get a ready-to-sign NTP letter with the commencement date, the completion dates worked out in calendar or working days, the early-work scope for a limited notice and the contractor’s acknowledgment.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link
Type of notice
Contract and parties
Date of commencement
Contract time
Comma-separated, yyyy-mm-dd: shutdowns, local holidays.
$
Limited NTP: authorized early work
ScopeCost codeNot to exceed $
Due before work starts

Key datesLive

Commencement
—
Substantial completion
—
Final completion
—
Liquidated damages
—

    The letterLive

    Sample: a full notice on a 540-calendar-day contract, commencing 10 days after the contractor receives it, with $2,500 a day in liquidated damages.

    Method

    How this is calculated

    The dates come straight from the agreement’s terms. The generator adds the contract time to the date of commencement in calendar days, or steps through working days skipping weekends, observed US federal holidays (optional) and any non-working dates you list.

    Commencement          = notice date | stated date | receipt date + N calendar days
    Substantial (calendar) = commencement + contract days        (− 1 if day 1 is the commencement date)
    Substantial (working)  = the Nth working day after commencement
                             (the commencement date is day 1 if you tick it; weekends, holidays and listed dates skipped)
    Final completion      = substantial completion + final completion days
    Limited NTP total     = Σ not-to-exceed amounts

    Worked example

    The sample notice is dated December 1, 2026 and the contractor receives it December 3. Commencement is 10 days after receipt: December 13, 2026. A 540-calendar-day contract time puts substantial completion on June 5, 2028, and 60 more days puts final completion on August 4, 2028. Switch to working days and the same 540 days, skipping weekends and federal holidays, runs into 2029.

    Full or limited?

    Use a limited notice to proceed when early work has to start before financing, permits or the final contract are done: name each activity, cap it, set an expiry and say what happens if the full notice never comes. The NTP glossary entry covers the meaning, and the notice to proceed template has a printable checklist for what to confirm before the notice goes out.

    How to write a notice to proceed with this generator

    1. Pick full or limited. A full notice starts the work and usually the contract time. A limited notice releases only named early work under a not-to-exceed amount.
    2. Fill in the parties and the contract. Project, contract number, owner, contractor and who signs for the owner.
    3. Set how commencement is fixed. The date of the notice, a stated later date, or a number of days after the contractor receives it, as your agreement says.
    4. Set the contract time. Enter the days, calendar or working, and whether the commencement date counts as day 1. Working days can skip US federal holidays and any shutdown dates you list.
    5. Check the dates and print. Read the computed substantial and final completion dates, then print the letter or download it as Word or plain text and get the acknowledgment signed.

    Notice to proceed questions

    What does NTP mean in construction?

    NTP is a notice to proceed: the owner’s written notice telling the contractor to start work. It often fixes the date of commencement, which starts the contract time and so sets the dates for substantial and final completion.

    What is the difference between a limited and a full notice to proceed?

    A full NTP releases the whole contract. A limited NTP authorizes only named early work, such as mobilization, design, permits or long-lead purchases, usually under a not-to-exceed amount and an expiry date, and usually without starting the contract time unless it says so.

    How is the completion date calculated from the NTP?

    Contract time is added to the date of commencement. Whether the commencement date counts as day 1, and whether days are calendar or working days, comes from your agreement. Federal contracts using FAR 52.211-10 set completion as a number of calendar days after the contractor receives the notice. This generator shows both counting conventions.

    Are weekends and holidays excluded?

    Only if the contract counts working days. Calendar-day contracts count every day. For working days, this tool skips Saturdays, Sundays, optionally US federal holidays as observed (5 U.S.C. 6103), and any extra dates you enter, such as a holiday shutdown.

    Is this notice a legal form?

    It is an original template with plain wording, not an AIA, EJCDC or ConsensusDocs form. Your agreement controls the date of commencement, contract time and liquidated damages; check the notice against it before you send it.

    Sources

    Checked Nov 21, 2026. The letter wording is original. Check it against your agreement; the contract’s definitions of commencement, contract time and days control.

    1. FAR 52.211-10: Commencement, Prosecution, and Completion of Work, Acquisition.gov (checked Nov 21, 2026).Used for: federal contracts: start within a stated number of calendar days after receiving the notice to proceed and complete within the stated period, including final cleanup.
    2. 5 U.S.C. § 6103: Holidays, Legal Information Institute, Cornell Law School (checked Nov 21, 2026).Used for: the eleven legal public holidays used for the optional working-day calendar.
    3. Federal holidays, U.S. Office of Personnel Management (checked Nov 21, 2026).Used for: a holiday on a Saturday is observed the Friday before; on a Sunday, the Monday after.

    When the spreadsheet version stops scaling

    Put the dates the notice sets into the schedule.

    A notice to proceed sets the dates everything else hangs from. In os.construction the prime contract records its dates, the schedule holds commencement, substantial and final completion as milestones with contract-date constraints, and the signed notice is filed with the contract in Documents.

    • CPM schedule with milestones and date constraints (live).
    • Prime contracts with their dates and schedule of values (live).
    • Versioned, permissioned Documents for the signed notice and acknowledgment (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file