In construction, NTP stands for notice to proceed: the owner’s written authorization for the contractor to start work. On most jobs, the NTP date starts the contract time, the countdown to substantial completion, so it anchors the schedule, liquidated damages and any time extension claims. A limited NTP may authorize only early work first.
| NTP at a glance | |
|---|---|
| Stands for | Notice to proceed |
| Issued by | The owner (or its representative), in writing |
| Issued when | After the contract is signed and bonds and insurance are in |
| Starts | Contract time, unless the contract sets another commencement date |
| Drives | Substantial completion date, liquidated damages, time extensions |
| Variant | Limited NTP: early scope only, often with a dollar cap |
In plain English
Illustrative: you sign a $6.2 million contract for a library on January 15 that allows 420 calendar days to substantial completion. The city is still waiting on its building permit, so nothing starts. On March 1 the city sends a one-page letter: “You are hereby notified to proceed on March 4, 2026.” That letter is the NTP, March 4 is the NTP date, and day 420 falls on April 27 of the following year (counting March 4 as day 1). Finish late and liquidated damages start counting from then, not from the January signing date.
The NTP normally comes after the contract is signed and the contractor has delivered required bonds and insurance. It may be a one-page letter or a standard agency form. It typically states the project, the contract, the date work may begin, the contract time and the resulting completion dates.
How it works
- Award and agreement. The owner awards the job and both parties sign the contract.
- Pre-NTP requirements. The contractor delivers performance and payment bonds, certificates of insurance and any other items the contract requires. The owner secures financing, land and key permits.
- Optional limited NTP. If early work is needed, the owner issues a limited notice to proceed for specific scope, often with a dollar cap.
- Full NTP. The owner issues the notice to proceed for the whole work. The contract states whether contract time starts on the NTP date, on a later date in the notice, or a set number of days after receipt.
- Contract time runs. The schedule baseline is set from the NTP date. Substantial completion is due when contract time ends, adjusted by approved time extensions.
What goes in a notice to proceed
A good NTP is short, but it should leave nothing to argue about later. The usual sections, which our free notice to proceed template follows:
- Parties and project: owner, contractor, project name, contract number and contract date.
- Authorization: a plain statement that the contractor is authorized to proceed with the work, or, for a limited NTP, exactly which work and up to what dollar cap.
- Commencement date: the date contract time starts, and whether the NTP date counts as day 1.
- Contract time and completion dates: the number of calendar or working days, and the resulting substantial and final completion dates, with any interim milestones.
- Conditions already met or still due: bonds, insurance, permits and submittals received, and anything the contractor must still deliver before mobilizing.
- Site access: when and where the site is available, laydown areas and any restrictions.
- Signatures: the owner’s authorized representative, and the contractor’s acknowledgment of receipt with the date.
NTP vs notice of award vs notice of commencement
| Notice of award | Notice to proceed | Notice of commencement | |
|---|---|---|---|
| Who issues it | Owner | Owner | Owner, recorded with the county (in states that use it) |
| What it does | Tells the winning bidder it was selected | Authorizes work and starts contract time | Gives public notice of the project for lien purposes |
| Authorizes work? | No | Yes | No |
| Sent to | Winning bidder | Contractor | County recorder; posted on site |
A notice of commencement is a lien-law document in states such as Florida; it has nothing to do with contract time.
Limited NTP vs full NTP
| Limited NTP | Full NTP | |
|---|---|---|
| Authorizes | Named early scope only | All work under the contract |
| Typical scope | Mobilization, design, permitting, long-lead procurement | Everything |
| Dollar limit | Usually capped | Contract sum |
| Starts contract time | Usually not, unless the contract says so | Usually yes |
| Common on | Design-build, EPC, energy, financed projects | All contract types |
Timeline
Typical, set by your contract:
- Award to NTP: often a few weeks, longer when the owner is waiting on financing or permits. Some contracts let the contractor request a price or time adjustment if the NTP is delayed past a stated date.
- Receipt to start: federal contracts using FAR 52.211-10 require the contractor to begin work within a stated number of calendar days after receiving the NTP, and to complete within the stated period.
- Contract time: measured in calendar days or working days from the commencement date. A201-based contracts define substantial completion as the end point.
Who is responsible
- Owner: issues the NTP, and is typically responsible for site access, permits it must obtain, and funding.
- Contractor: meets pre-NTP requirements, mobilizes and starts work within the required period, and records the NTP date in the schedule baseline.
- Architect or engineer: may transmit the NTP, and administers contract time from it.
What to check before you mobilize
- The NTP is written and signed by someone with authority under the contract.
- The commencement date and contract time match the agreement, and you know whether the count is calendar or working days.
- Pre-NTP items are delivered: bonds, insurance certificates, schedule of values, initial schedule and any submittals the contract requires before start.
- The site is actually available, including access, laydown areas and any owner-furnished items.
- Permits are issued, or you know which ones are your responsibility.
- The baseline schedule starts from the NTP date and shows the contract completion milestone.
If any of these are missing when the NTP arrives, say so in writing right away. It protects your time extension rights later.
Many of these items are covered at the preconstruction meeting; see how to run a preconstruction meeting for a sample agenda.
Why it matters
The NTP date is the anchor for schedule, liquidated damages and time extension claims. An owner that issues the NTP late, or issues it before the site is available, may owe time and sometimes money, depending on the contract. Starting work before you have it can mean unpaid work if the project stalls, and an unclear NTP date makes every later schedule argument harder.
Worked example
Illustrative: a contract allows 540 calendar days from NTP to substantial completion. NTP is issued March 3, so day 540 lands in late August of the following year (the exact day depends on whether the contract counts the NTP date as day 1 and whether a leap day falls in between). If the owner issues the NTP three weeks late, completion moves three weeks with it. If the owner issues it on time but the site isn’t available for those three weeks, the contractor should give written notice and request a time extension, which may be compensable depending on the contract.
Common mistakes
- Mobilizing on a handshake before a written NTP.
- Confusing a limited NTP with authorization for the full scope.
- Not recording the NTP date in the schedule baseline.
- Assuming the signing date is the commencement date when the contract says otherwise.
- Missing the “begin within X days” requirement after receipt.
This is general information, not legal advice. Commencement terms vary by contract and owner.
How os.construction handles it
In Scheduling, you set the notice to proceed when you create a plan: it becomes the planned start, and every date is calculated from it. Name the baseline after it, for example “Contract baseline, NTP 2026-03-02”, and use a constraint on the substantial completion milestone for the contract date, so float shows how much room remains.
To issue one, the free notice to proceed template covers the commencement date, contract time, completion dates and a limited NTP option, with the contractor’s acknowledgment.
Watch the explainer · 2:50
Notice to proceed (NTP) explained
- 0:00What NTP means
- 0:21Paperwork first, then the NTP
- 0:41What the notice says
- 0:59When the clock starts
- 1:23An illustrative contract
- 1:43NTP on time, site not ready
- 2:04Limited notice to proceed
- 2:26Before you mobilize
Read the transcript
NTP stands for notice to proceed. It's the owner's written authorization for the contractor to start work under a signed contract. On most jobs, the NTP date starts contract time, the countdown to substantial completion. That one date anchors the schedule, liquidated damages and any time extension claims.
The NTP usually isn't the day the contract is signed. First comes award and the agreement. Then the contractor delivers its performance and payment bonds and certificates of insurance, while the owner lines up financing, land and key permits. Only then does the owner issue the notice to proceed, often weeks after signing.
The notice can be a one-page letter or an agency form. It should name the project and the contract, the date work may begin, the contract time, and the completion dates that result. It must be in writing and signed by someone with authority under the contract.
When does the clock actually start? The contract decides. The standard AIA owner-contractor agreement lets the parties pick the agreement date, a date set in a notice to proceed, or another method. Federal contracts using the FAR commencement clause require work to begin within a stated number of calendar days after the contractor receives the notice.
Here's an illustrative contract: five hundred forty calendar days from NTP to substantial completion. The NTP is issued March third, so completion lands in late August of the following year. If the owner issues the NTP three weeks late, the completion date moves three weeks with it.
Now flip it. The NTP goes out on time, but the site isn't available for those three weeks. The clock is running, but the crews can't work. Give written notice right away and request a time extension, which may be compensable depending on the contract. Terms vary by contract; this is general information, not legal advice.
A limited notice to proceed authorizes only named early work, such as design, permitting, mobilization or ordering long-lead equipment, usually with a dollar cap. It usually doesn't start contract time; the full NTP releases everything else. Track spending against the cap, and don't treat a limited NTP as a green light for the whole job.
Before you mobilize, check that the NTP is written and signed, that the commencement date and contract time match the agreement, and that the site and permits are really available. In os.construction Scheduling, the notice to proceed is the planned start of a new schedule, and every date is calculated from it.
Video page with chaptersMore in Construction concepts explained
FAQ
What does NTP mean in construction?
NTP stands for notice to proceed. It is the owner's written authorization for the contractor to begin work under a signed contract. In most contracts, the date of the NTP, or a set number of days after it, is the date of commencement, which starts the contract time used to measure substantial completion and liquidated damages.
What is the NTP date?
The NTP date is the date stated in, or established by, the notice to proceed. Depending on the contract, contract time may start on that date, on a later date written in the notice, or a fixed number of days after the contractor receives it. Federal contracts, for example, often require work to start within a set number of calendar days after receipt of the notice.
What is a limited notice to proceed?
A limited notice to proceed (LNTP) authorizes only part of the work, such as mobilization, design, permitting or ordering long-lead equipment, usually with a dollar cap. It lets early activities start while financing, permits or the final contract are still being completed. A full NTP later releases the rest of the work and usually starts or confirms the contract time.
Is the contract signing date the same as the notice to proceed?
Not necessarily. Many contracts are signed weeks before the NTP because the owner is waiting on permits, financing or land. AIA A101-2017 lets the parties choose whether the date of commencement is the agreement date, a date set in a notice to proceed, or another method. Check which one your contract uses.
Can you start work before the notice to proceed?
You can, but it's risky. Work done before a written NTP or other written authorization may not be paid if the project stalls, may not be covered by the owner's insurance or permits, and can muddy the start of contract time. If early work is needed, ask for a limited notice to proceed that spells out the scope and a dollar cap.
What is the difference between a notice of award and a notice to proceed?
A notice of award tells the winning bidder it has been selected and asks it to sign the contract and deliver bonds and insurance. It doesn't authorize work. The notice to proceed comes after those steps and actually authorizes the contractor to start, usually starting contract time. On public jobs the two can be weeks apart.
How does an AIA contract handle the notice to proceed?
AIA A101-2017 handles it through the date of commencement. The parties choose whether work starts on the agreement date, on a date set in a notice to proceed issued by the owner, or another stated date, and contract time runs from that date to substantial completion. Owners then usually issue the notice itself on their own letterhead or agency form.
What does NTP mean outside construction?
In contracting generally, NTP still means notice to proceed: the customer's written go-ahead to begin work under a signed contract, common in government, engineering and IT services contracts. In computing, NTP means Network Time Protocol, which keeps clocks in sync and has nothing to do with contracts. Context tells you which one is meant.