Bid bond calculator
Work out the bid bond penal sum the bid documents require, what the owner could recover if you won and walked away, and how risky it is to withdraw your bid at each stage. For the premium on your performance and payment bonds, use the bond premium calculator.
Example inputs: a $4,200,000 bid with a 10% bid bond, a difference-type bond form, and a next-lowest bid of $4,515,000.
How this is calculated
The penal sum comes from the bid documents. What you could owe if you walk away after award depends on the bond form and on how far your bid was below the next one.
Penal sum = bid × required % (capped if the documents set a cap)
= fixed amount (if the documents state one)
= min(20% × bid, $3,000,000) (US federal, FAR 28.101-2)
Owner's loss = max(0, next-lowest bid − your bid) + re-procurement cost
Surety pays = min(penal sum, owner's loss) difference bond
= penal sum forfeiture bond
Above the bond = owner's loss − penal sum difference bond, if positive
Your exposure = surety payment (recovered from you under the indemnity agreement) + above the bondWorked example
A $4,200,000 bid with a 10% bid bond has a $420,000 penal sum. The next bid is $4,515,000, so the gap is $315,000 (7.5% of your bid). With $15,000 to re-procure, the owner’s loss is $330,000, under the penal sum: the surety pays $330,000 and looks to you to repay it. Under a forfeiture form the whole $420,000 would be at stake. On a federal job the same bid needs a guarantee of at least $840,000.
A big gap is a warning
If your bid is well below the next one, check your recap for a dropped line or an extension error before you do anything else. That is exactly the kind of mistake the bid bond rules give relief for, and only if you report it quickly. Our guide to construction bonds covers bid, performance and payment bonds, and the bonding capacity calculator shows whether the job fits your program.
How to calculate a bid bond and the risk of withdrawing
- Enter your bid. Type the total bid price the bond secures.
- Set the bond requirement. Pick a percentage of the bid (5% and 10% are common on public work), a fixed dollar amount from the bid documents, or the US federal rule of at least 20% capped at $3 million.
- Pick the bond form. A difference bond pays the owner’s actual loss up to the penal sum; a forfeiture bond pays the whole penal sum. Read your bond and the instructions to bidders.
- Add the next-lowest bid. Enter the second bid and any re-procurement cost to see what the owner could claim if you walked away after award.
- Check the withdrawal risk. Answer four questions about when and why you might withdraw to see the risk level, the deadline that applies and what to do first.
Bid bond questions
What is a bid bond penal sum?
The most the surety can owe the owner under the bid bond. It is set by the bid documents, usually as a percentage of the bid (5% or 10% is common on state and local work) or a fixed amount. On US federal contracts the bid guarantee must be at least 20% of the bid price, but not more than $3 million (FAR 28.101-2).
How much does a bid bond cost?
Often little or nothing separately for a contractor with an established bond program, because the surety earns its premium on the performance and payment bonds if the bid wins. Some sureties charge a flat fee per bid bond. The penal sum is not the cost. For premium on the final bonds, use the bond premium calculator.
What happens if you win and refuse to sign?
The owner can claim on the bid bond. Under a difference bond the surety pays the extra cost of awarding to the next bidder, up to the penal sum. On federal work the bidder is liable for any cost of acquiring the work above its bid, and the bid guarantee offsets that (FAR 52.228-1). Either way your surety will look to you to repay it under your indemnity agreement.
Will I lose my bid bond if I withdraw my bid?
Usually not before the bid opening deadline, if you withdraw by the method the solicitation allows. After opening, the bid is usually firm for the acceptance period; withdrawal is generally allowed only for a provable clerical mistake reported quickly. The withdrawal check on this page walks through it, and our full article covers the federal rule and state statutes.
Is the surety’s payment the end of it?
No. Contractors sign a general indemnity agreement with their surety, so what the surety pays the owner is normally recovered from the contractor, and the claim can affect your bonding program. Under a difference bond the owner may also pursue losses above the penal sum directly.
Sources
Checked Nov 21, 2026. State deadlines shown are examples summarized from the statute text; other states, cities and owners set their own rules. Re-check the current statute and your solicitation before relying on them.
- FAR 28.101-2: Solicitation provision or contract clause (bid guarantees), Acquisition.gov (checked Nov 21, 2026).Used for: federal bid guarantee: at least 20% of the bid price, not to exceed $3 million.
- FAR 52.228-1: Bid Guarantee, Acquisition.gov (checked Nov 17, 2026).Used for: failure to sign or furnish bonds; liability for excess cost of acquiring the work, offset by the guarantee.
- FAR Part 14 (14.303 modification or withdrawal of bids; 14.407 mistakes in bids), Acquisition.gov (checked Nov 17, 2026).Used for: withdrawal before opening; correction or withdrawal for mistakes after opening.
- Cal. Public Contract Code § 5103, California Legislature (via public.law) (checked Nov 17, 2026).Used for: relief for a mistake in a bid: written notice within 5 working days after opening.
- N.Y. General Municipal Law § 103, New York State Senate (checked Nov 17, 2026).Used for: withdrawal for an arithmetic error or omission: before award or within 3 days after opening.
- 73 P.S. § 1602, Pennsylvania (via FindLaw) (checked Nov 17, 2026).Used for: withdrawal for a clerical error: written claim within 2 business days after opening.
When the spreadsheet version stops scaling
Bonding follows your WIP and your balance sheet.
Your surety prices and sizes your program from your financial statements and work in progress. In os.construction Accounting, WIP is computed from posted job cost, billings and approved forecasts and reviewed before it posts, and vendor bonding capacity is recorded in prequalification.
- WIP snapshots with a calculation trace on every job (live).
- Vendor prequalification questionnaires, including bonding capacity (live).
- Bid packages with award review and a draft commitment from the winning quote (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →