Back charge calculator

Price a back charge the way it survives a dispute: actual cost to correct the work at burdened rates, markup only where the subcontract allows it, a cure period that ended before you started, and a clear split between the current payment and retainage.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link
The back charge
Corrective cost
Trade / workerHoursBase rate $
%
Payroll taxes, insurance and fringe on top of the base rate. Use the labor burden calculator for yours.
$
$
$
If another sub did the fix.
Subcontract terms
%
$
$
Net of retainage.
$

Back chargeLive

Back charge amount
$0
Off this payment
$0
From retainage
$0
Cure period ends
—
Labor (burdened)
$0
LineAmountShare

    Example inputs: 24 hours of carpenter and laborer time at a 35% burden, $640 of material, a $180 lift and a $1,250 firestop invoice, with 10% markup and a $150 fee allowed by the subcontract.

    See it in the app

    Method

    How this is calculated

    A back charge is actual cost plus only what the subcontract allows. The timeline matters as much as the math: notice, then the cure period, then corrective work.

    Labor (base)      = Σ hours × base rate
    Labor burden      = labor (base) × burden %
    Direct cost       = labor + burden + material + equipment + other trade invoice
    Markup            = direct cost × markup %        only if the subcontract allows it
    Back charge       = direct cost + markup + admin fee
    Cure period ends  = notice date + cure days       work should not start before this
    Off this payment  = min(back charge, amount owed this pay app)
    From retainage    = min(remainder, retainage held)

    Worked example

    Sixteen carpenter hours at $48 and eight laborer hours at $32 are $1,024 of base labor; a 35% burden adds $358.40. With $640 of material, a $180 lift and a $1,250 firestop invoice, direct cost is $3,452.40. The subcontract allows 10% markup ($345.24) and a $150 fee, so the back charge is $3,947.64. The sub is owed $2,000 this month, so $2,000 comes off now and $1,947.64 from the $9,500 retainage. Notice went out November 2 with a 2-day cure, so work starting November 5 is after the cure period ended.

    Where back charges fail

    No written notice, work started inside the cure period, markup the subcontract does not allow, and no cost backup. Keep the T&M ticket, photos and daily log for every back charge, and see our article on issuing, disputing and documenting back charges.

    How to calculate a back charge

    1. Record the notice. Enter the date you sent written notice and the cure period the subcontract gives. The tool works out when the cure period ends.
    2. Enter the corrective cost. Hours and base rates for your own forces, the labor burden, material, equipment and any other trade’s invoice for the fix.
    3. Apply the subcontract terms. Tick markup only if the subcontract allows it, and enter the percentage and any administrative fee it sets.
    4. Show where it comes from. Enter what you owe the sub on the current pay app and the retainage you hold, to see how much comes off now and how much from retainage.
    5. Export the backup. Download the CSV for the back charge file, print the summary, and log it in the back charge log.

    Back charge questions

    How do you calculate a back charge?

    Add up what it actually cost to correct the problem: your own labor hours at burdened rates, material, equipment and any other trade you paid, then add markup or an administrative fee only if the subcontract allows it. Keep the T&M tickets, invoices, photos and daily log entries as backup.

    Can I charge markup on a back charge?

    Only if the subcontract gives you the right. Some subcontracts allow a stated percentage for overhead and profit or a flat administrative fee; others allow actual cost only. A markup the contract does not support is the easiest part of a back charge for the sub to dispute.

    Do I have to give notice before back-charging?

    Almost always. Most subcontracts require written notice and an opportunity to cure before you correct the work yourself and charge for it. Starting the work before the cure period ends is the most common reason back charges fail. Read your subcontract’s notice clause.

    Can I take the back charge out of retainage?

    Many subcontracts let you withhold amounts owed under the subcontract from progress payments and retainage, but prompt payment statutes in many states limit what can be withheld and require written notice of the reason. Check your subcontract and your state’s prompt payment law before withholding.

    What is the difference between a back charge and a deductive change order?

    A back charge recovers cost the sub caused. It is usually documented as a deductive change to the subcontract so the revised subcontract amount and the next pay app reflect it.

    Sources

    Checked Nov 21, 2026. Back charge rights, notice periods, markup and withholding come from your subcontract and the law where the job is. General information, not legal advice.

    1. Back charges: how to issue, dispute and document them, os.construction blog (Nov 2026).Used for: notice, cure, cost backup and deduction workflow.
    2. Labor burden calculator, os.construction (Nov 2026).Used for: how to build a burdened labor rate from payroll taxes, insurance and fringe.

    When the spreadsheet version stops scaling

    Put the deduction on the subcontract, not in a spreadsheet.

    In os.construction a back charge is entered as a commitment change order with a negative amount on the sub’s subcontract, so the revised commitment reflects it when the next sub invoice comes in. The daily log, photos and T&M tickets on the same project hold the evidence. There is no dedicated back charge record yet.

    • Commitment change orders with Draft, Pending, Approved, Rejected and Void statuses (live).
    • T&M tickets with labor, material and equipment lines (live).
    • Daily log and photos on the same project record (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file