Back charge calculator
Price a back charge the way it survives a dispute: actual cost to correct the work at burdened rates, markup only where the subcontract allows it, a cure period that ended before you started, and a clear split between the current payment and retainage.
Example inputs: 24 hours of carpenter and laborer time at a 35% burden, $640 of material, a $180 lift and a $1,250 firestop invoice, with 10% markup and a $150 fee allowed by the subcontract.
How this is calculated
A back charge is actual cost plus only what the subcontract allows. The timeline matters as much as the math: notice, then the cure period, then corrective work.
Labor (base) = Σ hours × base rate Labor burden = labor (base) × burden % Direct cost = labor + burden + material + equipment + other trade invoice Markup = direct cost × markup % only if the subcontract allows it Back charge = direct cost + markup + admin fee Cure period ends = notice date + cure days work should not start before this Off this payment = min(back charge, amount owed this pay app) From retainage = min(remainder, retainage held)
Worked example
Sixteen carpenter hours at $48 and eight laborer hours at $32 are $1,024 of base labor; a 35% burden adds $358.40. With $640 of material, a $180 lift and a $1,250 firestop invoice, direct cost is $3,452.40. The subcontract allows 10% markup ($345.24) and a $150 fee, so the back charge is $3,947.64. The sub is owed $2,000 this month, so $2,000 comes off now and $1,947.64 from the $9,500 retainage. Notice went out November 2 with a 2-day cure, so work starting November 5 is after the cure period ended.
Where back charges fail
No written notice, work started inside the cure period, markup the subcontract does not allow, and no cost backup. Keep the T&M ticket, photos and daily log for every back charge, and see our article on issuing, disputing and documenting back charges.
How to calculate a back charge
- Record the notice. Enter the date you sent written notice and the cure period the subcontract gives. The tool works out when the cure period ends.
- Enter the corrective cost. Hours and base rates for your own forces, the labor burden, material, equipment and any other trade’s invoice for the fix.
- Apply the subcontract terms. Tick markup only if the subcontract allows it, and enter the percentage and any administrative fee it sets.
- Show where it comes from. Enter what you owe the sub on the current pay app and the retainage you hold, to see how much comes off now and how much from retainage.
- Export the backup. Download the CSV for the back charge file, print the summary, and log it in the back charge log.
Back charge questions
How do you calculate a back charge?
Add up what it actually cost to correct the problem: your own labor hours at burdened rates, material, equipment and any other trade you paid, then add markup or an administrative fee only if the subcontract allows it. Keep the T&M tickets, invoices, photos and daily log entries as backup.
Can I charge markup on a back charge?
Only if the subcontract gives you the right. Some subcontracts allow a stated percentage for overhead and profit or a flat administrative fee; others allow actual cost only. A markup the contract does not support is the easiest part of a back charge for the sub to dispute.
Do I have to give notice before back-charging?
Almost always. Most subcontracts require written notice and an opportunity to cure before you correct the work yourself and charge for it. Starting the work before the cure period ends is the most common reason back charges fail. Read your subcontract’s notice clause.
Can I take the back charge out of retainage?
Many subcontracts let you withhold amounts owed under the subcontract from progress payments and retainage, but prompt payment statutes in many states limit what can be withheld and require written notice of the reason. Check your subcontract and your state’s prompt payment law before withholding.
What is the difference between a back charge and a deductive change order?
A back charge recovers cost the sub caused. It is usually documented as a deductive change to the subcontract so the revised subcontract amount and the next pay app reflect it.
Sources
Checked Nov 21, 2026. Back charge rights, notice periods, markup and withholding come from your subcontract and the law where the job is. General information, not legal advice.
- Back charges: how to issue, dispute and document them, os.construction blog (Nov 2026).Used for: notice, cure, cost backup and deduction workflow.
- Labor burden calculator, os.construction (Nov 2026).Used for: how to build a burdened labor rate from payroll taxes, insurance and fringe.
When the spreadsheet version stops scaling
Put the deduction on the subcontract, not in a spreadsheet.
In os.construction a back charge is entered as a commitment change order with a negative amount on the sub’s subcontract, so the revised commitment reflects it when the next sub invoice comes in. The daily log, photos and T&M tickets on the same project hold the evidence. There is no dedicated back charge record yet.
- Commitment change orders with Draft, Pending, Approved, Rejected and Void statuses (live).
- T&M tickets with labor, material and equipment lines (live).
- Daily log and photos on the same project record (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →