Back charge notice
Written notice to a subcontractor or supplier: what happened, the clause, the cure period, and what you will charge if it isn't cured.
Free template
1 · What happened
Describe the condition: what is damaged, defective, incomplete or left uncleaned, and why it is this party's responsibility.
Attached
2 · Contract basis
3 · What you need to do
Corrective action required
If the condition is not corrected by the date above, or you do not respond in writing, we will correct it with our own forces or others and charge the cost to your subcontract as a back charge, as the subcontract allows. If the condition is an emergency affecting safety or other work, we may act immediately and will document the cost.
4 · Cost if not cured
Fill in after correction. Attach signed T&M tickets, invoices or time records for every line.
| Cost element | Backup (ticket / invoice #) | Amount |
|---|---|---|
| Labor (own forces or another trade) | ||
| Material | ||
| Equipment | ||
| Other trade invoice | ||
| Subtotal: cost | ||
| Markup ( ____ %, only if the subcontract allows) | ||
| Total back charge |
Before you deduct, check: the clause is cited; notice went out by the method the subcontract requires and the date is logged; the cure period ran out (or the emergency is documented); photos and the daily log show who was working there; cost is backed by signed tickets or invoices; a deductive subcontract change is entered so the commitment and retainage stay in line; and the withholding fits your state's prompt payment rules.
5 · Subcontractor response
General information, not legal advice. Use your subcontract's notice method, cure period and dispute process; back charge rights and withholding limits vary by contract and state. Log every notice on the back charge log.