Back charge notice

Written notice to a subcontractor or supplier: what happened, the clause, the cure period, and what you will charge if it isn't cured.

os.construction
Free template
Project
Job #
Back charge #
Date of notice
To (subcontractor / supplier)
Subcontract / PO #
From (contractor)
Sent by (method)

1 · What happened

Date observed
Observed by
Location (level, room, grid)
Daily log date / ref

Describe the condition: what is damaged, defective, incomplete or left uncleaned, and why it is this party's responsibility.

Damage to others' workDefective or nonconforming workCleanup / debrisFailure to perform or man the jobSafety violationOther

Attached

Photos ( ___ )Daily log extractInspection or test reportDrawings / spec referenceCorrespondence

2 · Contract basis

Subcontract clause(s)
Cure period in subcontract

3 · What you need to do

Corrective action required

Start by (date / time)
Complete by (date / time)

If the condition is not corrected by the date above, or you do not respond in writing, we will correct it with our own forces or others and charge the cost to your subcontract as a back charge, as the subcontract allows. If the condition is an emergency affecting safety or other work, we may act immediately and will document the cost.

4 · Cost if not cured

Fill in after correction. Attach signed T&M tickets, invoices or time records for every line.

Cost elementBackup (ticket / invoice #)Amount
Labor (own forces or another trade)
Material
Equipment
Other trade invoice
Subtotal: cost
Markup ( ____ %, only if the subcontract allows)
Total back charge
Deductive change / CCO #
To be deducted from (pay app #)

Before you deduct, check: the clause is cited; notice went out by the method the subcontract requires and the date is logged; the cure period ran out (or the emergency is documented); photos and the daily log show who was working there; cost is backed by signed tickets or invoices; a deductive subcontract change is entered so the commitment and retainage stay in line; and the withholding fits your state's prompt payment rules.

5 · Subcontractor response

Will correct by the date aboveAgree to the back chargeDispute (reasons below or attached)
ContractorSignatureName, title, date
Subcontractor / supplierSignatureName, title, date
ReceivedMethod and dateEmail, delivery, certified mail

General information, not legal advice. Use your subcontract's notice method, cure period and dispute process; back charge rights and withholding limits vary by contract and state. Log every notice on the back charge log.

Template from os.construction/resources/templates/back-charge-log. Free to use and adapt.Your subcontract and local law govern.