Back charges that survive the dispute.
Notice first, cost second, deduction last. Send the notice the day you find the problem, then log each back charge through cure, cost backup, the deductive subcontract change and the pay app it comes off.
Back charge notice and log
os.construction · free template- Project
- Contract / job #
- Log kept by
- Last updated
Back charge log
| BC # | Date found | Sub / supplier | Subcontract # | Description and location | Subcontract clause | Notice sent | Cure period | Cured? | Cost backup | Amount | Sub response | Deductive change # | Deducted on | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| BC-007 | Drywall sub | SC-09 | Ductwork damaged at L2 corridor, grid C-4 (SAMPLE · delete this row) | Subcontract damage and cleanup clause | 48 hours | No | T&M ticket 0418, photos, daily log | 3850 | Disputed, then accepted | CCO-09-03 | Pay app #7 | Deducted | ||
| BC-008 | Concrete sub | SC-03 | Washout left in stair 2 pit | Subcontract cleanup clause | 24 hours | Yes | 0 | Cured, no charge | ||||||
| BC-009 | Electrical sub | SC-14 | Firestopping removed at 3 penetrations, L3 | Subcontract correction of work clause | 5 days | No | Firestop sub invoice, photos | Response due | Noticed | |||||
Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/back-charge-log
Using the back charge notice and log
- Use the printable back charge notice the day you find the problem. Cite the subcontract clause, describe what happened and where, attach photos and set the cure period the subcontract gives.
- Log the notice the same day: BC number, sub, clause, notice date and cure period. Disputes usually start with those dates.
- If the sub cures, close the line with no charge. That is the best outcome.
- If it doesn’t, correct the work with your own forces or another trade and track the cost on its own T&M ticket or cost code. Markup only if the subcontract allows it.
- Send the back charge with the cost backup, enter a deductive change on the sub’s subcontract, and note which pay app it comes off. Check that the withholding fits your state’s prompt payment rules.
- Review open lines at every pay app and before closeout, so nothing is left to argue about at final payment.
- Problem foundPhotos, daily log, location
- Written noticeClause cited, cure period set
- Cure periodSub fixes it or doesn’tCured: no charge: back to “Problem found”
- GC corrects itCost tracked on a ticket
- Back charge issuedCost backup attached
- Deductive changeOff the next pay app
Text version
- Problem found: Photos, daily log, location
- Written notice: Clause cited, cure period set
- Cure period: Sub fixes it or doesn’t
- GC corrects it: Cost tracked on a ticket
- Back charge issued: Cost backup attached
- Deductive change: Off the next pay app
Cured: no charge: from “Cure period” back to “Problem found”.
Do this in os.construction instead of a spreadsheet
In os.construction a back charge is entered as a commitment change order on the subcontract: a title, cost code and negative amount, with Draft, Pending, Approved, Rejected or Void statuses, so the revised commitment reflects it when the next sub invoice comes in. The daily log, photos and T&M tickets hold the evidence. There is no dedicated back charge record yet, so keep this log alongside the commitment.
Try it on the sample project
Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.
Questions about the back charge notice and log
What is a back charge in construction?
A deduction a contractor takes from what it owes a subcontractor or supplier to recover cost that party caused: damage, defective work, skipped cleanup or work finished after they failed to perform. It is usually documented as a deductive change to the subcontract.
What should a back charge notice include?
The subcontract clause that gives the right, what happened, where and when, photos, what the sub must do and by when, what happens if it doesn’t, and a contact. Send it the way the subcontract requires and log the date.
Can I add markup to a back charge?
Only if the subcontract allows it. Some subcontracts allow a stated percentage for overhead or administration; others allow actual cost only. A markup the contract doesn’t support is an easy point for the sub to dispute.
How does a back charge show in os.construction?
As a commitment change order with a negative amount on the sub’s subcontract, so the revised contract amount reflects it. The supporting daily log entries, photos and T&M tickets stay on the same project.
Is this template legal advice?
No. Back charge rights, notice periods and withholding limits come from your subcontract and the law where the job is. Use the template as a working aid and get advice on disputed or large charges.
Keep going
- GlossaryBack charge
- GlossaryCommitment
- GlossaryDaily Log
- GlossaryRetainage
- GlossarySubcontract
- GlossaryTime and Materials Ticket (T&M Ticket)
- Free resourceBack charge calculator
- Free resourcePrintable back charge notice
- Free resourceBack charges: issue, dispute and document
- Free resourceT&M ticket template
- TemplatePunch list template
- TemplateMeeting minutes template
- TemplateInspection checklist starter pack
- TemplateT&M ticket template
- TemplateRFI writing checklist
- TemplateDaily log checklist
- TemplateChange event log
- TemplateThree-week look-ahead template
- TemplateSafety observation log
- TemplateAction item tracker
- TemplateCloseout and TCO checklist
- TemplateNotice to proceed template
- TemplateJob cost report template
- TemplateConstruction schedule (Gantt) template
- TemplateChange order log template
- TemplateBid tabulation and leveling template
- TemplateCash flow projection template
- TemplateBuyout log template
- TemplateASI log template
Keep exploring
Related across os.construction
- Free toolBack charge calculatorBurdened cost, allowed markup, notice and cure dates, and the payment offset.
- BlogBack charges: how to issue, dispute and document themA back charge is a deduction a contractor takes from a subcontractor or supplier for cost they caused. It sticks when the subcontract allows it, notice and a chance to cure came first, and the cost is documented. Here is how to issue one, how to dispute one, and the paper trail both sides need.
- DocsSubcontracts and commitment changesHow subcontracts and purchase orders are structured, how commitment change orders follow owner changes, and how sub invoices, retainage and compliance are checked against the commitment.
- PlatformRole guide: SuperintendentA superintendent’s week in os.construction.
- Free toolDaily log checklistFree daily report checklist for superintendents.
- ExplainerFrom the field to the invoice: daily log → T&M ticket → priced change (video)An 8-minute walkthrough with real os.construction screens: log the crew, write and sign a T&M ticket at cost, review it against the log, then carry it into a change event and PCO.