# Back charge notice and log

**Project:** ______________________  
**Contract / job #:** ______________________  
**Log kept by:** ______________________  
**Last updated:** ______________________  

## Back charge log

| BC # | Date found | Sub / supplier | Subcontract # | Description and location | Subcontract clause | Notice sent | Cure period | Cured? | Cost backup | Amount | Sub response | Deductive change # | Deducted on | Status |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| BC-007 |   | Drywall sub | SC-09 | Ductwork damaged at L2 corridor, grid C-4 (SAMPLE · delete this row) | Subcontract damage and cleanup clause |   | 48 hours | No | T&M ticket 0418, photos, daily log | 3850 | Disputed, then accepted | CCO-09-03 | Pay app #7 | Deducted |
| BC-008 |   | Concrete sub | SC-03 | Washout left in stair 2 pit | Subcontract cleanup clause |   | 24 hours | Yes |   | 0 |   |   |   | Cured, no charge |
| BC-009 |   | Electrical sub | SC-14 | Firestopping removed at 3 penetrations, L3 | Subcontract correction of work clause |   | 5 days | No | Firestop sub invoice, photos |   | Response due |   |   | Noticed |
|   |   |   |   |   |   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |   |   |   |   |   |

## How to use it

1. Use the printable back charge notice the day you find the problem. Cite the subcontract clause, describe what happened and where, attach photos and set the cure period the subcontract gives.
2. Log the notice the same day: BC number, sub, clause, notice date and cure period. Disputes usually start with those dates.
3. If the sub cures, close the line with no charge. That is the best outcome.
4. If it doesn’t, correct the work with your own forces or another trade and track the cost on its own T&M ticket or cost code. Markup only if the subcontract allows it.
5. Send the back charge with the cost backup, enter a deductive change on the sub’s subcontract, and note which pay app it comes off. Check that the withholding fits your state’s prompt payment rules.
6. Review open lines at every pay app and before closeout, so nothing is left to argue about at final payment.

Template by os.construction: https://os.construction/resources/templates/back-charge-log. Sample rows are illustrative; your contract and specifications govern.