Esc

↑↓ move↵ openIndex · Pagefind
Accounting

Back charge

Definition

A charge a contractor issues to a subcontractor or supplier for costs it incurred because of their defective work, damage, cleanup or failure to perform.

Part of: From RFI to change order: ASI, field order, CCD and CO

Topic: Changes & claims

Updated

Back charge process from notice to deductionSteps: damage or default is observed and documented with photos and the daily log. Written notice goes to the subcontractor citing the clause and cure period. The subcontractor has an opportunity to cure; if it cures, there is no back charge. If not, the general contractor corrects the work and tracks the cost on a T&M ticket or separate cost code. The back charge is issued with backup, entered as a deductive subcontract change, and deducted from the next pay application or settled against retainage at closeout.1 Damage or default seenphotos, daily log, who was there2 Written notice to subcite clause, set cure period3 Opportunity to curesub fixes it, or doesn’t4 GC corrects itT&M ticket or own cost code5 Back charge issuedcost + notice + backup attached6 Deductive sub changecommitment, retainage stay in sync7 Deducted from pay appor against retainage at closeoutCuredno chargeExample: $3,850 repair → $3,850 deduction
Notice and a chance to cure come first. Documented cost and a deductive subcontract change make the deduction stick.

A back charge (or backcharge) is a cost a general contractor deducts from what it owes a subcontractor or supplier, to recover money it spent because of them: repairing damage they caused, correcting defective work, doing cleanup they skipped, or finishing work after they failed to perform. Most subcontracts require written notice and a chance to cure first.

Free template: the back charge notice and log (printable notice plus a CSV log). For the full process, see back charges: how to issue, dispute and document them.

In plain English

Illustrative: your painter’s lift gouges a finished storefront frame. You email the painter the same afternoon with photos and give them two days to fix it, as the subcontract allows. They don’t. The glazier repairs it for $1,200 in labor and $400 in parts, $1,600 total. You issue a $1,600 back charge, reduce the painter’s subcontract by $1,600, and pay their next invoice $1,600 lighter. The painter pays for the damage; you don’t eat it.

Back charges run downhill. An owner can make a similar deduction from a prime contractor, and a subcontractor can back charge its own sub-subcontractors or suppliers under the same kinds of terms.

How it works

  1. The problem is observed and documented. Photos, the daily log entry, the location and who was working there.
  2. Written notice to the responsible party. The notice should cite the subcontract clause, describe the problem and set the time to cure.
  3. Opportunity to cure. The sub fixes it, and there’s no back charge. This is the outcome everyone should want.
  4. If it isn’t cured, the GC corrects it with its own forces or another sub, tracking cost on a T&M ticket or separate cost code.
  5. The back charge is issued with the costs and backup, and usually entered as a deductive change to the subcontract.
  6. It is deducted from a payment, typically the sub’s next pay application, or settled at closeout against retainage.

Emergencies are the exception: when damage threatens safety or other work, most subcontracts let the GC act immediately and give notice right after.

What makes a back charge stick

Evidence Why it matters
Subcontract clause Shows the right to charge and the required process
Dated written notice Proves the sub was told and had a chance to cure
Photos and daily log Shows the condition, location and who caused it
Signed T&M tickets or invoices Proves the cost was real and reasonable
Deductive subcontract change Keeps commitment, retainage and AP in sync

Writing the notice

A good back charge notice is short, specific and sent fast. Include:

  • The subcontract clause that gives the right to charge.
  • What happened, where and when, with photos attached.
  • What you need the sub to do and by when, matching the cure period in the subcontract.
  • What you will do if it isn’t done, and that costs will be charged back.
  • Who to contact.

Send it the way the subcontract requires, usually email plus a copy to the sub’s office. Log the notice date: if the matter turns into a dispute, that date and the cure period are often the first things anyone checks.

Back charge vs change order vs offset

Back charge Change order General offset
Direction Reduces what you owe the sub Usually adds to it Reduces payment
Cause Sub caused a cost Scope changed Any amount owed, possibly from another job
Needs Notice, cure, cost backup Agreement on price and time Express contract right, often limited by law

Who is responsible

  • GC project team: spots the issue, sends notice, documents cost. The superintendent’s daily log is often the deciding evidence.
  • Subcontractor: responds to notice, cures or disputes in writing.
  • Project accounting: applies the deduction to the right commitment and pay app, not as an unexplained short payment.

Why it matters

Back charges are one of the main ways a GC recovers margin that leaked because of someone else’s problem. They’re also one of the most disputed items in construction. Without timely notice, photos, daily logs, labor and material tickets, a back charge is a negotiating position, not a recovery. Sloppy back charges damage subcontractor relationships and often get dropped at closeout. Prompt payment statutes in many states also restrict withholding to amounts that are documented and noticed, so a casual deduction can backfire.

Worked example

Illustrative: on Riverside Medical Center, a drywall sub’s crew damages installed ductwork. The GC sends written notice the same day with photos, giving the drywall sub 48 hours under the subcontract to repair or agree to costs. The drywall sub declines, so the GC has the mechanical sub repair it on a T&M ticket for $3,850. The GC issues a $3,850 back charge to the drywall sub that references the notice, the ticket and the daily log entry, enters a deductive subcontract change order for $3,850, and deducts it from the sub’s next pay app.

Common mistakes

  • Issuing back charges months later, without the notice the subcontract requires.
  • No supporting documentation, such as daily log entries, photos or signed tickets.
  • Deducting the money without reducing the subcontract value, so commitments and retainage get out of sync.
  • Adding large markups the subcontract doesn’t allow.
  • Back charging for damage when several trades were in the area and there’s no evidence of who caused it.

This is general information, not legal advice. Back charge rights and withholding limits vary by state and subcontract.

How os.construction handles it

Today the evidence lives in the app: the Daily Log and photos record what happened, T&M tickets capture repair labor, equipment and material with a sign-off, and a back charge is entered as a commitment change order directly on the sub’s commitment, so the revised commitment and the next sub invoice stay in line. A dedicated back charge record that ties all of these together is in development.

Watch the explainer · 2:48

Back charges explained: notice, cure and evidence

  1. 0:00What a back charge is
  2. 0:17Who charges whom
  3. 0:36Notice and cure
  4. 1:00Five pieces of evidence
  5. 1:20An illustrative back charge
  6. 1:40Applying the deduction
  7. 2:00Why back charges fail
  8. 2:25Back charges in os.construction
Read the transcript

A back charge is a cost a general contractor deducts from what it owes a subcontractor or supplier. It recovers money the GC spent because of them: repairing damage they caused, fixing defective work, cleanup they skipped, or finishing work after they failed to perform.

Back charges run downhill. An owner can make a similar deduction from the prime contractor, the GC can back charge its subs, and a sub can back charge its own sub-subcontractors and suppliers. In every case the right comes from the contract, so the subcontract clause is the starting point.

Most subcontracts require written notice and a chance to cure before the GC can fix the problem and charge for it. The notice cites the clause, says what happened and where, attaches photos, and sets the cure period. If the sub fixes it, there's no back charge, which is the outcome everyone should want. Emergencies that threaten safety can be handled first, with notice right after.

If it isn't cured, the GC corrects the work and documents the cost. A back charge holds up with five pieces of evidence: the subcontract clause, a dated written notice, photos and the daily log showing who was working there, signed time and materials tickets or invoices, and a deductive subcontract change.

Here's an illustrative example. A drywall crew damages installed ductwork. The GC sends notice the same day with photos, giving forty-eight hours to repair under the subcontract. The drywall sub declines, so the mechanical sub repairs it on a time and materials ticket for three thousand eight hundred fifty dollars.

The GC issues a three thousand eight hundred fifty dollar back charge that references the notice, the ticket and the daily log. It enters a deductive change to the drywall subcontract, so the commitment and retainage stay correct, and deducts it from the sub's next pay app. An unexplained short payment invites a dispute.

Back charges are among the most disputed items in construction. They fall apart when they're issued months later without notice, when there's no backup, when markups exceed what the subcontract allows, or when several trades were in the area and nobody can show who did it. Prompt payment laws in many states also limit withholding. Rules vary by state and contract; this is general information, not legal advice.

In os.construction, the daily log and photos record what happened, time and materials tickets capture the repair labor, equipment and material with a sign-off, and the back charge is entered as a commitment change order on the sub's commitment, so the revised commitment and the next invoice line up.

FAQ

What does back charge mean in construction?

A back charge is a deduction a contractor takes from what it owes a subcontractor or supplier to recover costs it incurred because of that party: repairing damage they caused, correcting defective work, cleanup they didn't do, or finishing work after they failed to perform. It is usually applied as a deductive change to the subcontract and taken from a later payment.

Is a backcharge legal?

Back charges are generally enforceable when the subcontract allows them and the contractor follows its terms, which usually means written notice, a chance to cure, and reasonable, documented costs. Without those steps a back charge is easy to dispute. Some states also limit withholding from payments through prompt payment laws, so rules vary by state and contract.

How do you dispute a back charge?

Respond in writing within the time the subcontract allows. Ask for the notice, photos, daily logs and cost records behind it, and point out any missing notice or opportunity to cure. Show your own evidence, such as who was working in the area. Follow the subcontract's dispute process, and keep working while it is resolved unless the contract says otherwise.

What is the difference between a back charge and a change order?

A change order adjusts the contract for changed scope, usually adding money for extra work. A back charge reduces what's owed because the subcontractor caused a cost. Back charges are often documented as deductive subcontract change orders, so the subcontract value, retainage and remaining commitment stay correct.

How much notice is needed before a back charge?

Whatever the subcontract says. Many subcontracts require written notice and a short cure period, often stated in days, before the contractor can do the work itself and charge it back. Emergencies affecting safety or other trades may allow immediate action with notice right after. Prime contracts often contain a similar owner right, such as a 10-day notice in AIA A201-2017.

Is it backcharge or back charge?

Both spellings mean the same thing. "Back charge" (two words) and "backcharge" (one word) are used interchangeably in subcontracts, accounting systems and industry writing, and you will also see "back-charge" and "charge-back." What matters is how your subcontract defines the right to charge and the process for it, not the spelling.

What should a back charge template include?

At minimum: the subcontract and clause relied on, a description of the problem with date, location and photos, the date notice was sent and the cure deadline, the corrective work done and by whom, an itemized cost (labor hours and rates, material, equipment, any allowed markup) with tickets attached, and a signature line for the subcontractor to accept or dispute. Log each one so it can be matched to a deductive subcontract change.

Sources

Open file