Esc

↑↓ move↵ openIndex · Pagefind
Analytics

Backlog

Definition

Contracted revenue not yet earned: the work a contractor has signed but not yet performed.

Topic: Accounting & WIP · Preconstruction & bidding

Updated

Backlog roll-forward for one quarterA waterfall chart. Opening backlog of 99 million dollars rises by 12 million of new contracts and 1.5 million of approved change orders, then falls by 22.5 million of revenue earned, leaving closing backlog of 90 million dollars.99+12+1.5−22.590OpenNewCOsEarnedClose$M, one quarter
Illustrative. Earned revenue outran new work, so backlog fell from $99.0M to $90.0M.

Backlog is the total value of signed work you haven’t yet earned. For a job in progress, backlog equals current contract value minus earned revenue to date. For the company, it’s the sum across all open jobs plus signed jobs not yet started. Some companies track “gross profit in backlog” too: the projected profit still to be recognized.

How it works

  1. Define what counts. Most contractors count only executed contracts and approved change orders. Verbal awards and unsigned letters of intent stay in the pipeline.
  2. Per job. Backlog = current contract value − earned revenue to date. Earned revenue comes from the WIP schedule, not from billings.
  3. Gross profit in backlog. Projected gross profit at completion − gross profit earned to date.
  4. Company total. Add every open job and every signed job not yet started.
  5. Roll forward. Opening backlog + new contracts + approved changes − revenue earned = closing backlog.
  6. Months on hand. Divide backlog by average monthly earned revenue to estimate how long the work lasts at the current pace.
  7. Book-to-bill. New work added divided by revenue earned in the same period. Above 1.0, backlog is growing; below 1.0, it’s shrinking.

Worked example

Illustrative: Riverside Medical Center has a $49.3M contract and $35.78M earned to date.

  • Job backlog: $49.3M minus $35.78M = $13.52M
  • Gross profit in backlog at 11.4%: about $1.54M

If the 14-job portfolio has $90M in total backlog and the company earns about $7.5M a month, that’s roughly 12 months of work on hand. Three fading jobs would shrink the gross profit in that backlog even if the revenue figure stays the same.

The quarter’s roll-forward for the same portfolio (sample data):

Line Amount
Opening backlog $99.0M
New contracts signed $12.0M
Approved change orders $1.5M
Revenue earned in the quarter (3 × $7.5M) −$22.5M
Closing backlog $90.0M

Book-to-bill for the quarter is ($12.0M + $1.5M) ÷ $22.5M = 0.60. Backlog fell $9.0M, so unless awards pick up, months on hand will keep falling.

Reading backlog beyond the headline number

The total is only the start. Three further checks make it more useful:

  • Profit coverage. If the $90M backlog carries an average 10% projected margin, gross profit in backlog is $9.0M. Against company overhead of $0.9M a month, that covers 10 months, two fewer than the 12 months of revenue on hand.
  • Concentration. Riverside’s $13.52M is 15% of the $90M total. A dispute or suspension on one large job moves the whole picture.
  • Timing. A job signed today that won’t start for six months adds to backlog but not to next quarter’s revenue. Spread backlog by expected month of earning, not just as one total.
Measure What it includes Certainty
Backlog Signed contract value not yet earned Contracted
Gross profit in backlog Projected profit on that work Contracted, but forecast-dependent
Pipeline Bids and pursuits, often weighted by odds Not contracted
Remaining performance obligations ASC 606 / IFRS 15 term for unsatisfied obligations Contracted, by accounting rules
Billings in excess / under-billing Timing gap between billings and earned revenue Not backlog

Why it matters

Backlog tells you how many months of work you have lined up and whether you can cover overhead next year. It drives hiring, equipment purchases and bidding decisions. Sureties look at backlog against working capital and equity when setting bonding capacity, because a contractor can take on more work than its balance sheet can support.

Too little backlog means overhead won’t be covered. Too much, especially at thin margins, can stretch cash, staff and bonding capacity at the same time.

Backlog figures given to sureties, banks or investors should come with their definition: whether they include signed but unstarted work, unpriced change orders or letters of intent, and the date they were measured. Companies reporting under ASC 606 or IFRS 15 may also disclose remaining performance obligations, which follow the accounting standard’s rules and can differ from internal backlog.

Common mistakes

  • Counting verbal awards or unsigned LOIs as backlog.
  • Reporting revenue backlog without the gross profit in it. Low-margin backlog can be a trap.
  • Using billed to date instead of earned revenue, which distorts backlog by the amount of over or under billing.
  • Leaving cancelled or descoped work in backlog after the change is agreed.
  • Counting pending change orders at full value before they’re approved.
  • Dividing by a historical monthly run rate when the crews and project mix are changing.

How os.construction handles it

The Accounting reports include a backlog roll-forward from posted WIP rows: opening backlog plus awards and changes, less earned revenue, equals closing backlog. Signed work not yet included in a posted snapshot is outside that report. See the accounting guide.

FAQ

How do you calculate construction backlog?

For each job, take the current contract value including approved change orders and subtract revenue earned to date. Add those amounts across all open jobs, then add the full value of signed contracts that haven't started. The total is company backlog.

What is a backlog roll-forward?

It's a reconciliation from one date to the next: opening backlog, plus new contracts and approved changes, less revenue earned in the period, equals closing backlog. It shows whether the company is replacing the work it burns off.

What is gross profit in backlog?

It's the projected gross profit still to be recognized on signed work. For a job in progress, it's projected gross profit at completion less gross profit earned to date. It shows whether backlog is worth having, not just how big it is.

Why do sureties care about backlog?

Backlog is work the contractor has promised to finish, and some of it is bonded. Sureties compare it with working capital, equity and past performance to judge whether the contractor can complete it, which affects bonding capacity.

Is backlog the same as remaining performance obligations?

They're close. Remaining performance obligations is the term ASC 606 and IFRS 15 use for the transaction price allocated to obligations not yet satisfied, which some companies disclose. Internal backlog definitions vary, for example in how they treat unpriced change orders or signed letters of intent.

Sources

Open file