Preconstruction, estimating, bidding and buyout
Preconstruction turns drawings into a price and a plan: quantity takeoff, estimating, risk and contingency, subcontractor prequalification and bid leveling, then buyout once the job is won.
The sales side has its own vocabulary too. Pipeline value, weighted pipeline, win rate and quote hit rate tell a contractor whether there is enough work coming to keep crews busy.
Preconstruction & bidding: terms defined
Preconstruction
The planning phase before construction starts, when the builder estimates, prices, sequences and buys out the work so the project can be built for the budget and schedule the owner expects.
Project managementTakeoff
The process of measuring and counting quantities of materials and work from drawings to build an estimate.
AccountingCSI MasterFormat
The Construction Specifications Institute's standard numbering system that organizes specifications into divisions like 03 Concrete and 26 Electrical.
Project managementThree-Point Estimate
An activity duration given as optimistic, most likely and pessimistic values, used to describe uncertainty for schedule risk analysis.
Project managementRisk Register
A list of identified project risk events, each with an owner, probability, impact and mitigation, that can feed a quantitative schedule risk analysis.
Project managementValue Engineering (VE)
A structured review of a design to lower cost or improve value without reducing required function, quality or performance.
ContractsRFP vs. RFQ
An RFQ asks contractors to submit qualifications so the owner can shortlist; an RFP asks for a proposal with approach and often price. In trade buying, RFQ can also mean request for quotation.
Project managementPrequalification
Screening contractors or subcontractors on safety, finances, experience and capacity before they're allowed to bid.
ContractsBid Bond
A surety bond submitted with a bid that guarantees the bidder will sign the contract and provide performance and payment bonds if awarded.
Project managementBid Leveling
Comparing subcontractor bids line by line, adjusting for scope gaps and exclusions, so they can be judged on equal terms.
Project managementBuyout
The process after award of turning the estimate into signed subcontracts and purchase orders, locking in actual costs and scope for each trade.
AccountingBuyout Savings
The difference between a trade's budgeted cost and the actual amount committed at buyout, positive when the subcontract or PO comes in under budget.
AnalyticsPipeline Value
The total estimated value of every open pursuit: work you're chasing that hasn't been won or lost yet.
AnalyticsWeighted Pipeline
The sum of each open pursuit's estimated value multiplied by its probability of winning: a probability-weighted forecast of new work.
AnalyticsWin Rate
Pursuits won divided by pursuits decided (won plus lost). Open pursuits are left out.
AnalyticsQuote Hit Rate
Of the quotes a vendor submits, the share that win: quotes awarded divided by quotes received.
AnalyticsLead Conversion Rate
The share of incoming inquiries that become real pursuits: inquiries converted to an opportunity divided by inquiries received.
AnalyticsAverage Deal Size
Total value of won pursuits divided by the number won: the typical size of the work you actually land.
AnalyticsSales Cycle
How long a pursuit takes from first entry to a win, averaged over won pursuits.
AnalyticsBacklog
Contracted revenue not yet earned: the work a contractor has signed but not yet performed.
Tools, templates and guides
Lessons and videos
Articles
- Direct vs indirect costs in construction: job cost, general conditions and overhead Nov 18, 2026
- Hard costs vs soft costs in construction: what goes where, and why it matters Nov 18, 2026
- How to build a construction estimate from scratch: from takeoff to bid price Nov 18, 2026
- How to calculate general conditions costs: build them from the schedule, not a percentage Nov 18, 2026
- How to calculate construction overhead and markup for a bid Nov 18, 2026
- How to level subcontractor bids: building a bid tab that compares the same scope Nov 18, 2026
- How to price a change order: labor, material, subs and markup, worked line by line Nov 18, 2026
- How to run a construction buyout: buy-by dates, a buyout log and where the savings go Nov 18, 2026
- Construction job costing: how to set up cost codes Nov 18, 2026