- Step 1: Read the bid documents before you measure anything
- Step 2: Set up the estimate on your cost codes
- Step 3: Take off quantities
- Step 4: Price self-performed labor
- Step 5: Price material and equipment
- Step 6: Get subcontractor quotes and level them
- Step 7: Build general conditions from the schedule
- Step 8: Add contingency for the risk that’s left
- Step 9: Apply overhead and profit, then insurance and bond
- Step 10: Review, qualify and check against history
- Worked example: a 6,000 square foot office tenant improvement
- Common mistakes
- How os.construction handles it
- FAQ
To build a construction estimate, work in layers: take off quantities from the drawings, price direct cost line by line (labor at the fully burdened rate, material with tax and waste, equipment, and leveled subcontractor quotes), build general conditions from the schedule, add contingency for the risk you can name, apply your overhead and profit markup, and add insurance and bond on the total. Each layer has its own base, and mixing them up is how bids go out too low.
An estimate is a model of the job you haven’t built yet. If it’s organized the way the job will be run, on the same cost codes the budget will use, it becomes the budget on the day you win and the yardstick for every month after. If it lives in a one-off spreadsheet with its own structure, someone re-keys it at award and the link between what you bid and what you spend is gone.
Step 1: Read the bid documents before you measure anything
Collect the drawings, specifications, addenda, the bid form and the bid instructions. Note:
- What the bid form asks for: a lump sum, unit prices, alternates, allowances, a breakdown.
- The contract form and any unusual terms, such as liquidated damages, retainage or payment terms that affect cost and cash.
- Bond and insurance requirements. A bid bond, a performance and payment bond on award, builder’s risk, any project-specific coverage.
- The schedule, or the duration you’ll have to commit to. General conditions depend on it.
- Owner-furnished items and work by others, so you don’t price them twice or not at all.
Then make a list of every specification section and who carries it: you, a named trade package, the owner or nobody. That list is your first check for scope gaps.
Step 2: Set up the estimate on your cost codes
Use the same codes you’ll use to track cost, usually built on CSI MasterFormat divisions or your own list, with cost types for labor, material, equipment, subcontract and other. Add general conditions as their own codes. The estimate then loads straight into the budget at award, and the job cost report compares like with like.
Step 3: Take off quantities
Measure and count from the drawings, by cost code and, where the job is big enough, by area or floor. Record the quantity, the unit and where it came from. Keep waste separate from the measured quantity, as a factor you apply when pricing, so the takeoff stays checkable. The takeoff entry covers units and formulas; the point here is that every priced line should trace back to a measured quantity or a quote.
Step 4: Price self-performed labor
For each labor line:
hours = quantity × production rate (hours per unit) labor cost = hours × base wage × (1 + burden %)
Production rates should come from your own completed jobs, recorded as hours per unit by cost code, then adjusted for this job: height, access, phasing, occupied space, overtime. Price at the fully burdened rate, which adds payroll taxes, insurance, benefits or union fringes to the wage. Labor burden: the number behind every bid explains why, and the labor burden calculator works out your percentage.
Step 5: Price material and equipment
Material comes from current quotes, with sales tax where it applies, delivery and a waste factor. Note how long each quote is valid and whether it holds through your award date. Equipment is priced at rental rates or your internal rates for the duration you’ll need it, plus fuel, delivery and pickup.
Step 6: Get subcontractor quotes and level them
Send each trade the same scope lines and a bid form, then level the bids: compare them line by line, price every exclusion with a plug, and carry the leveled number, not the lowest cover-sheet number. The bid tabulation template does that arithmetic for up to four bidders. Before you rely on a bid, check the bidder can perform at this size; see how to prequalify subcontractors.
Step 7: Build general conditions from the schedule
General conditions are mostly time: the superintendent, project management, the field office, temporary utilities, dumpsters and cleanup run for as long as the job does. Build them from a schedule duration and monthly or weekly rates, not as a percentage of trade cost. How to calculate general conditions costs walks through it, and the general conditions calculator gives you the weekly burn.
Step 8: Add contingency for the risk that’s left
After pricing, list what you still don’t know: drawings that aren’t finished, existing conditions you couldn’t see, quantities you had to assume, quotes that may not hold. Put a number on the ones that matter and carry it as a separate contingency line. A visible line can be reviewed and argued about at the bid review; contingency hidden in inflated unit prices can’t.
Step 9: Apply overhead and profit, then insurance and bond
Markup recovers the company overhead that isn’t in the job, then earns profit. Set it from your overhead budget and revenue forecast, as in how to calculate overhead and markup for a bid, and remember that markup on cost isn’t margin on price; the markup and margin calculator converts between them.
Costs charged on the contract value, such as the bond premium and any insurance rated on revenue, go on last, after markup, because they’re calculated on the final number. The bond premium calculator handles tiered bond rates.
Step 10: Review, qualify and check against history
Before the number goes out:
- A second person checks the biggest quantities and the largest lines.
- Compare with your history for similar jobs, by trade and in total, including cost per square foot. A big difference isn’t wrong by itself, but you should be able to explain it.
- Check the spec list from Step 1 again. Every section should have an owner.
- Write the clarifications and exclusions that describe what your price assumes, and make sure they match the leveled sub scopes.
Worked example: a 6,000 square foot office tenant improvement
A GC bids the interior build-out of a 6,000 square foot office suite on a 14-week schedule. It self-performs the door, frame and hardware installation and final cleaning, and subcontracts the rest.
Self-performed work
| Line | Calculation | Amount |
|---|---|---|
| Door, frame and hardware install labor | 24 openings × 3.0 h = 72 h × $40.00 × 1.40 | $4,032.00 |
| Doors, frames and hardware | quote, delivered | $26,400.00 |
| Sales tax on material | $26,400.00 × 7% | $1,848.00 |
| Final cleaning labor | 80 h × $28.00 × 1.40 | $3,136.00 |
| Scissor lift | 4 weeks × $400 | $1,600.00 |
| Self-performed direct cost | $37,016.00 |
The 3.0 hours per opening is the company’s own average from past jobs. The 1.40 multiplier is a 40% labor burden.
Subcontracts, leveled
| Package | Amount |
|---|---|
| Selective demolition | $18,500 |
| Metal framing and drywall | $142,000 |
| Acoustical ceilings | $38,600 |
| Flooring | $54,200 |
| Painting | $21,900 |
| Fire sprinkler modifications | $24,800 |
| HVAC | $96,000 |
| Plumbing | $31,500 |
| Electrical | $118,000 |
| Subcontract total | $545,500 |
General conditions, 14 weeks
| Item | Calculation | Amount |
|---|---|---|
| Superintendent, burdened | 14 weeks × $3,200 | $44,800 |
| Project manager, part time | 14 weeks × $900 | $12,600 |
| Dumpsters | 10 hauls × $650 | $6,500 |
| Floor and finish protection, temporary items | lump sum | $4,500 |
| General conditions | $68,400 |
From direct cost to bid price
| Line | Calculation | Amount | Running total |
|---|---|---|---|
| Self-performed direct cost | $37,016.00 | $37,016.00 | |
| Subcontracts | $545,500.00 | $582,516.00 | |
| General conditions | $68,400.00 | $650,916.00 | |
| Contingency, 2% | $650,916.00 × 2% | $13,018.32 | $663,934.32 |
| Overhead and profit, 10% | $663,934.32 × 10% | $66,393.43 | $730,327.75 |
| Insurance, 1% | $730,327.75 × 1% | $7,303.28 | $737,631.03 |
| Bond, 1% | $737,631.03 × 1% | $7,376.31 | $745,007.34 |
| Bid price | $745,007.34 |
The bid goes in at $745,000, giving up $7.34 to rounding. That’s $745,000 ÷ 6,000 = about $124.17 per square foot, which the estimator compares with the company’s last few office TIs of similar finish level. Subcontracts are $545,500 of the $650,916 direct cost, 83.8%, so the sub leveling is where this estimate is most likely to be wrong, and it’s where the second reviewer spends most of the time.
Two checks on the markup: the 10% overhead and profit on cost is a margin of 10 ÷ 110 = 9.1% on the marked-up subtotal, not 10%. And because the bond and insurance were calculated last, they’ll scale correctly if the number changes on bid day.
Common mistakes
- Pricing labor at the base wage. Burden is real cost and belongs in direct cost.
- Carrying the low sub number instead of the leveled one. An excluded item that nobody priced shows up later as your cost.
- General conditions as a flat percentage. They follow time, so a longer schedule should cost more.
- Hiding contingency in the unit prices. Nobody can review it, and nobody knows how much is left once the job starts.
- Adding overhead and profit percentages to get a margin. Markup on cost and margin on price are different numbers.
- Bond and insurance before markup, when the premium is charged on the final contract value.
- An estimate on a different code structure than the budget, so it has to be re-keyed at award.
- No clarifications. If your price assumes something, write it down.
How os.construction handles it
os.construction doesn’t include takeoff or estimating tools, so quantities and pricing come from your estimating software or spreadsheet. Once you have numbers, the Budget accepts a quantity, unit of measure and unit cost on each cost code line and multiplies them, so the estimate’s structure carries into the job. In Bidding, invited subs price each bid line and can mark lines excluded, the leveling grid compares quotes side by side, and an approved award becomes a draft subcontract or purchase order. A project opportunity in the CRM can carry a proposal draft with itemized estimate lines, scope, exclusions and a validity date. For how the numbers flow on after award, see budget, commitments and cost.
FAQ
What are the steps to build a construction estimate?
Read the bid documents, set the estimate up on your cost codes, take off quantities, price self-performed labor, material and equipment, get and level subcontractor quotes, build general conditions from the schedule, add contingency for the risk that's left, apply overhead and profit, then add insurance and bond on the total. Review it, write the clarifications and exclusions, and check the result against your own history.
What is the difference between direct cost and bid price?
Direct cost is what the job itself will cost you: labor with burden, material, equipment, subcontracts and general conditions. Bid price is direct cost plus contingency, the markup that recovers company overhead and earns profit, and costs charged on the contract value such as bond and some insurance.
How do you estimate labor for a construction bid?
Multiply each quantity by a production rate, in labor hours per unit, to get hours, then multiply hours by the fully burdened hourly rate. The best production rates come from your own past jobs, recorded by cost code, adjusted for the conditions of this job.
Should the estimate include contingency?
Most estimates carry some contingency for risk that remains at bid time: incomplete design, quantities you couldn't verify, or pricing that may move. Size it from the specific risks you can name rather than a flat habit, and keep it on its own line so it's visible. On some contracts, contingency is a defined line the owner can see; on a lump sum it's part of your own price.
How do I check whether my estimate is reasonable?
Compare it with your own completed jobs of similar type on cost per square foot and by trade, have a second person review quantities and the biggest lines, check that every specification section has an owner in the estimate, and look at the spread of subcontractor bids. A trade far from your history or far from the other bids deserves a second look.