A takeoff (quantity takeoff) is the estimator’s process of measuring and counting the quantities of work and materials shown on the drawings and specs: linear feet of wall, square feet of drywall, cubic yards of concrete, counts of doors and fixtures. Quantities are grouped by scope, then multiplied by unit costs to build the estimate.
Takeoffs are done on paper, in on-screen digital tools that measure PDFs, or by extracting quantities from BIM models. Whatever the tool, the output is the same: a structured list of quantities with units, usually organized by CSI MasterFormat division or the contractor’s own cost codes, ready for pricing.
In plain English
A takeoff is counting and measuring everything on the drawings before you price it. Illustrative: a plan shows a 100 ft by 60 ft slab, 6 inches thick, and 200 ft of interior wall 10 ft high. The estimator turns that into 111 cubic yards of concrete and 3,580 square feet of drywall (after subtracting door openings), then adds waste to get 117 yards to order and 83 sheets of board. Pricing comes next; the takeoff only answers “how much.”
Quantity takeoff vs material takeoff
| Quantity takeoff (QTO) | Material takeoff (MTO) | |
|---|---|---|
| Purpose | Measure all the work to build the estimate | List the materials to buy |
| Measures | Work items, including labor-driven ones such as LF of framing or SF of paint | Purchasable items: sheets, sticks, tons, pieces |
| Who uses it | GC and trade estimators | Suppliers, subs, purchasing |
| Allowances | Waste factors applied at pricing | Waste, lap and cut-off built into order quantities |
| Example | 4,000 SF of partition board, both sides | 83 sheets of 4 × 12 drywall |
Takeoff vs estimate
| Takeoff | Estimate | |
|---|---|---|
| Question | How much work is there? | What will it cost? |
| Output | Quantities and units (CY, SF, LF, EA, TON) | Dollars by line, with markups |
| Inputs | Drawings, specifications, addenda, models | Takeoff quantities, unit costs, productivity, sub quotes |
| Adds | Waste and lap allowances | Labor, equipment, general conditions, overhead, contingency, fee |
| Typical owner | Estimator or quantity surveyor | Estimator and chief estimator |
How a takeoff works
- Collect the documents. Current drawings, specifications and every addendum. Note the scale of each sheet.
- Set up the structure. Organize by division or cost code so the takeoff matches how the job will be bought out and tracked.
- Measure. Lengths (LF), areas (SF), volumes (CY) and counts (EA), sheet by sheet, marking what’s been counted so nothing is counted twice.
- Read the specs. Specifications add items the drawings don’t show: accessories, testing, finishes, mock-ups.
- Apply allowances. Add waste, lap and overlap factors by material, based on your history.
- Check it. Compare against a second takeoff, a historical cost per square foot, or quantities from a model.
- Hand it to pricing. Quantities × unit costs for labor, material and equipment, plus subcontractor quotes for trades you won’t self-perform.
Formulas
- Concrete volume (CY) = length (ft) × width (ft) × depth (ft) ÷ 27
- Wall area (SF) = length (LF) × height (ft) × sides − openings
- Order quantity = net quantity × (1 + waste factor), rounded up to purchasable units
Worked example
Illustrative numbers for two items on a small building:
Slab on grade. 100 ft × 60 ft × 6 in (0.5 ft) = 3,000 cubic feet ÷ 27 = 111.1 CY net. With a 5% allowance for subgrade variation and waste: 111.1 × 1.05 = 116.7, so order 117 CY. At an illustrative $165 per CY delivered, material is $19,305 before pumping, finishing labor and testing.
Drywall partitions. 200 LF of wall, 10 ft high, board on both sides = 4,000 SF. Ten door openings of 3 ft × 7 ft = 21 SF each, both sides = 420 SF, leaving 3,580 SF net. With a 10% waste factor: 3,938 SF. In 4 × 12 sheets (48 SF each): 3,938 ÷ 48 = 82.04, so 83 sheets.
If the estimator had missed the second side of the wall, the drywall quantity would be half of what’s needed, a bust carried straight into the bid, the buyout and the budget.
Why it matters
Everything downstream depends on the quantities. A missed scope or bad count becomes a bust in the bid, then a budget problem, then margin fade. A good takeoff organized by cost code also becomes the starting budget, so the field and the office measure the job the same way, and unit costs from completed jobs (installed quantity ÷ hours) improve the next estimate. On unit price contracts, measured quantities also drive what the owner pays.
When the drawings are wrong, the takeoff inherits the error. A takeoff that missed fire dampers because the drawings didn’t show them is a design gap recoverable through an RFI and change order; the same miss on the contractor’s own scope is not.
Common mistakes
- Takeoff organized differently from the cost codes the job will be tracked on.
- Reading only the drawings and not the specs or addenda.
- Using the wrong scale on a reduced or “not to scale” sheet.
- No waste factor, or the same waste factor for every material.
- Double counting items that appear on more than one sheet.
- Not recording assumptions, so the PM can’t tell what was included at bid leveling.
For how quantities become a bid price, layer by layer with a worked example, see how to build a construction estimate from scratch.
How os.construction handles it
os.construction does not include takeoff or estimating tools; use your takeoff and estimating software for quantities and pricing. Once the job is awarded, the budget lives on the project by cost code and cost type, and many contractors base those codes on CSI MasterFormat divisions so the estimate, budget and job cost line up. Budgets are entered in the Budget tool, and importing cost codes and budgets from other systems is planned. See Cost codes and budgets and Budget.
FAQ
What is a takeoff in construction?
A takeoff is the estimator's measurement of quantities from the drawings and specifications: linear feet of wall, square feet of drywall, cubic yards of concrete, counts of doors, fixtures and devices. The quantities are organized by scope and then priced with unit costs for labor, material and equipment to build the estimate. It is called a takeoff because quantities are taken off the plans.
What is the difference between a takeoff and an estimate?
A takeoff answers how much: quantities measured from the documents. An estimate answers how much it will cost: quantities multiplied by unit prices, plus labor productivity, equipment, subcontractor quotes, general conditions, overhead, contingency and markup. The takeoff is an input to the estimate, and errors in it carry straight into the price.
What is a material takeoff (MTO)?
A material takeoff is a takeoff focused on the materials to purchase, such as tons of rebar, sheets of drywall or lengths of pipe, often including waste and lap allowances. Suppliers and subcontractors use material takeoffs for quotes and ordering, while a general estimate takeoff may also measure labor-driven items like linear feet of wall framing.
What units are used in a quantity takeoff?
Each item is measured in the unit it will be priced and bought in: cubic yards (CY) for concrete and earthwork, square feet (SF) for slabs, drywall, roofing and flooring, linear feet (LF) for walls, curbs, pipe and conduit, each (EA) for doors, fixtures and devices, and tons for rebar and structural steel. Using the purchasing unit avoids conversion errors at pricing and buyout.
How are takeoffs done today?
Takeoffs are done by hand from paper drawings with a scale, on screen with digital takeoff software that measures PDFs, or from BIM models that can report quantities by element. Each method still needs an estimator to check scale, read the specifications and catch items the drawings or model don't show.
What waste factor should I use in a takeoff?
It depends on the material, the layout, the crew and company history, so there is no single right number. Estimators typically apply different allowances to items like drywall, flooring and concrete, and the best source is your own records of quantities ordered versus quantities installed on past jobs.