Suspend and Resume

Definition

Dates that record a pause in started work: the suspend date when it stopped and the resume date when its remaining work restarts.

Topic: Scheduling

Updated

Suspend and resume dates record a pause in work that has already started. The suspend date is when work stopped, for example when a crew was pulled off for a design hold. The resume date is when the remaining work restarts. In Primavera P6, a started activity with both dates and a resume date after the data date has its remaining work scheduled from the resume date.

Worked example

Illustrative: Curtain wall, east elevation started on 2 March and was suspended on 10 March, waiting for revised anchor details. The resume date is set to 30 March, and the data date is 16 March. Its 8 days of remaining work now restart on 30 March instead of the data date, so it finishes about two weeks later and its successors move with it.

Why it matters

Without a resume date, the remaining work is scheduled from the data date as if the crew were still there, and the forecast is too optimistic. A resume date makes the stoppage visible in the dates and the float.

Common mistakes

  • Entering a suspend date without a resume date and expecting the dates to move. The resume date is what moves the remaining work.
  • Leaving a resume date in the past after work restarted. Once the data date passes it, it has no effect, but it can confuse a reviewer.
  • Using suspend and resume on work that hasn’t started. A pause before the start is logic or a constraint, not a suspension.

How os.construction handles it

The engine schedules suspend and resume as P6 23.12.1 does on its probe projects: started work with a resume date after the data date restarts its remaining work then, and the schedule log notes it. Suspend and resume dates come in from XER, show as Planner columns and go back out on export. P6 XML doesn’t carry them, the suspension isn’t taken out of elapsed start-to-start lag, and the resume date is read to the day. See P6 compatibility.

FAQ

Does a resume date move the schedule?

Yes, when the work has started and the resume date is after the data date. The remaining work can't restart before the resume date, so its finish and its successors move out.

What if there's a resume date but no suspend date?

In P6, and in os.construction, a resume date only matters together with a suspend date. On its own, or on or before the data date, it changes nothing.