Weather Allowance

Definition

Working days a schedule sets aside for normal bad weather, usually by month and applied only to weather-sensitive work.

Topic: Scheduling

Updated

A weather allowance builds normal bad weather into the schedule, so a typical wet spring doesn’t read as a delay. It’s usually stated as expected lost working days per month for the site, and applied only to weather-sensitive activities. Many contracts also use those monthly figures as the threshold above which weather becomes excusable delay.

Worked example

Illustrative: records for the site show about 4 lost working days in January, 3 in February and 1 in July. Earthworks and the roof are tagged weather-sensitive; interior fit-out isn’t. As a calendar allowance, those days become non-working days on the sensitive activities’ calendars and the site finish moves out 6 working days. In a probabilistic risk run, January varies between 1 and 8 lost days, and the P80 finish moves 9 working days later than without weather.

Why it matters

Without an allowance, normal weather eats float that wasn’t meant for it. With an allowance on every activity, indoor work is padded for no reason. Stating the allowance by month and by activity makes weather claims measurable against it.

Common mistakes

  • Spreading weather days evenly across the year when the risk is seasonal.
  • Applying the allowance to the whole calendar, including work under cover.
  • Adding the same weather risk both as an allowance and inside pessimistic durations.

For the field records that show lost days against the allowance, see how to document weather delays.

How os.construction handles it

The Risk page keeps weather calendars by region and month, imports them from CSV by month or season, and tags weather-sensitive activities by ID or activity code. Weather is applied either as calendar exceptions or as monthly draws in each Monte Carlo iteration, and the result shows the finish with and without weather on the same random numbers. See Weather.

FAQ

How many weather days should a schedule include?

Enough for normal weather at the site in each month, usually from historical records for the location. Many contracts state the expected days per month, and only weather beyond them is excusable.

Should weather days go on every activity?

No. Only work that weather stops, such as earthworks, concrete pours, roofing and exterior envelope. Interior work under a dry roof usually carries none.

What is the difference between a calendar allowance and a probabilistic one?

A calendar allowance takes the expected days as non-working days on the sensitive work's calendar. A probabilistic allowance varies the lost days between a minimum and a maximum in a risk simulation, so the forecast shows a range.