A schedule of values (SOV) is the breakdown of the contract sum into billable line items, each with a dollar value, that together equal the contract sum. The contractor prepares it, the architect or owner accepts it before the first pay application, and every progress bill afterward reports work completed against those same lines.
Lines are usually organized by trade, CSI division, building area or phase. On AIA-based jobs the SOV becomes the left-hand columns of the G703 continuation sheet. In the UK the closest equivalents are the JCT Activity Schedule and the Contract Sum Analysis, though many UK interim valuations work from a bill of quantities instead.
How it works
- The contractor drafts it. Under AIA A201 §9.2, on stipulated sum and GMP contracts the contractor submits a schedule of values allocating the entire contract sum to portions of the work, before the first application for payment.
- The architect reviews it. The architect checks that values look reasonable and aren’t front-loaded. It can ask for supporting data. Once accepted, the SOV is the basis for reviewing every pay app.
- Each month, progress is reported per line. On the G703: work completed from previous applications, this period, materials presently stored, total to date, percent complete, balance to finish and retainage. The G702 summarizes the totals.
- Change orders add lines. Each approved change order is added, usually as its own line, so the SOV always equals the current contract sum.
- Subcontracts mirror it. Each sub’s SOV covers its own scope and drives its own pay applications to the GC.
Building a good SOV
| Choice | Too coarse | About right | Too fine |
|---|---|---|---|
| Line count | A few lines per trade | Lines you can measure progress on, tied to cost codes | Hundreds of tiny lines nobody updates |
| Progress evidence | Hard to defend “40% of MEP” | Each line has a clear measure (units, areas, milestones) | Measuring costs more than it’s worth |
| Link to job cost | None | One SOV line maps to one or a few cost codes | Every cost code is a billing line |
| Change orders | Rolled into existing lines | Separate CO lines | Fine either way |
The goal is an SOV where billing, job cost and WIP tell the same story. When an SOV line maps to cost codes, the billed percent on that line can sit next to the cost percent, and a gap shows up as over billing or under billing before month end.
Front-loading
Front-loading means putting more value on early lines (mobilization, general conditions, foundations) than the work is worth, so more is billed early. Contractors do it to fund the job with the owner’s money instead of their own. Owners push back because it leaves them paying ahead of the work; if the contractor defaults, the money left in the contract may not finish the job.
A small amount of weighting is common and sometimes negotiated. Heavy front-loading is what architects look for when they review the SOV, and it creates large over billings that a surety will notice on the WIP.
Why it matters
The SOV sets how fast you can bill for the life of the job. Lines that are too coarse make progress hard to prove, so pay apps get cut. Lines that don’t map to cost codes make it hard to see whether billing is ahead of or behind cost. And because the SOV is accepted once at the start, mistakes in it stay with you every month. For how the SOV differs from the cost budget and how to map one to the other, see schedule of values vs budget.
Worked example
Illustrative: Riverside Medical Center has a $48,200,000 original contract. The SOV splits it into lines such as general conditions, sitework, concrete, steel, mechanical, electrical and finishes, with $1,013,600 of earlier approved change orders (COs #1 to #13) added as separate lines. When CO #14 for $86,400 (fire dampers) is executed, it becomes its own line, and the total scheduled value becomes $49,300,000.
On Pay App #9, the CO #14 line shows $51,840 of work this period and $17,280 of dampers stored on site: $69,120 to date, 80% of the line, with $6,912 retainage at 10%. Because it has its own line, anyone can trace the change from the RFI to the dollars billed. The anatomy of a pay app walks through the full G702 and G703.
Common mistakes
- No mapping to cost codes. Billing and job cost can’t be compared line by line.
- Heavy front-loading. The architect rejects it, or it creates over billings that reverse painfully later.
- Rolling change orders into existing lines. They can’t be traced, and percent complete on the original line becomes meaningless.
- Lines with no measurable progress. “MEP: $6,000,000” invites a fight every month.
- Forgetting stored materials. Materials delivered but not installed are billed in their own column on the G703, under the contract’s stored materials terms.
Once the SOV is approved, every pay application bills against it; how to fill out a G702/G703 pay application walks through the monthly routine. To keep cost and billing comparable, map each cost code to exactly one SOV line.
How os.construction handles it
Prime contracts, subcontracts and purchase orders each hold a schedule of values. On a commitment, each SOV line carries a cost code, description, quantity, unit and amount; see Commitments. Payment applications fill the G703 lines from the contract’s SOV, add executed change orders for you and carry From Previous forward from the last pay app, so nobody retypes the SOV each month. The concept page Pay apps, SOV and retainage explains the full flow.
Watch the explainer · 2:02
What is a schedule of values?
- 0:00The contract sum, line by line
- 0:18Who prepares it
- 0:39Billing against the lines
- 0:57Change orders get their own lines
- 1:17Front-loading
- 1:39The SOV in os.construction
Read the transcript
A schedule of values, or SOV, breaks the contract sum into line items, such as general conditions, sitework, concrete, steel, mechanical and electrical, each with a dollar value. The lines add up to the contract sum, and every pay app bills against them.
The contractor prepares it. Under AIA A201, section nine point two, on stipulated sum and GMP contracts, the contractor submits it before the first application for payment. The architect reviews the values and can ask for backup. Once it's accepted, it's the basis for reviewing every pay app.
Each month, the continuation sheet reports every line: work from previous applications, work this period, materials stored, total to date, percent complete, balance to finish and retainage. The summary page rolls those columns up into the current payment due.
Approved change orders change the contract sum, so each one is added, usually as its own line. On the sample Riverside job, change order fourteen, eighty-six thousand four hundred dollars for fire dampers, becomes its own line, and the SOV now totals forty-nine point three million. Pending changes stay off the bill.
Front-loading means putting more value on early lines, like mobilization or general conditions, than the work is worth, so more is billed early. It helps the contractor's cash flow, but leaves the owner paying ahead of the work, which is why architects look for it. A good SOV has lines you can measure progress on, each tied to cost codes.
In os.construction, prime contracts, subcontracts and purchase orders each hold a schedule of values. Payment applications fill the continuation sheet from the contract's SOV, add executed change orders and carry the previous column forward, so nobody retypes the SOV each month.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a schedule of values in construction?
A schedule of values is a list that divides the contract sum into line items, such as general conditions, sitework, concrete, steel, mechanical and electrical, each with a dollar value. The lines add up to the contract sum. Every progress billing then reports how much of each line is complete, usually on an AIA G703 continuation sheet or a similar form.
Who prepares the schedule of values?
The contractor. AIA A201 §9.2 requires the contractor, on stipulated sum and GMP contracts, to submit a schedule of values to the architect before the first application for payment, allocating the entire contract sum to portions of the work. Once accepted, it is the basis for reviewing pay applications. Subcontractors prepare their own SOV for their subcontract.
What is front-loading a schedule of values?
Front-loading means putting more value on early lines, such as mobilization, general conditions or foundations, than the work is really worth, so the contractor bills more early in the job. It improves the contractor's cash flow but shifts risk to the owner, which is why architects and owners review SOVs for it and can require the values to be supported.
How do change orders affect the schedule of values?
Approved change orders increase or decrease the contract sum, so they are added to the SOV, usually as their own lines so each one can be billed and traced. After each change the SOV still adds up to the current contract sum.
What is the UK equivalent of a schedule of values?
Under JCT contracts, the closest equivalents are the Activity Schedule, a priced schedule of activities that can be used for interim valuations under the Standard Building Contract, and the Contract Sum Analysis used with Design and Build contracts. Many UK projects value interim payments from a bill of quantities instead.
