Scope of Work

Definition

The written description of the work a contractor or subcontractor must perform, including what is included, what is excluded and the standards it must meet.

Topic: Project delivery & contracts

Updated

A scope of work (SOW) is the written description of the work a contractor or subcontractor must perform under its contract. It names the work and the documents it is based on, lists what is included and excluded, and sets the standards, deliverables and milestones the work must meet. Anything outside it is extra work, normally priced through a change order.

On the prime contract, the scope is mostly defined by the drawings and specifications; AIA A201 defines the Work as the construction and services the Contract Documents require. On a subcontract, the general contractor writes the scope itself, usually as an exhibit, and that document decides who pays when something turns out to be missing.

How it works

  1. Bid package. The GC groups work into trade packages, usually by CSI MasterFormat section and cost code, and writes a draft scope for bidders.
  2. Quotes. Bidders price the scope and add their own inclusions, exclusions and qualifications.
  3. Leveling. In bid leveling, the GC lines quotes up against the same scope and prices any excluded items, so a low number with gaps isn’t mistaken for the best value.
  4. Scope exhibit. The chosen trade’s scope is written into the subcontract: the base scope, the clarified inclusions, the accepted exclusions and the items the GC will provide.
  5. Changes. During the job, anything outside the written scope is handled as a change. Anything inside it is the trade’s cost, whatever its quote assumed.

What a good subcontract scope contains

Section What it says Typical example
Basis Drawings, specs, addenda and dates Bid set dated 3/14, addenda 1-3
Work included Work by spec section and description Section 09 21 16 gypsum board assemblies
Specific inclusions Items often disputed, named outright Fire caulking at rated walls, blocking for casework
Exclusions What the trade won’t do Painting, final cleaning
By others What the GC or other trades provide Hoisting, temporary power, dumpsters
Deliverables Submittals, mockups, closeout documents Shop drawings, O&M data, warranty
Schedule Milestones and durations Board complete per floor in 15 working days
Allowances and unit prices Priced placeholders $25,000 allowance for access panels

Why it matters

Most disputes between a GC and its trades come down to scope. If the subcontract scope is narrower than what the prime contract requires, the GC owns the gap, because the owner holds it to the full contract. If the scope is vague, both sides read it in their own favor, and the argument happens after the work is installed.

A clear scope also makes changes cleaner. When the base scope is written down, a change event can be sorted quickly into owner change, in-scope work or trade back charge, and a flow-down clause can carry the owner’s terms to the trades without leaving holes.

Worked example

Illustrative: a GC receives three drywall quotes. The low bid, $812,000, excludes fire caulking and the installation of access panels. The other two include both. In leveling, the GC prices the exclusions at $24,500 and $9,800 using the lowest other quotes, which brings the low bidder to $846,300, still the best value. The scope exhibit then names fire caulking at rated assemblies and access panel installation as included, with the price adjusted to match. Three months later the drywall foreman questions the caulking. The scope settles it in a sentence.

Common mistakes

  • Writing the scope only by spec section, when the drawings show work that no section assigns.
  • Accepting a bid’s exclusions without pricing them during leveling.
  • Leaving “by others” items unassigned, so they belong to nobody.
  • Copying last job’s scope without checking it against this job’s documents.
  • Forgetting deliverables like submittals, testing and closeout documents.
  • Using “per plans and specs” as the whole scope.

This is general information, not legal advice. How a scope is read depends on the contract and the governing law.

For a step-by-step method with a responsibility matrix that finds gaps between trades, see how to write a scope of work for subcontractors.

How os.construction handles it

In the app today, a bid package carries its scope and bid form lines, and an approved vendor release fixes exactly what bidders see. Bidders mark lines excluded and add qualifications and alternates, and the leveling grid shows “Excl.” where a line is missing. When the award becomes a draft subcontract or purchase order, each included priced line carries its cost code into the commitment’s schedule of values. See from bid to awarded commitment and the commitments guide.

FAQ

What is a scope of work in construction?

A scope of work is the part of a construction contract or subcontract that says exactly what work the contractor will do. It lists the work and deliverables, references the drawings and specification sections, and states inclusions, exclusions, assumptions and any allowances. Anything outside it is extra work, which is normally priced through a change order.

What should a construction scope of work include?

At minimum: the project and location, the drawings, specifications and addenda it is based on, a description of the work by spec section or cost code, specific inclusions and exclusions, who supplies and who installs each material, schedule milestones, site rules, submittal and closeout deliverables, and how changes are priced. Subcontract scopes also list items the general contractor provides, such as hoisting or temporary power.

What is the difference between a scope of work and a statement of work?

In construction they mean the same thing, and scope of work is the more common term. Statement of work is more common in government and services contracting, where it describes tasks and deliverables. In UK usage the phrase is often scope of works, with works being the usual British word for construction work.

What is a scope gap?

A scope gap is work the prime contract requires that none of the subcontracts or purchase orders covers. Gaps usually come from exclusions in bids, work that sits between two trades, such as fire caulking or controls wiring, and scopes written by spec section without checking the drawings. The general contractor usually pays to fill them.

Who writes the scope of work?

For the prime contract, the owner and its designers define the work through the drawings and specifications. For subcontracts, the general contractor's estimators and project managers write each trade's scope, usually as an exhibit to the subcontract, based on the bid package and the trade's leveled quote.