- Step 1: Start from the bid package and the leveled quote
- Step 2: Name the documents, exactly
- Step 3: Write the general scope statement
- Step 4: List the specific inclusions
- Step 5: List the exclusions, and who carries each
- Step 6: Check every interface item in a responsibility matrix
- Step 7: Add schedule, logistics and the GC’s services
- Step 8: Add deliverables and pricing structure
- Step 9: Review it with the sub, then attach it
- Worked example: an interface matrix on an office fit-out
- Common mistakes
- How os.construction handles it
- FAQ
To write a subcontractor scope of work, start from the leveled bid, list the contract documents it’s based on by number and date, write a general statement of the work, then name every item trades argue about as an inclusion or an exclusion with the party who carries it. Before you sign, check each interface item across all the trades in a responsibility matrix, so every item has exactly one owner.
The scope of work is the part of a subcontract that decides who pays when something is missing. The owner holds the GC to the whole prime contract. If the trade scopes add up to less than that, the difference is the GC’s cost, usually discovered in the field when the work is already late. A good scope is boring to read and short on surprises.
Step 1: Start from the bid package and the leveled quote
Don’t start from last job’s scope. Start from the scope lines you sent bidders, the quote you’re accepting, and the notes from the scope review call where the bidder confirmed what’s in. If you leveled the bids properly, you already have a line-by-line list of what each bidder included, excluded and qualified, and what you plugged. The scope exhibit is where those answers become contract terms.
Step 2: Name the documents, exactly
List what the work is based on:
- Drawings by sheet number, title and revision date, or by reference to a dated drawing list.
- Specification sections by number and title.
- Addenda and bulletins by number and date.
- The prime contract terms that flow down, if your subcontract incorporates them. Check the flow-down clause does what you think it does.
A scope that says “the latest drawings” is a scope nobody can check. When a revision comes out after award, a dated list makes it clear whether the change is in the sub’s price or is a change order.
Step 3: Write the general scope statement
One or two sentences that state the trade’s responsibility in plain terms: furnish all labor, material, equipment and supervision to complete the named work as shown and specified, including the items listed below. Then the specification sections it covers. Keep it short; the detail goes in the lists.
Step 4: List the specific inclusions
Name the items that sit between sections or that bidders commonly leave out, even if you think the specs already cover them. For a drywall package that might be:
- Fire-rated joint systems and head-of-wall details at rated assemblies.
- Blocking and backing in stud walls for casework, grab bars, wall-mounted equipment and owner-furnished items.
- Installing access panels furnished by other trades.
- Sound insulation and sealant at acoustically rated walls.
- Daily cleanup of the trade’s debris to the GC’s dumpster.
The point of listing them isn’t to repeat the spec. It’s to stop the argument about whether the spec applied.
Step 5: List the exclusions, and who carries each
Every exclusion should name who does the work instead: the GC, another trade by name, or the owner. “Excluded” with no owner means the work belongs to nobody, which in practice means the GC. Accept only the exclusions you priced during leveling.
Step 6: Check every interface item in a responsibility matrix
Put the interface items down the side of a table and the trades across the top: who furnishes, who installs. Typical rows include blocking, firestopping at penetrations, access panels, cutting and patching, sleeves and cores, layout, hoisting, temporary power and lighting, cleanup and dumpsters, testing and inspections, and protection of installed work.
Read across each row. A row with no mark is a gap. A row with two marks is an overlap you’re paying for twice. Fix both before award, by adding the item to one scope and deleting it from another, at a price.
Step 7: Add schedule, logistics and the GC’s services
Write down what the sub needs to plan around: the schedule or milestones it must meet, durations per area if they matter, working hours, site access, laydown and parking, hoisting, and what the GC provides, such as temporary power, toilets, dumpsters or a material hoist. Requirements the sub would otherwise discover on site belong here, because each one has a cost.
Step 8: Add deliverables and pricing structure
- Submittals, mockups, testing and inspections the trade is responsible for.
- Closeout: as-builts, O&M data, warranties, attic stock and training.
- Pricing: the schedule of values lines you want, any unit prices for added or deleted work, accepted alternates and allowances.
Step 9: Review it with the sub, then attach it
Walk the sub’s project manager through the exhibit before signing, line by line. It’s cheaper to argue about an item now than after it’s installed. Then attach it to the subcontract as an exhibit, and make sure the subcontract amount matches the scope you wrote, including any items you added or removed in Step 6.
Worked example: an interface matrix on an office fit-out
A GC is buying out drywall, electrical, mechanical and painting for an office fit-out. Before writing the scope exhibits, the project manager builds a matrix of the interface items from the four leveled quotes:
| Interface item | Drywall | Electrical | Mechanical | GC | Result |
|---|---|---|---|---|---|
| Blocking for owner-furnished TVs and casework | excluded | Gap | |||
| Firestopping at MEP penetrations of rated walls | joints only | own conduit excluded | own duct excluded | Gap | |
| Installing access panels | included | included | Overlap | ||
| Cutting and patching for own work | included | included | OK | ||
| Hoisting | included | OK | |||
| Final cleaning | included | OK |
The drywall quote excluded blocking “for items by others”, and each MEP trade excluded firestopping at its own penetrations, expecting someone else to do it. Meanwhile both drywall and mechanical priced installing the access panels.
The PM prices the fixes from the bidders’ unit prices:
| Item | Calculation | Amount |
|---|---|---|
| Firestopping at 46 penetrations, added to the drywall scope | 46 × $85 | $3,910 |
| Blocking, 120 linear feet, added to the drywall scope | 120 × $18 | $2,160 |
| Gaps closed | $6,070 | |
| Access panel installation, 28 panels, deleted from the mechanical scope | 28 × $50 | −$1,400 |
| Net change to the commitments | $6,070 − $1,400 | $4,670 |
The drywall subcontract goes out with blocking and penetration firestopping named as inclusions, priced at $6,070, and the mechanical subcontract excludes access panel installation “by drywall subcontractor”, $1,400 lower. The net $4,670 is a known cost on day one. Found after award, the $6,070 would have arrived as two change orders, and the $1,400 would have been paid twice without anyone noticing.
Common mistakes
- “Per plans and specs” as the whole scope. It doesn’t say who does the work between sections.
- Copying last job’s exhibit without checking it against this job’s documents and quotes.
- Exclusions with no owner. “Excluded” alone means the GC does it.
- No dated document list, so nobody can tell whether a revision is in the price.
- Skipping the matrix, so gaps between trades show up in the field.
- A subcontract amount that doesn’t match the written scope after scope review changes.
- Leaving out deliverables: submittals, testing, closeout documents and attic stock all cost money.
- Vague words like “complete” or “as required” standing in for a list. Where a scope is ambiguous, it may end up read against whoever drafted it, which is usually the GC.
This is general information, not legal advice. How a subcontract scope is interpreted depends on the subcontract, the prime contract and the governing law.
Scope problems found later turn into change orders or back charges, so the time is better spent now. The scope is also the first thing to check when you prequalify a subcontractor for a package this size, and it’s the heart of buyout.
How os.construction handles it
In Bidding, a bid package carries its scope and bid form lines, and bidders mark lines excluded and add qualifications, so the leveling grid shows where each quote is short. An approved award becomes a draft subcontract or purchase order with the priced lines and their cost codes. On the subcontract itself, Commitments has fields for inclusions and exclusions alongside retainage and contract dates, so the scope you agreed sits on the record the invoices and change orders are checked against. The free bid tabulation template works for the leveling step if you’re doing it in Excel.
FAQ
What should a subcontractor scope of work include?
The contract documents it's based on, listed by number and date; a general statement of the work; specific inclusions for items that are often disputed; exclusions and who carries each one; site logistics and the GC's services; schedule requirements; submittals, testing and closeout deliverables; and the pricing structure, including unit prices, alternates and allowances. It's usually attached to the subcontract as an exhibit.
Is 'per plans and specs' enough for a subcontract scope?
Usually not on its own. It ties the sub to the documents, but it doesn't say which trade does work that sits between sections or isn't assigned by any section, such as blocking, firestopping penetrations, access panels, cutting and patching or cleanup. Those interface items are where most scope disputes start, so name them.
What is a scope or responsibility matrix?
A table with interface items down the side and trades across the top, marking who furnishes and who installs each item. Reading across a row shows gaps, where nobody has the item, and overlaps, where two trades have priced it. It's built during bid leveling and used to write each trade's scope exhibit.
Who writes the subcontractor scope of work?
The general contractor, usually the estimator or project manager who leveled the bids. It's based on the bid package, the leveled quote and any scope review calls with the bidder, and it's reviewed with the subcontractor before the subcontract is signed.
What happens if the subcontract scope misses something the prime contract requires?
The owner holds the GC to the full prime contract, so the GC usually pays for the missing work, either by paying the sub a change order or by hiring someone else to do it. That's why the scope check against the prime contract documents and the neighboring trades matters before award.