Stored materials are materials the contractor has bought and received but not yet installed. On the G703 they appear in the “materials presently stored” column. Many contracts allow billing for them, especially for expensive or long-lead items, but with conditions: proof of purchase, proper storage, insurance, title passing to the owner, and for off-site storage, often a bonded warehouse and the owner’s approval in advance.
Why it matters
Contractors often have to pay suppliers before installation. Billing stored materials keeps that cash gap from landing on the GC or sub. But stored materials are also a risk: they can be damaged, stolen or double counted. Once installed, the value must move from “stored” into “work completed,” or it gets billed twice.
Worked example
Illustrative: on Riverside Medical Center, the fire dampers for CO #14 arrive before installation. Their invoiced cost of $17,280 is billed as stored materials on Pay App #9, with the supplier invoice and a photo in the backup. Next month, once installed, the $17,280 moves from stored materials into work completed this period, and the stored column for that line goes to zero.
Common mistakes
- Billing off-site stored materials without the owner’s prior approval.
- Not moving value out of “stored” when installed, which double bills.
- Missing insurance or title documentation that lenders require.
For the backup package and a two-month example of moving stored material to installed, see how to bill stored materials on a pay application.
How os.construction handles it
On the pay app, Materials Stored is its own column on every SOV line. A new pay app carries stored materials forward in that column until they are installed; when they go in, you move the amount into This Period, and it switches from the materials retainage rate to the work rate. The contract can set a separate retainage rate for stored materials. See Payment applications.
See how stored gear bills for electrical contractors and mechanical contractors.
Watch the explainer · 2:02
What is a schedule of values?
- 0:00The contract sum, line by line
- 0:18Who prepares it
- 0:39Billing against the lines
- 0:57Change orders get their own lines
- 1:17Front-loading
- 1:39The SOV in os.construction
Read the transcript
A schedule of values, or SOV, breaks the contract sum into line items, such as general conditions, sitework, concrete, steel, mechanical and electrical, each with a dollar value. The lines add up to the contract sum, and every pay app bills against them.
The contractor prepares it. Under AIA A201, section nine point two, on stipulated sum and GMP contracts, the contractor submits it before the first application for payment. The architect reviews the values and can ask for backup. Once it's accepted, it's the basis for reviewing every pay app.
Each month, the continuation sheet reports every line: work from previous applications, work this period, materials stored, total to date, percent complete, balance to finish and retainage. The summary page rolls those columns up into the current payment due.
Approved change orders change the contract sum, so each one is added, usually as its own line. On the sample Riverside job, change order fourteen, eighty-six thousand four hundred dollars for fire dampers, becomes its own line, and the SOV now totals forty-nine point three million. Pending changes stay off the bill.
Front-loading means putting more value on early lines, like mobilization or general conditions, than the work is worth, so more is billed early. It helps the contractor's cash flow, but leaves the owner paying ahead of the work, which is why architects look for it. A good SOV has lines you can measure progress on, each tied to cost codes.
In os.construction, prime contracts, subcontracts and purchase orders each hold a schedule of values. Payment applications fill the continuation sheet from the contract's SOV, add executed change orders and carry the previous column forward, so nobody retypes the SOV each month.
Video page with chaptersMore in Construction concepts explained
