A purchase order (PO) is the buyer’s written authorization to a supplier: what to deliver, how much, at what price, to which job and cost code. Once issued, it becomes a commitment against the job budget. In construction, POs typically cover materials, rentals and smaller service scopes; scopes with labor on site usually go under a subcontract instead.
How it works
- Request. The project team identifies a need, often from the estimate, the buyout plan or an approved submittal.
- Price. Quotes are gathered and compared. The chosen supplier’s prices, freight and lead times are confirmed.
- Issue. The PO is written with line items, quantities, unit prices, tax treatment, delivery dates and site, and each line is coded to a cost code.
- Approve. POs above a set amount need approval before they go to the supplier.
- Commit. Once issued, the PO’s value is recorded as a commitment, so the job’s committed cost and projected cost update straight away.
- Receive. Deliveries are checked at the site against the PO and the delivery ticket, and the receipt is recorded.
- Match and pay. The supplier’s invoice is matched to the PO and the receipt in a three-way match, then approved in accounts payable.
- Change or close. Price or quantity changes go through a PO change. When everything is delivered and billed, the PO is closed and any leftover commitment is released.
Worked example
On Riverside Medical Center, PO-118 has $42,050 of commitment remaining. INV-4471 comes in at $48,200, which is $6,150 over. Because the PO exists, the overage is flagged at entry. The PM confirms whether the extra quantity or price was approved; if it was, the PO is revised first, then the invoice is paid. If not, the vendor issues a credit. (Illustrative sample data.)
Illustrative (sample data) of the electrical gear PO behind it:
| Line | Qty | Unit price | Amount | Billed to date | Remaining |
|---|---|---|---|---|---|
| Panelboards | 12 | $4,800 | $57,600 | $38,400 | $19,200 |
| Transformers | 3 | $9,850 | $29,550 | $9,850 | $19,700 |
| Freight | 1 | $3,150 | $3,150 | $0 | $3,150 |
| Total | $90,300 | $48,250 | $42,050 |
INV-4471 bills the remaining panelboards, transformers and freight ($42,050), plus $6,150 of conduit fittings that aren’t on the PO, for $48,200. The line-level detail shows the overage is the unlisted fittings, not a price change on the gear.
Purchase order vs related documents
| Document | Used for | Typical terms |
|---|---|---|
| Purchase order | Materials, equipment, rentals, simple services | Items, quantities, prices, delivery |
| Subcontract | Work with labor on site | Scope, schedule, insurance, retainage, waivers, flow-down |
| Quote | The supplier’s offer before a PO | Prices and validity period |
| Delivery ticket | Proof of what arrived | Items and quantities received |
| Invoice | The supplier’s request for payment | Items billed and amount due |
Why it matters
A PO sets the price before the invoice arrives. That gives accounting something to match the invoice against, gives the PM visibility into committed cost and protects the job from surprise pricing. Without POs, AP is approving invoices on trust.
POs are also how the cost report sees the future. Projected cost on a job is cost to date plus open commitments plus what’s still to buy. If materials are ordered by phone with no PO, the commitment is missing, projected cost is too low and the overrun shows up only when the invoice arrives, often months later.
Common mistakes
- Blanket POs with no quantities or unit prices, which can’t be matched to anything.
- Creating the PO after the invoice (“after-the-fact POs”) just to satisfy a process.
- Coding the PO to the wrong cost code, so the job total looks right but the detail is wrong.
- Using a PO for work with labor on site, which leaves out insurance, indemnity and lien waiver terms.
- Never closing POs, so leftover commitment inflates projected cost.
- Ignoring the terms on the supplier’s acknowledgment when they differ from the PO.
How os.construction handles it
Purchase orders are project commitments. Before one exists, a purchase request can record what is needed, the supplier, cost code and estimate, shown next to the cost code’s current budget; a reviewer other than the requester approves it, and the approved request can then be turned into one draft purchase order, which is executed as a separate step. Requests can start from an approved submittal. The Accounting AP app supports bill matching with approved changes and receipts. Check exceptions and coding before approval; issuing a PO alone does not post a company expense. See Accounts payable.
FAQ
What is a purchase order in construction?
A purchase order is the contractor's written order to a supplier for materials, equipment rental or services. It states what is being bought, the quantity, the unit price, delivery details, and the job and cost code it's charged to. Once the supplier accepts it, it forms the contract for that purchase.
What is the difference between a purchase order and a subcontract?
A PO is generally used to buy goods, and sometimes simple services, with no work performed on site. A subcontract is used when the vendor performs work on site with its own labor, because it needs terms a PO usually lacks, such as scope, schedule, insurance, indemnity, retainage, lien waivers and flow-down of the prime contract.
Is a purchase order legally binding?
A PO is an offer to buy. It becomes a binding contract when the supplier accepts it, for example by signing, confirming or shipping. For the sale of goods in the US, the Uniform Commercial Code governs, and when the supplier's acknowledgment has different terms, UCC 2-207 decides which terms apply.
What is a blanket purchase order?
A blanket PO sets prices and a maximum amount for repeated purchases over a period, such as consumables or rental equipment, with deliveries called off as needed. It works only if it still lists unit prices, so each invoice can be checked.
How does a purchase order affect job cost?
Issuing a PO doesn't create cost. It creates a commitment, which shows the project manager money that's spoken for. The cost is recorded when the goods are received or the invoice posts, and the open commitment goes down by the same amount.