A submittal is a package the contractor or subcontractor sends to the architect or engineer to show exactly what it plans to furnish and install: shop drawings, manufacturer product data, samples, mock-ups, test reports or calculations. The design team reviews it against the design intent and returns it with an action such as “Approved,” “Approved as noted,” “Revise and resubmit” or “Rejected.”
The specifications decide which submittals a job needs, usually in Division 01 (Section 01 33 00, Submittal Procedures) and in the “Submittals” article of each technical section. The full list becomes the submittal register.
Types of submittals
| Type | What it is | Example |
|---|---|---|
| Shop drawings | Fabrication and installation drawings by the sub, fabricator or supplier | Steel connection details, duct layouts, curtain wall anchors |
| Product data | Manufacturer cut sheets, catalog data, performance ratings | Light fixture cut sheets, pump curves |
| Samples | Physical examples for color, texture or finish selection | Carpet tiles, brick, paint drawdowns |
| Mock-ups | Built assemblies reviewed in place or off site | A wall panel with window, flashing and finish |
| Informational | Test reports, certifications, calculations, qualifications | Delegated-design calcs stamped by the sub’s engineer |
| Closeout | Warranties, O&M manuals, attic stock lists | Equipment warranties and maintenance data |
How the review works
- The sub prepares the package from the spec section’s requirements and sends it to the GC.
- The GC reviews it. Under AIA A201 §3.12, the contractor must review and approve submittals before sending them on, checking field dimensions, materials, and coordination with other trades. Deviations from the documents must be called out in writing.
- The architect or engineer reviews it for conformance with the design intent, within the review period the contract sets. Consultants may review their own disciplines, which adds time.
- An action code comes back. Approved, or “no exceptions taken”: proceed. Approved as noted: proceed, incorporating the notes. Revise and resubmit: correct and send a new revision; don’t fabricate. Rejected: the item doesn’t meet the documents; start again. Some reviewers also return items “for record only” without approval.
- The sub orders and fabricates. Only once the action allows it. The approved submittal then becomes part of the record the owner keeps for operations and closeout.
The ball in court moves with each step, which is how teams see whether a late submittal is sitting with the sub, the GC or the designer.
What approval does and doesn’t mean
A submittal approval is not a change order. Under A201, the architect’s action doesn’t change the contract documents unless the contractor specifically identified a deviation in writing and the architect approved that specific deviation. Approval also doesn’t relieve the contractor of errors in the submittal itself. If the reviewer’s notes add scope, raise a potential change order instead of absorbing it, and if the design itself is unclear, ask with an RFI, not a submittal.
Worked example
Illustrative: the electrical switchgear must be on site August 2. The supplier quotes 16 weeks to fabricate and deliver after an approved submittal. The contract gives the architect 14 calendar days per review, and the GC allows itself 7 days for its own review.
- Release to fabrication: August 2 minus 112 days = April 12
- Submit to architect: April 12 minus 14 days = March 29
- Sub submits to GC: March 29 minus 7 days = March 22
- Allowance for one revise-and-resubmit round (7 days to revise, 14 days to re-review): March 22 minus 21 days = March 1
So the sub’s submit-by date in the register is March 1. If the package arrives March 22 and comes back revise and resubmit, the gear arrives about three weeks late, and if switchgear drives energization, the critical path moves with it.
Submittal vs RFI
The two are often confused because both go to the design team and both carry a ball in court. They run in opposite directions.
| Submittal | RFI | |
|---|---|---|
| Purpose | Shows what the contractor intends to furnish | Asks the designer what the documents mean |
| Who starts it | Usually the sub, through the GC | Usually the GC or a sub |
| Required by | The specifications, item by item | Whatever question comes up |
| Typical answer | An action code with review notes | A written clarification or instruction |
For when to send each one and how they connect to change events, see submittal vs RFI.
Why it matters
Most long-lead equipment can’t be ordered until its submittal is approved. A late submittal pushes procurement, and late procurement pushes the schedule even when field work is on time. Submittals are also a record: they show what was actually approved for installation, which matters for warranty, maintenance and any later dispute about what the contract required.
Common mistakes
- Building the submittal register late, after procurement deadlines have already passed.
- Passing a sub’s submittal to the architect without the GC reviewing it first.
- Treating “Approved as noted” as approved with no changes; the notes are binding.
- Hiding a substitution inside a submittal instead of flagging the deviation in writing.
- Releasing fabrication on a revise-and-resubmit response to save time.
How os.construction handles it
The Submittals tool holds the log with spec section, type, status, ball in court and due date. Each submittal can carry an ordered approval workflow; reviewers respond Approved, Approved as Noted, Revise and Resubmit, Rejected, Forwarded for Review or For Record Only, and a revise-and-resubmit response leads to a new revision with its own workflow. Draft submittals can be generated from spec sections, and delivery fields track lead time, required on-site date and confirmed and actual delivery. The log has queues for overdue reviews and resubmittals and a procurement follow-up that flags approved items whose release date (required on site minus lead time) is close or passed. An approved revision can be prepared into a purchase request, approved by a different reviewer and turned into a draft purchase order, and the request shows if that submittal is later superseded. A submittal can be tied to a scheduled activity, and the schedule’s constraints lookahead lists linked submittals that gate upcoming work.
FAQ
What is a submittal in construction?
A submittal is a document package a contractor or subcontractor sends to the architect or engineer showing exactly what it plans to furnish and install: shop drawings, manufacturer product data, samples, test reports or calculations. The design team reviews it for conformance with the design intent and returns it with an action such as approved, approved as noted or revise and resubmit.
What are the types of submittals?
The main types are shop drawings (fabrication and installation drawings prepared by the sub or fabricator), product data (manufacturer cut sheets, catalog pages and performance data), samples (physical examples of finishes or materials), and mock-ups. Specs also call for informational submittals such as test reports, certificates, calculations and qualifications, plus closeout submittals like warranties and O&M manuals.
What does approved as noted mean on a submittal?
Approved as noted (sometimes 'make corrections noted' or 'no exceptions taken with comments') means the contractor may proceed, but must incorporate the reviewer's notes. The notes are binding. If a note changes cost or scope beyond the contract documents, raise it promptly as a potential change rather than quietly building it.
Does an approved submittal change the contract?
Generally no. Under AIA A201, the architect's review of a submittal does not authorize a change in the contract documents unless the contractor specifically flagged the deviation in writing and the architect approved that specific deviation. Approval also doesn't relieve the contractor of responsibility for errors in the submittal.
Who reviews submittals first, the GC or the architect?
The general contractor reviews first. Under A201 the contractor must review, approve and submit shop drawings, product data and samples, confirming field dimensions, materials and coordination with other work. Only then does the architect review for conformance with the design intent. Passing a sub's package through unreviewed is a common and costly shortcut.
How long does submittal review take?
The contract sets it. Many specifications give the architect a fixed period per round, often around 10 to 14 days, sometimes longer for complex or engineered items. Build that time, plus the GC's own review and a likely resubmittal, into the submit-by date for every long-lead item.