Transmittal

Definition

A cover record that lists exactly which documents, drawings or samples were sent, to whom, when, how and for what purpose.

Topic: Field operations

Updated

A transmittal is the cover record for a package of documents sent from one project party to another. It lists each item, its revision and number of copies, who sent it, who it went to, the date, how it was sent (attached, or under separate cover) and what the recipient is asked to do with it. AIA publishes a standard form, the G810 Transmittal Letter, and many project specifications set their own.

The transmittal doesn’t change the documents it carries. Its job is evidence: months later, when someone says they never got revision 3 of the structural sheets, the transmittal log shows what was sent, to whom and when.

What goes on a transmittal

Field Why it matters
Number and date Gives the package an identity the log and later letters can refer to
From and to The sender, and every recipient, with copies noted separately
Items Each document, drawing, sample or file with its number, revision, date and number of copies
Sent via Attached, or under separate cover with the delivery method
Purpose Approval, review and comment, your use, as requested, or further processing
Action or response due The date a response is needed, when the contract sets a review period
Remarks Anything the recipient needs to know, such as superseded sheets to discard

How it works

  1. The package is assembled. The sender picks the exact items and revisions, not “latest drawings.”
  2. The transmittal is written with the items, recipients, purpose and any response date.
  3. The package goes out with the transmittal attached or referenced.
  4. Receipt is recorded where it matters, by acknowledgment or a delivery record.
  5. Responses are tracked against the purpose: a package sent for approval needs an answer; one sent for your use doesn’t.
  6. The log is kept for the life of the job and through closeout.
Record What it is What it proves
Transmittal Cover record for a package What the sender sent, to whom, when and why
Submittal Content for design review (shop drawings, product data, samples) What the contractor proposes to furnish
Acknowledgment or receipt Recipient’s signature or recorded receipt That the recipient got it
Meeting minutes distribution Who the minutes went to Who was told what was agreed

Why it matters

Review periods, notice periods and “issued for construction” status often run from the date documents were sent or received. Without a transmittal, the argument about whether a sub built from a superseded sheet comes down to memory. With one, it comes down to the record. Transmittals also hold closeout together: the owner’s O&M manuals, warranties and as-built drawings are usually handed over under a transmittal that lists every item.

Worked example

Illustrative: after an ASI revises three sheets, the GC sends Transmittal 0412 to the drywall and electrical subs. It lists A-201 revision 4, A-202 revision 4 and E-301 revision 2, one electronic copy each, sent attached, purpose “your use,” with a remark to discard revision 3. The electrical sub records receipt the same day; the drywall sub doesn’t. The project engineer follows up with the drywall sub before the framing crew lays out the revised walls, instead of finding the problem in the punch walk.

Common mistakes

  • Listing “updated drawings” instead of each sheet and revision.
  • Treating the transmittal as proof of receipt.
  • Leaving out the purpose, so nobody knows whether a response is expected.
  • Sending the transmittal to the sub’s office but not to the people building from the documents.
  • Keeping transmittals in email threads instead of a log someone can search.

How os.construction handles it

The Transmittals tool keeps a numbered log of transmittals with from, recipients, items, sent via (attached or under separate cover), submitted for (approval, your use, as requested, review and comment, or further processing), action-as-noted checkboxes and a Due By date. A package can start in Documents: you choose the exact document versions, and the transmittal keeps those captured versions even after newer ones are uploaded. A receipt follow-up view shows, for the sender, which To recipients haven’t recorded receipt and, for a recipient, what they still need to receipt, with anything past its Due By date flagged. Recorded receipt isn’t treated as approval or acknowledgment, and the tool records email in its local log rather than sending it. See Documents and drawings and submittals.

FAQ

What is a transmittal in construction?

A transmittal is a cover sheet or record that goes with documents sent between project parties. It lists each item sent (drawing numbers, revisions, specifications, product data, samples), the number of copies, the date, the sender and recipients, how the items were sent and what the recipient is asked to do with them, such as approve, review and comment, or keep for their use.

What is the AIA transmittal form?

AIA publishes the G810, Transmittal Letter, a standard form for recording information exchanged between project parties during design and construction. Many specifications, especially on public work, name the transmittal form they expect.

Is a transmittal the same as a submittal?

No. A submittal is the content the design team reviews, such as shop drawings or product data. A transmittal is the cover record that sends a package, which may be a submittal, a drawing set, an O&M manual or anything else, and records what went and why.

Does a transmittal prove the recipient received the documents?

Not by itself. It proves what the sender says was sent. Receipt is shown by a signed or recorded acknowledgment, a delivery confirmation, or the recipient's own record. Track receipt separately when it matters, for example for drawing revisions issued for construction.

When should you use a transmittal?

Whenever a document leaves your company and someone may later ask what was sent and when: submittals to the architect, revised drawings to subcontractors, closeout documents to the owner, and anything with a review or response period that starts on receipt.