Esc

↑↓ move↵ openIndex · Pagefind
Accounting

General conditions

Definition

In construction, either the contract document that sets the parties' general rights and duties (such as AIA A201), or the job-specific costs of running the site that aren't tied to one trade: staff, field office, temporary facilities and cleanup.

Topic: Accounting & WIP

Updated

The two meanings of general conditionsGeneral conditions splits into two meanings. The contract meaning: the general conditions document, such as AIA A201 or EJCDC C-700, which sets the rules for changes, payment and claims. The cost meaning: jobsite overhead such as staff, the field office and temporary utilities, which is driven by time. Below, a bar of monthly general conditions cost grows month by month, and an illustrative six-week delay adds about 277,500 dollars at 185,000 dollars a month.General conditionsTHE CONTRACTAIA A201rules: changes,pay and claimsTHE COSTJob overheadstaff, trailer,temp utilitiesCOST GROWS WITH TIME1 bar = 1 month of GCsdelay+6 weeks ≈ +$277,500illustrative
Same words, two meanings. The cost meaning runs by the month, so a schedule slip is a general conditions overrun.

General conditions in construction means one of two things. In contracts, it is the document that sets the general rights, duties and procedures of owner, contractor and architect, such as AIA A201-2017. In estimating and job cost, it is the contractor’s job-specific cost of running the site that isn’t tied to a single trade: project staff, the field office, temporary facilities and cleanup.

The two meanings are related but different, and people switch between them in the same meeting. “Check the general conditions” usually means read A201 or the owner’s equivalent. “Our general conditions are $185,000 a month” means the site cost. When it matters, say which one.

Meaning 1: the general conditions of the contract

Most construction contracts are a set of documents. The agreement (for AIA, A101 for a stipulated sum or A102 for cost plus a fee with a GMP) sets the price, the time and the parties. The general conditions set the rules everyone works under. The supplementary conditions modify the general conditions for this project and this owner. The drawings and specifications describe the work.

AIA A201-2017, General Conditions of the Contract for Construction, is the most widely used set in US private building work. Its 15 articles cover:

Articles What they govern
1-4 General provisions, and the roles of owner, contractor and architect
5-6 Subcontractors, and work by the owner or separate contractors
7-9 Changes in the work, time, payments and completion
10-12 Safety and protection, insurance and bonds, uncovering and correcting work
13-15 Miscellaneous provisions, termination or suspension, claims and disputes

Article 7 is where the change documents live: change orders, construction change directives and the architect’s minor changes. Our guide from RFI to change order walks through them.

Other families have their own: EJCDC C-700 Standard General Conditions on engineered and public works projects, ConsensusDocs (whose 200 standard agreement folds the general conditions into the agreement), and federal contracts, which use FAR clauses in place of a separate general conditions document. Public owners often write their own. AIA A201 vs ConsensusDocs 200 compares the two most common private families.

In CSI MasterFormat, the general and supplementary conditions sit in Division 00, Procurement and Contracting Requirements. Division 01, General Requirements, is the specification division for administrative and temporary requirements: submittal procedures, quality control, temporary facilities, cleaning and closeout. That is why the cost meaning drifted toward “general requirements” and “Division 01 costs”.

Meaning 2: general conditions costs

General conditions costs are the contractor’s jobsite overhead: what it costs to run this project, apart from the trade work itself. Contractors usually code them to Division 01 cost codes. A typical list:

  • Staff: project manager, superintendent, assistant superintendents, project engineers and project accountants, to the extent their time is charged to the job.
  • Field office: trailer rental, furniture, phones, internet, copiers and supplies.
  • Temporary facilities and utilities: power, water, heat, toilets, fencing, hoists, temporary roads and protection.
  • Cleanup: dumpsters, daily cleanup labor and final cleaning.
  • Safety and small tools: safety equipment, signage, first aid and consumables.
  • Job-specific costs the contract allows: permits, testing the contractor carries, project insurance or builder’s risk, and surveying.

Not everything belongs here. Home-office overhead, such as executives, accounting staff and office rent, supports every job and is usually recovered through the fee or markup.

General conditions vs general requirements

Construction managers often split the cost bucket in two:

General conditions General requirements
Typical items Site staff, field office, vehicles Temporary facilities, cleanup, hoisting, protection
What drives cost Time on the job Quantity of work and site needs
Often priced as Monthly rate or lump sum Lump sum or per item
Where it shows Its own line or part of the fee Division 01 lines in the SOV

The split matters on a GMP or cost-plus contract, where the agreement decides which items are reimbursable cost, which are covered by the fee, and which are capped. AIA A102-2017 defines the reimbursable cost of the work in detail, and owners frequently negotiate general conditions as a fixed monthly amount or lump sum so they can’t grow with the job.

Why it matters

General conditions are mostly time-driven. When the schedule slips, the superintendent, trailer and temporary utilities keep running, and that cost comes straight out of margin unless the delay is compensable. That makes them the core of most delay claims: the contractor claims “extended general conditions” for the added duration. They are different from unabsorbed home-office overhead, which some jurisdictions calculate with the Eichleay formula.

On owner-side reviews, general conditions are one of the first lines checked. Owners look at whether they are front-loaded on the schedule of values, whether staff is charged at agreed rates, and whether the same item appears both in general conditions and in the fee.

How to estimate general conditions

  1. Start from the schedule. Duration in months is the main driver. Build staffing by phase: a superintendent for the whole job, an assistant during peak months, a project engineer from buyout through closeout.
  2. Price time-related items monthly. Staff at burdened rates, trailer, utilities, phones and vehicles, times the months they are needed.
  3. Price fixed items once. Mobilization, trailer setup, fencing, final cleaning and demobilization.
  4. Price quantity-related items from the work. Dumpsters and cleanup scale with trade activity; hoisting with floors and duration.
  5. Check against the contract. Remove items the contract puts in the fee or excludes, and match the owner’s required breakdown.

Building them as a percentage of trade cost is a common shortcut, and the reason general conditions so often run over: a percentage doesn’t know the schedule is two months longer than last time.

Worked example

Illustrative: Riverside Medical Center carries general conditions of $185,000 a month for staff, trailers, temporary facilities and cleanup. A six-week delay costs about $277,500 ($185,000 × 1.5). On a $49.3M contract, that alone fades projected margin by about 0.56 points, from 11.4% to roughly 10.8%, unless some of it is recovered through a change order or a claim for extended general conditions.

Common mistakes

  • Budgeting general conditions as a percentage of cost instead of building them from duration.
  • Mixing them with company overhead, which makes job margins hard to compare.
  • Not tracking time-related costs by month, so there is nothing to support an extended general conditions claim.
  • Pricing a change order’s direct cost but not its time-related general conditions when the change extends the schedule.
  • Reading “general conditions” in a meeting as cost when the other person meant the A201 document, or the reverse.

General information, not legal or accounting advice. Your agreement, its general and supplementary conditions, and the law where the project sits decide what is reimbursable and how delays are compensated.

For a full worked estimate with staffing, monthly site costs and the burn rate, see how to calculate general conditions costs.

How os.construction handles it

You can code general conditions to their own cost codes in the budget, so cost to date, commitments and the forecast for staff, field office and temporary facilities show separately from trade work, and the schedule shows the duration they depend on. Linking general conditions budget lines to the schedule, so a slip shows its cost impact in the forecast automatically, is in development.

FAQ

What are general conditions in construction?

The term has two meanings. In contracts, the general conditions are the document that sets the general rights and duties of owner, contractor and architect, such as AIA A201-2017. In estimating and job cost, general conditions are the contractor's job-specific costs of running the site that don't belong to one trade: project staff, the field office, temporary utilities, cleanup and similar items.

What is included in general conditions costs?

Typically the project manager, superintendent and project engineer time charged to the job, the site trailer and its furnishings, temporary power, water, toilets and fencing, dumpsters and cleanup, small tools, safety equipment, job-specific insurance and permits where the contract puts them there, and final cleaning. The contract decides exactly which items count, especially on cost-plus and GMP work.

What is the difference between general conditions and general requirements?

In MasterFormat, Division 01 is called General Requirements and covers administrative and temporary-facility requirements in the specifications, while the general conditions document sits in Division 00. In cost terms, many construction managers use general conditions for time-related staff and field office costs and general requirements for task-related Division 01 items such as temporary facilities and cleanup. Usage varies, so the contract's definitions control.

What is the difference between general conditions and overhead?

General conditions are job overhead: costs incurred because this particular project exists, charged to its job cost. Company or home-office overhead, such as the accounting department, office rent and executives, supports every project and is usually recovered through the fee or markup. Mixing the two makes job margins hard to compare.

What is AIA A201?

AIA A201-2017, General Conditions of the Contract for Construction, is the American Institute of Architects' standard general conditions. Its 15 articles cover the owner, contractor and architect, subcontractors, changes in the work, time, payments and completion, insurance and bonds, correction of work, termination and claims. It is used with an owner-contractor agreement such as A101 or A102 and is usually modified by supplementary conditions.

How are general conditions billed?

It depends on the contract. On lump-sum work they are usually spread across the schedule of values or shown as their own line. On cost-plus and GMP contracts they may be reimbursed at actual cost, billed as a fixed monthly amount, or carried as a negotiated lump sum. Front-loading them early in the job is a common owner concern.

Sources

Keep exploring

Related across os.construction

Open file