Get started with the schedule Planner
Create a CPM plan, add activities, logic and a calendar, save and calculate your first version, then read the critical path and run a health check.
This guide takes you from an empty plan to a calculated, analysed schedule in about fifteen minutes. To start faster from a construction template, a copy of another project or a P6 or Microsoft Project file, see Create a schedule.
Build and calculate a plan
- Open the Planner. Go to Project Tools › Schedule and choose Planner. A new plan starts with today as both the planned start and the data date, and one calendar, Standard weekdays (Monday to Friday, 8 hours a day).
- Set the plan dates. Give the plan a name, and set the planned start, the data date and an optional must finish by date. A must finish by date gives late dates a hard end, so float becomes negative if the logic can’t meet it.
- Add the WBS outline. Add WBS summaries for the phases or areas you schedule by, and nest them as deep as you need. Each activity points at its Activity summary.
- Add activities. For each one, enter an ID, a name, a kind (task, start or finish milestone, level of effort or WBS summary), a calendar and a working duration in days. Milestones are zero duration.
- Add the logic. Add dependencies between predecessor and successor IDs: FS, SS, FF or SF, with a lag in days, or a negative lead. Give every activity a predecessor and a successor, except the project start and finish.
- Add constraints only where the contract requires them. Each activity takes a primary and a secondary constraint. Constraints override logic, and the DCMA health check counts hard ones.
- Save and calculate. Saving runs the engine first. Only a successful calculation creates a new version, and the version and its calculation are saved together. If someone else saved since you loaded the plan, the save is refused and nothing is lost: reload, then reapply your change.
Read the result
After the calculation, the grid shows early and late dates, total float and free float, and the critical flag for every activity. Turn on longest path focus to follow the longest path: the single driving chain to the finish. In the Gantt, critical bars are drawn with a distinct border as well as colour, and the data date line marks the status cutoff. Select any activity and ask Why this date? to see the trace of predecessors, constraints and calendars that put it there. See Activity grid and Gantt.
Check it, then baseline it
- Run Health. Open Analysis › Health (DCMA 14). Fix what it flags: open ends, leads, long lags, hard constraints, high float and high durations. Then save again. See Schedule analysis.
- Name a baseline. When the plan is agreed, name the saved version as a baseline. It’s a frozen reference to that exact version. See Baselines and versions.
- Status it each period. Move the data date. Record actual starts, actual finishes and remaining durations, then save. Compare the new version with the baseline, and measure SPI(t) with Earned Schedule.
A first plan worth baselining
- Every activity has a predecessor and a successor, apart from the start and finish milestones.
- Constraints appear only where a contract date requires them.
- Durations are short enough to status, usually 44 working days or less.
- The longest path runs from the start milestone to the finish milestone without gaps.
- Health shows no negative float you can’t explain.
Next steps
- Planning and CPM covers every input the engine reads.
- Resources and costs adds cost loading, histograms and leveling proposals.
- CPM analytics in Insights shows the plan’s health across your portfolio.
Keep exploring
Related across os.construction
- DocsReports, print Gantt, scheduled emails and the schedule assistantRun twelve P6-style schedule reports to CSV, XLSX or PDF, print a tiled Gantt PDF on tabloid or A3, email any of them on a daily, weekly or monthly schedule, and, where your company has turned it on, ask the schedule assistant questions answered only from cited, saved schedule facts.
- DocsScheduling: CPM planning, analysis and evidence in one workspaceA native critical path scheduling workspace with a P6-validated engine, P6-style layouts and views, Line of Balance and takt planning, Last Planner weekly work plans, activity discussion and a change feed, P6 import options, DCMA health, three-point risk, a reviewed update cycle, portfolio programs, reports, baselines, versions, resources, costs and period performance.
- GlossaryLongest PathThe chain of driving relationships from the data date to the project finish; it can differ from the set of activities with zero total float.
- GlossaryRetained LogicA progress setting where an out-of-sequence activity's remaining work still waits for its unfinished predecessors.
- ExplainerHow the critical path worksForward pass, backward pass and float on an eight-activity network, then one slip moves the critical path.
- Free toolConstruction schedule (Gantt) templateFree construction schedule template for Excel.
Was this helpful?
Run it on your own project.
Start a 14-day free trial. Want a say in what ships next? Join the founding program.
14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →