Using the app / Review every project from the Portfolio page

Review every project from the Portfolio page

Run a weekly portfolio review: read the company totals, find the jobs with overdue items and thin commitment coverage, group jobs into programs, and know exactly how each number is counted.

Preview

Partly in the app today. Items marked Planned are not built yet.

On this page

Portfolio is one table of every project you can see, with open items and cost roll-ups side by side and a company total at the bottom. It is the quickest way to answer “which jobs need me this week?” before you open any one of them.

Open it at /companies/{company}/portfolio.

What you see

Company totals come first, in two rows:

  • Projects (active / all), Open RFIs, Open submittals, Open punch, Open observations and Overdue items (with “of N open”).
  • Original budget, Committed (with % of budget), Change orders and Projected.

Then the Projects table, one row per project, with the same columns plus Stage, and a Company total row. Inactive (archived) projects stay on the list with an inactive tag. Under the table is Programs.

How each number is counted

Read these before you act on a number. They are the exact rules the page uses.

Column Counts
RFIs RFIs with status Open
Submittals Submittals that are Open or Revise and Resubmit
Punch Punch items in any status except Closed
Obs. Observations that are Initiated, Ready for Review or Not Accepted
Overdue Open RFIs, submittals and observations past their due date. Punch items are not included.
Orig. Budget Sum of original budget amounts on the budget lines
Committed Sum of line items on commitments that are not cancelled
Change Orders Sum of line items on every potential change order (PCO) that isn’t deleted, whatever its status, so pending and unapproved PCOs count
Projected Original budget + Change Orders

Who sees what

  • Company admins see every project. Everyone else sees only projects they are on.
  • Counts follow each tool’s privacy rules, so a private RFI you can’t open isn’t counted for you.
  • Original budget needs Budget view access with the Budget tool turned on. Committed and Change orders need permission to read the contracts behind them. If any of that is hidden from you, the amount shows Unavailable, and a notice says the financial totals are partial. Unavailable never shows as zero.

Two people can therefore see different totals on the same page.

Run a 15-minute weekly review

  1. Start with Overdue items

    Look at the company Overdue items tile and its “of N open” line. Then scan the Overdue column. Any row in red is a job with RFIs, submittals or observations past due.

  2. Open the job and find the owner

    Project names on Portfolio are not links. Open the job from the company home, then use My Open Items or the tool’s list filtered to overdue to see who has the ball. See Find anything: search and open items.

  3. Check commitment coverage

    Compare Committed to Orig. Budget on each active job. A job deep into construction with a low committed share usually means buyout is behind, or work is being bought without commitments in the system.

  4. Look at Change Orders against budget

    Because the column includes pending PCOs, a big number here is exposure as well as approved change. Open the job’s change orders to split pending from executed.

  5. Note it, assign it, move on

    Make a task for each follow-up in the project, so it shows up in the owner’s open items. Next week, the same rows should be smaller.

Worked example

Illustrative. Three active jobs:

Project Overdue Orig. Budget Committed Change Orders Projected
24-118 Riverside Medical 7 $42,640,000 $36,800,000 $1,160,000 $43,800,000
24-125 Mill Street Expansion 0 $6,200,000 $1,100,000 $40,000 $6,240,000
24-131 Harbor Point Dental 2 $390,000 $305,000 $0 $390,000

How to read it:

  • Riverside has the overdue items. Start there.
  • Mill Street has only 18% committed. If it is past mobilization, ask the PM about buyout.
  • Riverside’s $1.16M of change orders includes pending PCOs. Don’t quote it as approved change to the owner.

Group jobs into programs

A program groups projects (a campus, a client’s rollout, a region) and shows combined Overdue, Orig. budget, Committed, Change orders and Projected.

Company admins choose + New program, enter a Program name, an optional Description, tick the Projects, and choose Create program. Each program card can be deleted by an admin. Program totals follow the same visibility rules as the table.

Common mistakes

  • Mistake: Reporting Projected as the forecast cost

    In the app: Projected is original budget plus all PCO amounts. Use the Budget & cost pack for EAC and over/under.

  • Mistake: Assuming zero overdue means punch is on track

    In the app: Overdue excludes punch items. Check the Punch column and the punch list itself.

  • Mistake: Comparing your totals with a colleague's

    In the app: Totals depend on who is looking. Company admins see every project; others see their own.

  • Mistake: Reading Unavailable as nothing committed

    In the app: Unavailable means you can't read the contracts. Ask for access or ask someone who has it.

Weekly portfolio review

  • Company Overdue items noted and compared with last week
  • Every job with overdue items has a named owner and a task
  • Committed vs original budget checked on jobs in buyout
  • Pending PCO exposure confirmed on jobs with large Change Orders
  • Programs reflect current client groupings

Terms on this page

RFI · Submittal · Punch list · Commitment · Potential change order · Estimate at completion

Next steps

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file