A potential change order (PCO), also called a change order request (COR) or proposed change order, is the contractor’s priced proposal for a change. It usually includes the scope description, labor, material, equipment and subcontractor costs, markups, and any requested time extension. The owner reviews it, negotiates, and either approves it into a change order, rejects it, or directs the work with a construction change directive.
How it works
- A change event arises. An RFI answer, an ASI, a bulletin, a field condition or an owner request alters the work. The contractor logs it as a change event and gives any notice the contract requires.
- Pricing. The contractor collects sub and supplier quotes, prices self-performed work, and applies the contract’s markup rules. On AIA projects the architect may issue a proposal request (AIA G709) that asks for exactly this.
- Time. If the change affects the schedule, the PCO requests a time extension, supported by a fragnet or a time impact analysis.
- Submission and negotiation. The owner’s team reviews scope, quantities, rates and markup. Questions and revisions go back and forth.
- Outcome. Approved PCOs become a change order. Rejected ones are closed or pursued as claims. If the work can’t wait, the owner can issue a construction change directive and settle the price later.
Several approved PCOs are often rolled into one change order to reduce paperwork, with each listed separately.
Worked example
Illustrative: for the fire dampers found through RFI-212, the GC on Riverside Medical Center submits a PCO: mechanical sub quote $68,000, GC supervision $6,500, fire-stopping $3,600, subtotal $78,100, plus $8,300 of markup per the contract (about 10.6%: $6,014 of OH&P and sub markup, $2,286 of insurance and bond), total $86,400. The owner approves it as CO #14.
The PCO log for that month shows why tracking matters:
| PCO | Description | Amount | Status | Work done? |
|---|---|---|---|---|
| 031 | Fire dampers (RFI-212) | $86,400 | Approved as CO #14 | In progress |
| 032 | Added floor boxes, L2 | $14,200 | Pending | Complete |
| 033 | Owner-requested door relocation | $6,750 | Pending | Not started |
| 034 | Rock excavation | $41,000 | Disputed | Complete |
PCO 032 and 034 are $55,200 of finished work the contractor can’t yet bill. That’s real cost with uncertain revenue, and it belongs in the cost forecast and the WIP review whether or not the owner has signed.
PCO vs related documents
| Document | Who issues it | What it does |
|---|---|---|
| Change event | Contractor, internally | Logs a possible change before pricing |
| Proposal request | Owner or architect | Asks the contractor to price a possible change |
| PCO / COR | Contractor | Prices a change and asks for approval |
| Change order | Owner and contractor together | Changes price, time or scope by agreement |
| Construction change directive | Owner, often with the architect | Orders the work before price or time is agreed |
| Field order | Architect, engineer or owner’s rep | Directs minor work right away, with any price or time settled afterwards |
Why it matters
The PCO is where entitlement and price get argued. A clear PCO with backup gets approved faster, which means faster billing. Pending PCOs are also a key forecasting number: work already performed on unapproved PCOs is a real cost with uncertain revenue. On lump sum work in particular, a change that never makes it into a PCO is absorbed by the contractor.
Common mistakes
- Submitting PCOs without backup (quotes, T&M tickets, a time impact analysis).
- Bundling unrelated items so one disputed item holds up the rest.
- Not forecasting the cost of pending PCOs that the field is already building.
- Missing the contract’s notice deadline while the price is still being worked out.
- Leaving time out of the PCO, then struggling to raise it after the change order is signed.
For pricing method and markup, see how to price a change order and change events vs change orders.
How os.construction handles it
A PCO is created from its change event and copies the priced line items, and RFQs collect sub pricing on the same event. Pending owner changes show in the budget’s Pending Budget Changes until the PCO is approved and executed. See Change events and change orders.
Watch the explainer · 1:54
Change event vs change order
- 0:00A maybe vs a contract
- 0:18Log the event early
- 0:37Protect the notice clock
- 0:54Price it on one contract
- 1:11One change, several numbers
- 1:31Changes in os.construction
Read the transcript
A change event is a maybe. A change order is a contract. The change event records that something may change cost, scope or time. The change order is the signed amendment that fixes the price and time. Many events never become change orders.
Log the change event the day it shows up: an RFI answer that adds work, an owner request, a hidden condition. Mark the scope as in, out, or to be determined, and enter a rough order of magnitude, or ROM, by cost code. It's an early estimate, not a price.
If it may be a change or a claim, give written notice within the contract's deadline. The AIA A201-2017 general conditions use twenty-one days for claims, and your contract may be shorter. Logging the event early keeps you inside that window, while the record is fresh.
Next, get quotes from the subs, then create a potential change order, or PCO, against one contract. A PCO on the prime contract carries the revenue side. One on the subcontract carries the cost side. The PCO is where markup is added.
Here's an illustrative change. The event's ROM is four thousand eight hundred fifty dollars. The awarded quote comes in at five thousand three hundred. The PCO adds ten percent markup, for five thousand eight hundred thirty. Only once it's approved and executed does the contract change, and only then can you bill it.
In os.construction, quotes and PCOs made from a change event link back to it, and approved PCOs are executed in packages. Pending prime PCOs show as pending changes in the budget, approved ones as approved changes, and executed ones land on line two of the pay app.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a PCO in construction?
A PCO, or potential change order, is the contractor's priced proposal for a change to the contract. It describes the changed scope and its cost, markup and any time impact, with backup. The owner reviews it and either approves it into a change order, rejects it, or directs the work by construction change directive while the price is settled.
What is the difference between a PCO and a change order?
A PCO is a proposal; a change order is the signed agreement that changes the contract price, time or scope. The contractor can't bill a PCO. Once the owner and contractor agree and sign, the PCO becomes, or is rolled into, a change order that can be added to the schedule of values and billed.
Is a PCO the same as a change order request?
Usually, yes. Potential change order, change order request (COR), proposed change order and change proposal are different labels for the contractor's priced proposal. On US federal contracts, a request for equitable adjustment (REA) plays a similar role for changes the contractor believes it's entitled to. Check what the contract calls it, because notice and submission rules refer to its terms.
What should be included in a PCO?
A description of the change and what caused it, references to the RFI, ASI, bulletin or directive, a breakdown of labour, material, equipment and subcontractor costs, markups per the contract, any requested time extension with schedule support, and backup such as sub quotes and T&M tickets.
How long does an owner have to respond to a PCO?
Only as long as the contract says. Many contracts set response periods or allow the owner to issue a construction change directive if the price isn't agreed. Where the contract is silent, follow up in writing and track the PCO's age, because unapproved work can't be billed.
