Activity grid and Gantt: views, longest path and date traces
Work in the activity grid with quick filters, sorts and deep links, read the Gantt from day to year with float, progress, baseline and longest-path focus, and trace why any activity is on its date.
On this page
The Planner shows a saved, calculated plan two ways: an activity grid for numbers and a Gantt for time. Show them side by side in Grid + Gantt, one at a time, or switch to the Activity Network. Switch between them and the selection, filters, sort, grouping and collapsed groups come with you. Nothing you do in either view reorders or changes the saved plan.
Activity grid
Columns, filters, Group & Sort and layouts
The grid uses the Planner’s views and layouts: a columns dialog with 45 core columns, baseline, cost, units and earned value columns, and your activity codes and UDFs, default and user-defined filters with nested All/Any criteria and a highlight mode, Group & Sort to five levels with group and grand totals, and layouts saved for yourself, the project or the company. The quick filters below sit on top of whatever layout is open, and an N of M activities count shows how much you’re looking at.
Percent complete shows the duration percentage you entered, otherwise the physical percentage. A completed activity without either shows 100%. The baseline columns need a baseline chosen for the Gantt.
Quick filters
- Text search on ID, name or code.
- Critical, near-critical (up to a total float you set) and negative float.
- Milestones, unfinished work, and status: not started, in progress or completed.
- Constraint present and open ends: activities with no predecessor (other than start milestones) or no successor (other than finish milestones).
- WBS branch, including everything beneath it.
- Date window or look-ahead, and longest-path focus.
An activity whose calculated value is unknown never passes a calculated filter, so a filter never hides a missing number by mistake.
Sort
Click any column header to sort by it. Shift+click adds up to four sort keys, or reverses a key that’s already in the sort. Unknown values always sort last, and ties keep the authored order.
Deep links
Link straight to an activity with planner?activity=<id>. The Planner selects it, opens it in the editor and scrolls it into view. Schedule analysis uses these links for offenders, drivers and changed activities. If a filter hides the linked activity, the Planner tells you rather than quietly clearing the filter.
Large schedules and the keyboard
Rows are windowed, so only the rows on screen are drawn and even a 20,000-activity schedule scrolls smoothly. Up, Down, Page Up, Page Down, Home and End move the selection through the displayed order and keep it in view. Sortable headers announce their sort direction to screen readers.
Gantt
- Timescales: day, week, month, quarter and year presets, plus zoom in and out (keeping the centre date), Fit schedule and Find selected activity.
- Date lines: the data date line and a today line, each labelled on the axis.
- Bars and milestones: milestones are diamonds. Critical bars use a distinct border as well as colour, so they read without colour. Turn critical colouring off to see every bar in one neutral style.
- Progress fill shows percent complete as a share of each bar.
- Total float bars run from early finish to late finish. Negative float runs backwards above the bar in the risk colour.
- Dependency arrows for FS, SS, FF and SF links, with lag labels. Show links for the selected activity (the default), for all activities, or none. Up to 500 paths are drawn, and links that run off-screen are counted rather than lost.
- Summary bars: WBS brackets span each summary’s earliest start to latest finish, even when filters hide some children. Other groupings draw group bars too.
- Drag to edit: drag a bar to move it, or its end to change the duration. The move mode decides whether a move sets a constraint or a lag. Alt+arrow keys do the same from the keyboard.
- A legend lists every mark in use.
- Keyboard: with the timeline focused, Up, Down, Home and End move the selection and keep it in view.
Longest-path focus
Longest path focus follows the engine’s own ordered driving chain to the project finish. It’s separate from the critical filter: in a multi-calendar or constrained schedule, the activities with zero float and the chain that drives the finish can differ. If the chain is missing or stale for the plan on screen, focus is withheld with an explanation rather than guessed. See longest path.
Baseline overlay
Choose Show baseline on Gantt to draw one named baseline as outlined bars under the current bars. The baseline bars come from the baseline version’s original saved calculation. They’re display only, and they’re hidden while you have unsaved edits.
Date windows and look-ahead
Set an inclusive from and through date to focus on a window, or a look-ahead of 1 to 3,650 days. A look-ahead starts at the data date, leaves out completed work, and replaces any explicit window. A 21-day look-ahead is the classic three-week look-ahead.
Why this date? Date traces
Select an activity and choose Why this date? The engine traces what put it there:
- The chain of driving predecessors behind the activity, with relationship types and lags.
- The bounds that applied: the driving bound and the others that didn’t win.
- The steps after it, toward the finish.
A trace separates the chosen longest-path chain, the wider set of tied drivers, and activities that merely have zero float. You can override the data date for a trace.
- Run a trace on the saved version. Creating a trace never changes a date.
- See it highlighted. The selected activity, the chain leading to it and the steps after it are highlighted in both the grid and the Gantt. Highlighting appears only when the plan is clean and the trace matches the current version, data date and calculation.
- Keep it. Every trace is retained as an immutable record with its provenance. Reopen it from history, download it, or run one against an earlier version.
Limits
- Dragging a bar sets a start-no-earlier-than constraint or a predecessor lag, depending on the move mode. It never types a date into the activity. See Gantt.
- Show baseline on Gantt overlays one baseline. For up to three baseline bars, assign Primary, Secondary and Tertiary baselines and use the bar list. See Baselines.
- With unsaved edits, the Gantt shows the last calculation as a faded reference, and new traces wait until you save.
- See What’s not here yet for the P6 view features still to come. Fill down, Excel paste, Global Change and Progress Spotlight are in Editing and progress tools.
Keep exploring
Related across os.construction
- DocsViews and layouts: filters, Group & Sort, columns, Network and Trace LogicOpen and save P6-style layouts for yourself, the project or the company, export and import them as files, build filters with nested All/Any criteria and highlight mode, group and sort to five levels with totals, choose from 45 core columns plus baseline, cost, units and earned value columns, draw a progress line, read the logic in the Activity Network, Trace Logic and Assignments views, and roll the plan up in the WBS window.
- DocsP6 compatibility: settings, import, export and what round-tripsHow closely os.construction matches Primavera P6. Which scheduling settings the engine honours, which P6 calculated fields it works out, what crosses an XER or P6 XML file in both directions, the measured agreement with P6's own dates and costs, and the limits that remain.
- GlossaryCritical PathThe driving sequence of activities that determines a selected completion milestone under the schedule's logic, calendars, and settings.
- GlossaryGroup & SortA schedule view setting that bands activities by WBS, activity code or any field, up to several levels, with totals per band and a sort order within each band.
- Free toolConstruction schedule (Gantt) templateFree construction schedule template for Excel.
- Free toolCritical path calculatorForward and backward pass, total and free float and the critical path for your activities, with every step shown.
Was this helpful?
Run it on your own project.
Start a 14-day free trial. Want a say in what ships next? Join the founding program.
14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →