Esc

↑↓ move↵ openIndex · Pagefind
Topic · 15 terms

Closeout and turnover: punch list to certificate of occupancy

Closeout is where a job earns its last dollars: the retainage, the final payment and the warranty start date all hang on proving the work is done and the paperwork is complete.

The sequence usually runs substantial completion, punch list, inspections and commissioning, temporary and final certificates of occupancy, turnover documents (as-builts, O&M manuals, warranties), final completion and retainage release.

Read the guide: Closeout to occupancy: punch, Cx, as-builts, TCO and CO

Closeout & turnover: terms defined

Contracts

Substantial Completion

The point when the work is complete enough for the owner to occupy or use it for its intended purpose.

Field

Punch List

The list of incomplete or defective items that must be fixed before the owner accepts the work and final payment is released.

Field

Inspection Checklist

A list of items checked before work is covered or accepted, answered pass, fail or not applicable, so quality checks are the same every time.

Project management

Commissioning (Cx)

A quality process that verifies building systems are designed, installed, tested and operating to meet the owner's requirements.

Field

Building Permit

Written permission from the local building authority to construct, alter or demolish a building, issued after plan review and subject to inspections and conditions.

Project management

Temporary Certificate of Occupancy (TCO)

A time-limited certificate from the building department that allows all or part of a building to be occupied before every item is finished, as long as occupied areas are safe.

Project management

Certificate of Occupancy (CO)

The document a local building authority issues stating a building complies with codes and approved plans and may legally be occupied.

Field

As-Built Drawings

Drawings marked up to show how the project was actually built, including every field change from the original design.

Project management

O&M Manuals

Operation and maintenance manuals: the closeout documents that tell the owner how to run, maintain and repair the building's equipment and systems.

Project management

Warranty Period

The time after completion during which the contractor must correct defective work, typically one year from substantial completion plus any longer manufacturer or specified warranties.

Project management

Closeout

The final phase of a project: work finished, documents delivered, final payments and lien waivers exchanged, and the job closed financially.

Contracts

Final Completion

The point when all contract work, punch list and closeout requirements are done and final payment becomes due.

Contracts

Notice of Completion

A recorded notice that a private project is complete, which in many states shortens the deadline for contractors, subs and suppliers to record mechanics liens.

Billing

Retainage Release

Billing and paying out the retainage held on a contract, usually at substantial or final completion, once the contractual conditions are met.

Project management

Lessons Learned

What completed work shows about how long similar work really takes, recorded so the next plan starts from evidence rather than habit.

Open file