Building Permit

Definition

Written permission from the local building authority to construct, alter or demolish a building, issued after plan review and subject to inspections and conditions.

Part of: Closeout to occupancy: punch, Cx, as-builts, TCO and CO

Topic: Closeout & turnover · Field operations

Updated

A building permit is the local authority’s written permission to do the work shown in an approved application and set of plans. It’s issued after plan review, it comes with conditions, and it has to be kept alive: inspections at each stage, conditions met on time, and an expiration date that can arrive sooner than people expect. The permit is what the final inspections and the certificate of occupancy are measured against.

Codes are adopted and amended locally, so the rules below are typical, not universal. Check the adopted code and the building department for the specific project.

How it works

  1. Application. The permit applicant submits the application, plans and fees. Who applies depends on the contract and local rules.
  2. Plan review. The authority reviews the plans and issues comments. Corrections are resubmitted until the plans are approved.
  3. Issuance. The permit is issued, often with conditions: special inspections, deferred submittals, other agency sign-offs.
  4. Inspections. Work is inspected at set stages (footings, framing, rough-ins, insulation, final) before it’s covered or used.
  5. Keeping it valid. Activity rules and expiration dates are watched, and renewals or extensions are requested before they lapse.
  6. Final and closure. Final inspections pass, conditions are signed off, and the authority issues a certificate of occupancy or closes the permit.

Expiration rules vary

Example Rule
Model IBC Section 105.5, as adopted in Massachusetts (780 CMR 105.5) Invalid if work doesn’t start within 180 days of issuance, or is suspended or abandoned for 180 days; written extensions of up to 180 days each
New York City, DOB NOW: Build Expires at the earliest of the general liability, disability or workers’ comp insurance expiration, the license expiration, or one year from issuance

The New York City rule is a reminder that a permit can depend on other records. If the permit holder’s insurance lapses, the permit can lapse with it.

Why it matters

Work without a valid permit can be stopped, may have to be opened up for inspection, and can delay occupancy. Missed conditions surface at the worst time, at final inspection, when the owner is waiting to move in. Permit and inspection dates also belong in the schedule: a final inspection that can’t be booked until a condition is cleared is a critical path risk like any other.

Worked example

Illustrative: a tenant improvement permit is issued on March 3 with three conditions: a special inspection for post-installed anchors, fire alarm shop drawings as a deferred submittal, and a fire department final before the certificate of occupancy. The project engineer gives each condition an owner and a due date tied to the schedule. In June the fire alarm drawings are still with the engineer of record; because the condition has a due date, it shows up three weeks before the ceiling close-in inspection instead of on the day.

Common mistakes

  • Tracking the permit number but not its conditions.
  • Assuming a permit lasts for the whole job when activity rules or linked insurance dates can end it earlier.
  • Treating your own status note as the authority’s status: confirm with the building department.
  • Leaving trade permits to subs without checking they’re pulled and closed.
  • Losing the inspection records needed at closeout.

General information, not legal advice. Permit requirements, expiration rules and fees vary by jurisdiction.

How os.construction handles it

The Permits tool keeps a project permit register: authority, jurisdiction, permit type, scope, responsible person and the submitted, issued and expiration dates. Status changes are recorded as reports of what the authority did, backed by an exact document version, a link or a stated reason, and the app doesn’t file applications or grant permission to work. Conditions have an owner and a due date and can link to an inspection for follow-up; a field user can submit a document as the receipt for a condition, and a different permit administrator accepts it to complete the condition. A company work queue lists open conditions and expirations across projects by owner and due date, and a permit past its recorded expiration is flagged. See how to track construction permits and Inspections.

FAQ

What is a building permit?

A building permit is written authorization from the local building department to carry out the construction work described in the approved application and plans. It is issued after plan review, usually lists conditions, and requires inspections at set stages before the work can be covered up, occupied or closed out.

How long is a building permit valid?

It depends on the jurisdiction. Under the model International Building Code, as adopted in places such as Massachusetts, a permit becomes invalid if work doesn't start within 180 days of issuance or is suspended or abandoned for 180 days, and the building official can grant written extensions. Other jurisdictions set different periods, and some tie expiry to other dates: New York City's DOB NOW permits expire at the earliest of the permit holder's insurance expiration, license expiration or one year from issuance.

What are permit conditions?

Conditions are requirements the authority attaches to a permit, such as special inspections, a deferred submittal, a fire department sign-off or a document that must be filed before a given stage. Each condition needs an owner and a date, because unmet conditions can hold up inspections, the certificate of occupancy or permit closure.

Who pulls the building permit, the owner or the contractor?

It varies by jurisdiction and contract. Many contracts make the contractor responsible for obtaining and paying for permits needed for its work, while the owner obtains the general building permit; trade permits are often pulled by licensed subcontractors. Check the contract and the local rules.

What happens if a permit expires during construction?

Work done under an expired permit may need a renewal or a new permit before inspections can continue, and fees can apply. Watch the expiration date and the activity rules that keep a permit alive, and confirm current status with the authority rather than relying on your own record.