Cost-to-cost method

Definition

Measuring a contract's progress as cost incurred to date divided by estimated total cost, then recognizing that percentage of the contract price as revenue.

Cost-to-cost is the most common way contractors measure progress under ASC 606 (an input method, ASC 606-10-55-20). Percent complete = cost to date ÷ estimated cost at completion; earned revenue = percent complete × contract price. Costs that don’t reflect progress, such as uninstalled materials or wasted material, are left out of both numerator and denominator.

Why it matters

Every input matters: an EAC that’s too low makes a job look more complete, books revenue early and hides fade until late in the job.

Worked example

Riverside (sample data): $31,700,000 ÷ $43,679,800 = 72.5736%. Earned = 72.5736% × $49,300,000 = $35,778,781.04. Billing percent, $33.0M ÷ $49.3M = 66.9%, is a different number and shouldn’t be mixed in.

Common mistakes

  • Using billed percent as percent complete.
  • Including delivered-but-uninstalled equipment in cost to date.
  • Rounding percent complete before multiplying.