Uninstalled materials

Definition

Materials delivered to or stored for a job but not yet installed; under ASC 606 they are excluded from cost-to-cost progress and recognized at zero margin.

When materials are delivered but not yet installed, their cost may not reflect progress toward completing the work. If the owner controls the materials, the material is distinct-not-yet-installed, and you aren’t significantly involved in designing or making it, ASC 606-10-55-21 says to exclude its cost from the progress measure and recognize revenue equal to the cost (zero margin) until it’s installed.

This is an accounting concept. Stored materials on a pay app (G703 column F) is the billing concept; the two often overlap but aren’t the same thing.

Why it matters

Big-ticket equipment (switchgear, elevators, air handlers) can make a job look far more complete than it is, and pull margin forward.

Worked example

Contract $2,000,000; EAC $1,600,000 including $200,000 of delivered switchgear; cost to date $800,000 including it. Progress = $600,000 ÷ $1,400,000 = 42.857%. Earned = $200,000 + $1,800,000 × 42.857% = $971,428.57, not the naive $1,000,000 (illustrative).

Common mistakes

  • Counting delivered equipment as progress.
  • Excluding it but forgetting to recognize the zero-margin revenue.