Esc

↑↓ move↵ openIndex · Pagefind
Contracts

Pay-When-Paid

Definition

A subcontract clause that sets the timing of sub payment to follow the GC's receipt of payment from the owner.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

A pay-when-paid clause says the general contractor will pay the subcontractor within a set time after the GC receives payment from the owner for that sub’s work. It’s about timing. A related but different clause, pay-if-paid, makes owner payment a condition precedent, so if the owner never pays, the GC may not owe the sub at all. Enforceability varies a lot by state. Some states treat pay-when-paid as only delaying payment for a reasonable time, and some restrict or void pay-if-paid clauses entirely.

Why it matters

These clauses decide who carries the risk of an owner not paying. Subs need to know which one they signed. GCs need to know whether their clause holds up in the project’s state, and lien rights often still apply either way.

Worked example

Illustrative: Pay App #9 on Riverside Medical Center bills $2.31M for the period, with 10% retainage of $231,040 held. Suppose Volt Electric’s share of the payment is $410,000. Under a “within 7 days of receipt” pay-when-paid clause, if the owner pays the GC on the 30th, Volt is due by the 7th of the next month.

Common mistakes

  • Assuming pay-when-paid and pay-if-paid mean the same thing.
  • Not checking state law before relying on the clause.
  • Holding sub payments for unrelated disputes and calling it pay-when-paid.

For a checklist of the payment clauses to read before signing, including pay-when-paid, see how to read construction contract payment terms. For how the two clauses play out when an owner pays late, pays part or never pays, see pay-when-paid vs pay-if-paid.

How os.construction handles it

In Accounting, a payment run shows each bill’s payable amount with pay-when-paid terms taken into account, and a pay-when-paid bill’s retainage release also needs the owner payment. See Accounts payable. Timing those sub payments in the cash forecast from the expected owner receipt is planned.

Watch the explainer · 1:58

Pay-when-paid vs pay-if-paid, explained

  1. 0:00When vs whether
  2. 0:18Pay-when-paid: a timing term
  3. 0:34Pay-if-paid: a condition
  4. 0:54One illustrative bill
  5. 1:18Enforceability varies by state
  6. 1:39Pay-when-paid in os.construction
Read the transcript

Pay-when-paid and pay-if-paid clauses look almost the same in a subcontract. They answer different questions. Pay-when-paid sets when the sub gets paid. Pay-if-paid tries to decide whether the sub gets paid at all. The difference only shows up when the owner stops paying.

A pay-when-paid clause is a timing term: the general contractor pays within a stated number of days after the owner pays it. It's widely enforced. If the owner never pays, many courts say the GC still has to pay the sub within a reasonable time.

A pay-if-paid clause makes the owner's payment a condition precedent. If the owner never pays, the GC may owe nothing for that work. Courts usually look for clear words, like condition precedent, or that the sub assumes the risk of owner non-payment. Ambiguous clauses are often read as pay-when-paid.

Here's an illustrative case. A drywall sub bills one hundred fifty thousand dollars for March, payable ten days after the GC is paid. If the owner pays late, on May twentieth, the sub is due by May thirtieth either way. If the owner never pays, pay-when-paid in many states still means the sub gets paid after a reasonable time. An enforceable pay-if-paid clause may mean it doesn't.

Enforceability varies by state. Some states enforce a clear pay-if-paid clause, some limit it by statute, and courts in California and New York, among others, have refused to enforce it. Lien and bond rights are often treated separately, and their deadlines keep running. General information, not legal advice.

In os.construction Accounting, payment runs take a bill's pay-when-paid terms into account against the owner payments actually received, and releasing retainage on a pay-when-paid bill also needs the owner's payment.

Open file