On this page
- 1. Billing period and pay application due date
- 2. Review and certification period
- 3. Payment due date
- 4. Retainage
- 5. Conditions to each payment
- 6. Grounds to withhold
- 7. Late payment, suspension and disputes
- 8. Final payment
- 9. The flow-down to your subcontracts
- Worked example: from period end to cash
- Common mistakes
- How os.construction handles it
- FAQ
To read a construction contract’s payment terms, find seven things: the billing period and pay application due date, the review and certification period, the payment due date, retainage (rate, reductions and release), the conditions attached to each payment, the grounds to withhold, and the remedies for late payment. Then add up the days from the end of a billing period to cash in the bank, and check that your subcontracts’ terms line up with the prime contract’s.
Payment terms rarely sit in one clause. The agreement sets amounts and dates, the general conditions set the process, and supplementary conditions or owner riders change both. Reading them together, before signing, tells you how long you’ll be carrying the job’s cost, which is the number behind any cash flow projection.
1. Billing period and pay application due date
Find the billing period (usually monthly), the date the pay application is due, and the required format: an AIA-style application and continuation sheet, an owner form, or a lender’s draw format. Look for a pencil-draft or pre-review step and its deadline. Missing the submission date often pushes payment a full cycle. See how to fill out a pay application.
2. Review and certification period
How long the architect, owner’s representative or lender has to review and certify the application, and what happens if they don’t act in time. Note who can reduce the amount certified and whether they have to say why in writing.
3. Payment due date
The date the owner must pay, counted from submission, from certification or from a fixed day of the month. These differ by days or weeks, so read the trigger exactly. Standard forms often leave the numbers blank for the parties to fill in.
4. Retainage
Find the retainage rate, whether it applies to stored materials and to general conditions, whether it reduces partway through the job (for example after 50% complete), and the conditions to release it: substantial completion, final completion, closeout documents, consent of surety. State law may cap retainage or set release deadlines on some projects. The retainage calculator and how to calculate retainage cover the arithmetic.
5. Conditions to each payment
The documents that must come with each application: lien waivers (conditional or unconditional, yours and your subs’), certified payroll on prevailing-wage work, an updated schedule, insurance certificates, invoices and proof of insurance for stored materials. A missing waiver can hold the whole payment, so build the list into your billing routine.
6. Grounds to withhold
What the owner may hold back and for what: defective work, a sub’s unpaid claim or lien, failure to submit required documents, a projected cost overrun, liquidated damages. Check whether withholding must be in writing with reasons, whether it’s limited to an amount reasonably related to the problem, and how it’s released.
7. Late payment, suspension and disputes
Interest on late payments, any right to suspend work after notice, cost and time recovery for a suspension, and the dispute process. Many states have prompt payment laws that set deadlines and interest on some projects; they vary, and the contract may not repeat them.
8. Final payment
The conditions for final payment and retainage release: punch list, closeout documents, final waivers, consent of surety. Note any clause that says accepting final payment waives claims, so open claims are reserved in writing first.
9. The flow-down to your subcontracts
Line the prime terms up against your subcontract: billing date, retainage rate and release, pay-when-paid or pay-if-paid language, and the documents subs must supply. If the owner needs your pay app by the 25th, subs need to bill you earlier. A mismatch, such as holding 5% from the owner’s side while paying subs in full, is a cash flow decision you should make on purpose.
Worked example: from period end to cash
The prime contract says: the billing period ends on the last day of the month; the pay application is due 5 days later; the architect has 7 days to certify; the owner pays within 30 days of certification; retainage is 10%, reducing to 5% on billings after the job is 50% complete. The subcontracts pay within 7 days of the GC’s receipt of payment.
The March billing
| Event | Date | Days from period end |
|---|---|---|
| Billing period ends | March 31 | 0 |
| Pay application due | April 5 | 5 |
| Architect certifies (latest) | April 12 | 12 |
| Owner payment due (latest) | May 12 | 42 |
| Subs paid (latest) | May 19 | 49 |
Work done on March 1 is paid 72 days later at the latest; work on March 31, 42 days later. If the March application misses April 5, the whole cycle can slide a month, depending on how the contract handles late submissions.
Retainage on a $2,000,000 contract
| Flat 10% | 10%, then 5% after 50% | |
|---|---|---|
| Retainage on the first $1,000,000 | $100,000 | $100,000 |
| Retainage on the second $1,000,000 | $100,000 | $50,000 |
| Held at completion | $200,000 | $150,000 |
The reduction puts $50,000 in your hands during the job instead of after closeout. Check whether you have to request it, and whether the owner can restore the full rate if the job falls behind.
Common mistakes
- Reading only the agreement. The general and supplementary conditions often change the process and the dates.
- Missing the trigger. “30 days after certification” and “30 days after submission” are different dates.
- Not reading the withholding clause. Broad withholding rights can turn a small dispute into a held payment.
- Assuming retainage reduces automatically. Many clauses require a request or owner approval.
- Subcontract terms that don’t match the prime. Your cash sits in the gap.
- Accepting final payment with claims open. Reserve them in writing if the contract treats final payment as a waiver.
General information, not legal advice. Payment, retainage, prompt payment and pay-if-paid rules depend on the contract and the law where the project is located. Have a construction attorney review terms before you sign.
How os.construction handles it
Payment applications in os.construction bill against the prime contract’s schedule of values, carry retainage by line, and keep stored materials and change orders in the same record. The Getting paid in construction guide walks the full path from pay app to cash.
FAQ
What are payment terms in a construction contract?
The provisions that decide how and when the contractor is paid: the billing period and pay application due date, how long the owner or architect has to review it, when payment is due, how much retainage is held and when it's released, what documents must come with each application, what the owner may withhold, and what happens if payment is late.
Where are the payment terms in a construction contract?
Usually in several places: the agreement sets the amounts, dates and retainage, the general conditions set the application, certification and withholding process, and supplementary conditions or owner riders often change both. Read all of them together, plus any exhibits that specify billing format or required documents.
What is the difference between pay-when-paid and pay-if-paid?
Pay-when-paid generally sets the timing of a subcontractor's payment after the general contractor is paid. Pay-if-paid tries to make the owner's payment a condition of the sub being paid at all. Enforceability of both varies a lot by state, and some states restrict or void pay-if-paid clauses.
How long does an owner have to pay a contractor?
Whatever the contract says, within the limits of any prompt payment law that applies. Many US states have prompt payment statutes for public work, and some for private work, that set deadlines and interest on late payments. Check the contract and the law where the project is located.
Can a contractor stop work if not paid?
Some contracts and some state laws give a right to suspend work for non-payment after written notice, others restrict it. Stopping work without that right can be treated as a breach. Read the suspension and termination clauses and get legal advice before stopping.
Share this article