Field change to pay app: one change, start to finish

An excavator hits a footing nobody drew. This video follows that one surprise through four linked records in os.construction, from the change event to G702 line 2 on the next pay app, and checks every number on screen.

Video walkthrough9 min readSample data · Sandbox Test Project

Watch

The full walkthrough

Watch the walkthrough · 8:32

Field change to pay app: one change, start to finish

  1. 0:00The $18,400 surprise
  2. 0:34Four records, one change
  3. 1:22Step 1: Log the change event
  4. 2:31Steps 2–3: Create and price the PCO
  5. 3:21Step 4: Approve, then execute
  6. 4:16Step 5: Close the event, post the budget
  7. 4:38Step 6: Bill it on the next pay app
  8. 5:53Check the G702 math
  9. 6:37Who this helps
  10. 7:10Mistakes to avoid
  11. 7:55Recap checklist + try it yourself
Read the transcript

An excavator bucket hits concrete that isn't on any drawing. An old footing, right where the elevator pit goes. Removing it will cost money. In this video, we'll follow that one surprise all the way onto a pay application, and check every number on the way.

One worked example in os.construction: a $16,000 cost, priced to the owner at $18,400, approved, executed, and showing up on the July pay app. It's all sample data, in the app's Sandbox Test Project.

First, the map. Four records carry a change from the field to getting paid. The change event says something happened. The potential change order, or PCO, prices it against a contract. Approving and executing that PCO changes the contract. And the pay application bills against the new contract sum.

Each record links to the one before it, so nothing gets retyped. When the owner asks where a number came from, you can walk backward from the pay app to the footing in the ground.

Why four records instead of one email? Because each stage answers a different question. Did something happen? What will it cost? Did the owner agree? Has it been billed? Mix those together, and changes get lost, or billed before anyone signs.

Step one: log the change event. A change event records a possible change early, before anyone has priced or approved it. The superintendent who finds the footing doesn't need the price. They need it on record the same day.

In the app, open Change Events and select Create. We give it a title that says what happened: Buried concrete footing at elevator pit. We set Scope to Out of Scope, because we believe the owner pays for this, and describe what the crew found.

Then a line item. Cost code 02-000, existing conditions. Forty cubic yards at $400 a yard. Leave the ROM amount blank, and the app multiplies quantity by unit cost. We also enter a Budget Change of $16,000. That's the amount that will post to the budget later.

Select Create Change Event. The detail page shows the cost ROM, $16,000, and a pipeline across the top: change event, RFQs, PCOs, change orders, and budget change. Right now, only the first stage is filled in.

Step two: create the PCO. A potential change order prices the change against a specific contract. On the change event, scroll to Potential Change Orders, pick the contract, here the owner's prime contract, and select Create PCO from Change Event.

The new PCO links back to change event 7, and its line item is copied over: forty cubic yards at $400, $16,000. No retyping.

Step three: price it for the owner. Our cost is $16,000. We bill the owner $460 a yard, so we change the unit cost to 460 and the amount to $18,400, then save the line. Grand total: $18,400. The $2,400 difference is our margin on this change.

Step four: get it approved, then executed. In os.construction, these are two separate actions, and the difference matters. Approved means the owner agreed. Executed means the contract change is final, and that's what the pay app counts.

Select Submit for Review, and the PCO is pending. When the owner signs, select Approve. Now look at the last stage. Executed: No. Contract not yet updated. Select Execute, and it reads Yes, contract updated.

Open Prime Contracts. The original contract is $2,400,000. Approved change orders were $25,870 before ours. Add $18,400, and they're now $44,270. The revised contract is $2,444,270.

Step five: close the change event. Closing is what posts its Budget Change. Back on change event 7, select Close. The budget stage now reads $16,000, posted on close. The cost ROM alone never moves the budget. Only the Budget Change amount does, and only when the event is closed.

Step six: the next pay application. A pay app bills the owner for work done this period, line by line, against the schedule of values. Retainage holds back a percentage, here ten percent, until the work is finished.

Open Payment Applications and select Create. Pick the owner contract and the period, July first to July thirty-first. The schedule of values lines come from the prime contract, and earlier applications fill in what's already been billed.

Look at the G702 summary. Line one, the original contract sum, is $2,400,000, the total of those schedule of values lines. Line two, net change by change orders, is $44,270: the executed changes, including our $18,400. Line three, contract sum to date, is $2,444,270.

Now bill this period. On the HVAC line, we enter $60,000 of work this period and select Save This Period. Ten percent retainage on that is $6,000. So the current payment due is $54,000.

Check it the long way on the G702. Completed and stored to date, $1,572,000, less retainage of $157,200, is $1,414,800. Subtract previous certificates of $1,360,800, and you get the same $54,000.

One honest note. In the app today, the continuation sheet lines come from the prime contract's schedule of values, and the executed change appears on the G702 as net change by change orders. If your owner wants change work as its own continuation line, agree on that format before you bill.

Who does this help? Picture two moments. They're illustrative, not measured. A superintendent finds the footing at seven in the morning. Before the hole is backfilled, a change event exists, with a description and a rough cost, so nobody has to remember it at month end.

And a project manager building the July pay app. Instead of searching email for which changes were signed, they open the pay app, and line two already carries the executed changes, traceable back to change event 7.

Now, mistakes to avoid. One: waiting to log the change until it's priced. Log the event first. A rough number is fine.

Two: assuming the cost ROM changes the budget. It doesn't. Enter a Budget Change amount, and close the event.

Three: treating approved as billable. The pay app's net change counts executed change orders. A PCO that's approved but never executed won't be there.

Four: also typing the change into the original schedule of values. Line one is built from those lines, and line two adds executed changes, so the same $18,400 would count twice.

Here's the checklist. Log the change event the day you find it. Create the PCO from the event, and price it. Approve, then execute. Close the event to post the budget change. Then check lines two and three on the next pay app.

To try it yourself, the os.construction docs walk through change events and PCOs, and pay apps, schedule of values, and retainage. The links are in the description. Thanks for watching.

The worked example

One change, four linked records

Each record links to the one before, so you can walk backward from the pay app to the footing in the ground. These are the numbers the app showed during the recording.

  1. 01Change eventCE 7Buried concrete footing at elevator pit · Out of Scope40 CY × $400 = $16,000 cost ROMBudget Change $16,000 (posts when closed)
  2. 02Potential change orderPCO 7Created from CE 7 on Prime Contract #1; line copied40 CY × $460 = $18,400$2,400 over cost
  3. 03Change orderApproved, then executedSubmit for Review → Approve → ExecuteApproved COs $25,870 + $18,400 = $44,270Revised contract $2,444,270
  4. 04Pay applicationJuly, G702Line 1 + line 2 = line 3$2,400,000 + $44,270 = $2,444,270$60,000 this period − $6,000 retainage = $54,000 due
An animated diagram builds four linked cards: change event, PCO, change order and pay application, joined by arrows.
The four records build up · no sound · ▶️ Watch the full walkthrough on YouTube
The real PCO 7 screen zoomed on its line: unit cost changed from 400 to 460 and the amount to 18,400, then a grand total of $18,400.
Pricing the PCO: $400 → $460 a yard · no sound · ▶️ Watch the full walkthrough on YouTube
How to do it in the app

Six steps

  1. 01
    Log the change event

    Change Events → Create. Title it, set Scope (Out of Scope if you believe the owner pays), add a cost-coded line. Blank ROM Amount = Qty × Unit Cost. Enter a Budget Change if it should move the budget.

  2. 02
    Create the PCO from the event

    On the change event, pick the contract under Potential Change Orders and select Create PCO from Change Event. The lines are copied and linked back.

  3. 03
    Price it for the owner

    Edit the PCO line (here $400 → $460 a yard) and save. Markup rows show on the PCO, but budget, contract and billing roll-ups count the line amounts.

  4. 04
    Approve, then execute

    Submit for Review, Approve when the owner signs, then Execute. Only executed change orders reach G702 line 2.

  5. 05
    Close the event

    Closing posts the Budget Change amount to the budget. The cost ROM alone never does.

  6. 06
    Bill on the next pay app

    Create the pay app for the period. Line 2 carries executed changes; line 3 is the new contract sum to date. Enter this period and save.

The real PCO screen with its Executed stage reading No, contract not yet updated, then Yes, contract updated after Execute.
Execute: “contract not yet updated” becomes “contract updated” · no sound · ▶️ Watch the full walkthrough on YouTube
The real July pay application G702 panel with lines highlighted in turn: original contract sum $2,400,000, net change by change orders $44,270, contract sum to date $2,444,270.
G702: line 1 + line 2 = line 3 · no sound · ▶️ Watch the full walkthrough on YouTube
Check the math

$54,000 two ways

July pay app, G702 (sample data)
4. Completed & stored to date$1,572,000
− 5. Total retainage (10%)$157,200
= 6. Earned less retainage$1,414,800
− 7. Previous certificates$1,360,800
= 8. Current payment due$54,000

The short way: $60,000 billed this period on the HVAC line, less 10% retainage ($6,000), is $54,000. One honest note: in the app today the continuation sheet lines come from the prime contract's schedule of values, and the executed change shows on the G702 as line 2. If your owner wants change work as its own continuation line, agree on the format before you bill.

⚠️ Mistakes to avoid

Four ways a change goes missing or counts twice

  • ❌ Waiting to log the change until it is priced✅ Log the event the day you find it. A rough number is fine.
  • ❌ Assuming the cost ROM changes the budget✅ Enter a Budget Change amount and close the event.
  • ❌ Treating approved as billable✅ G702 line 2 counts executed change orders. Approve, then execute.
  • ❌ Also typing the change into the original schedule of values✅ Line 1 is built from those lines and line 2 adds executed changes, so it would count twice.
✅ Recap checklist

Before the next pay app goes out

  • Log the change event the day you find it
  • Create the PCO from the event
  • Price it for the owner
  • Approve, then execute
  • Close the event to post the budget change
  • Check G702 lines 2 and 3 on the next pay app

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

Change events, PCOs, change order execution, budget posting and pay apps are live in os.construction.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are sample data from the app's Sandbox Test Project, recorded in a local instance. The 3D scenes and the two vignettes in the video are illustrative, not measured results. Contract terms decide how changes and retainage are billed on your job.