Esc

↑↓ move↵ openIndex · Pagefind
Contracts

Integrated Project Delivery (IPD)

Definition

A delivery method where owner, designer and builder sign one multi-party agreement and share project risk and reward.

Part of: Project delivery methods: design-build, CMAR, GMP and more

Topic: Project delivery & contracts

Updated

Integrated Project Delivery brings the owner, architect, contractor and often key trades into a single multi-party agreement. Instead of each party protecting its own contract, the team agrees on a target cost, puts some or all of its profit at risk, and shares in savings or overruns together. Decisions are made jointly, usually by a core group with representatives from each party, and many IPD agreements limit claims between the parties.

How it works

  1. Form the team early. The owner selects the architect, the builder and key design-assist trades, such as mechanical and electrical, before design is far along.
  2. Sign one agreement. All parties sign a multi-party agreement, or join a single-purpose entity, with the same terms on governance, risk and reward.
  3. Set a target cost. The team validates the owner’s program and budget during early design and agrees an expected cost for the project.
  4. Put profit at risk. The non-owner parties’ profit goes into a shared pool. Their actual costs are usually reimbursed on open books.
  5. Govern jointly. A senior management team with a representative of each party makes key decisions, usually by consensus, with a project management team running day to day.
  6. Share the outcome. Underruns increase the pool by a formula in the agreement. Overruns reduce it. Many agreements also tie part of the pool to quality, schedule or other goals.
  7. Limit claims. The parties often waive most claims against each other, except for things like wilful misconduct, so problems are solved by the team instead of being passed along.

The AIA’s guide describes principles such as mutual respect and trust, early involvement of key participants, early goal definition, open communication and shared risk and reward.

Worked example

Illustrative: a team sets a $48.0M target cost with $3.0M of combined profit at risk. If the job finishes at $47.4M, the $600,000 savings is shared per the agreement’s formula, on top of the profit pool. If it finishes at $48.9M, the $900,000 overrun reduces the shared profit pool first, before the owner absorbs further costs.

Illustrative (sample data) of three outcomes under a simple formula where savings are split 50/50 between the owner and the pool:

Final cost Variance to target Profit pool paid Owner’s total cost
$47.4M $0.6M under $3.0M + $0.3M = $3.3M $50.7M
$48.9M $0.9M over $3.0M − $0.9M = $2.1M $51.0M
$52.0M $4.0M over $0 (pool exhausted) $52.0M

In the third case the pool is gone after $3.0M of overrun, and the owner pays the last $1.0M. The trades and builder still get their costs back but earn no profit. Real agreements vary, with different splits, caps and incentive payments.

IPD vs other delivery methods

Method Contracts Who carries cost risk
Design-bid-build Owner–architect and owner–contractor, separately Contractor, for its bid price
CM at risk Owner–architect and owner–CM CM, up to the GMP
Design-build Owner–design-builder Design-builder, for its price
IPD One multi-party agreement Shared: profit at risk, owner above that

Why it matters

IPD tries to fix the incentive problem in traditional delivery, where every party benefits when another party eats the cost. It needs a lot of trust, open books, and shared tools like BIM and a common cost model. Without transparent cost data, the shared risk pool turns into a negotiation.

Because profit depends on the whole project’s cost, IPD changes behavior in preconstruction. Trades contribute to design early, value engineering happens before drawings are finished rather than after bids come in high, and contingency is managed as a team resource rather than each party’s private cushion.

Common mistakes

  • Signing an IPD agreement but behaving like a hard-bid team.
  • Using separate cost systems so no one trusts the shared numbers.
  • Leaving the risk/reward formula vague until the money is on the table.
  • Bringing key trades in after design is mostly finished, which loses most of the benefit.
  • Not training project teams who have only worked under adversarial contracts.
  • Assuming the claims waiver removes the need for clear records of decisions and changes.

How os.construction handles it

Owners, architects and trade partners can be invited to a project, each with a permission template per tool (none, read only, standard or admin), so several parties can work from one cost and project record. See Roles and permissions.

FAQ

What is integrated project delivery?

Integrated project delivery is a way of delivering a building in which the owner, the designer, the builder and often key trade contractors sign one multi-party agreement, set a shared target cost, put some or all of their profit at risk against it and make decisions together from early design.

How is IPD different from design-build?

In design-build the owner has one contract with a design-builder, who carries the risk of delivering for the agreed price and holds the designer and trades under it. In IPD the owner, designer and builder are all parties to the same agreement and share risk and reward with each other, rather than one party carrying it for the rest.

What contract forms are used for IPD?

In the US, published forms include the AIA's multi-party and single-purpose-entity IPD agreements and ConsensusDocs 300. Many large owners use their own custom multi-party agreements. In the UK, the NEC4 Alliance Contract is a published multi-party form built on similar ideas.

What happens if an IPD project goes over the target cost?

It depends on the agreement. Commonly, the overrun first reduces the shared profit pool the non-owner parties put at risk. Once that pool is used up, many agreements have the owner pay the remaining actual cost, while the other parties are still reimbursed their costs but earn no profit.

When is IPD a good fit?

It tends to suit complex projects such as hospitals and laboratories, where early collaboration among designers and trades can save a lot, and owners who can commit their own people to joint decision-making. It's a poor fit where the owner needs a fixed price on day one or the parties don't trust each other with open books.

Sources

Keep exploring

Related across os.construction

Open file