Project management

Windows Analysis

Definition

A retrospective delay analysis that measures how the forecast completion moved in each period between consecutive schedule updates, and why.

Topic: Changes & claims · Scheduling

Updated

A windows analysis splits the project into periods, usually between consecutive schedule updates, and measures how much the forecast completion moved in each window and which path drove the movement. AACE RP 29R-03 classes the update-based forms as observational dynamic methods: MIP 3.3 (contemporaneous, as is), MIP 3.4 (contemporaneous, split into progress and plan revision) and MIP 3.5 (modified or recreated updates).

Worked example

Illustrative: monthly updates exist for March to June, but the April update was never statused. An analyst recreates April from daily reports and records every change in a modification register: three actual starts added, two remaining durations corrected, one missing tie restored, each with its source and reason. A MIP 3.5 analysis then shows the forecast completion slipping 4 days in March to April and 11 days in April to May, with the May slip driven by steel delivery.

Why it matters

Windows analysis follows what the project team actually knew and did, period by period, so it’s widely preferred for claims on projects with regular updates. Its credibility rests on the updates. Where they had to be changed, the modification register is what makes the result reviewable.

Common mistakes

  • Running MIP 3.3 on updates that were revised and re-issued, so plan changes are mixed with progress.
  • Recreating updates without recording each change and its basis.
  • Presenting a window’s slip as proof of responsibility.

How os.construction handles it

Accepted updates of record form a forensic series that opens the Forensics page with them as windows. The modified-or-recreated method runs MIP 3.4’s bifurcated windows over the updates you supply, with a declared provenance and a modification register for each, and the register is part of the kept report. See Forensic series.

FAQ

What is the difference between MIP 3.3, 3.4 and 3.5?

All three come from AACE RP 29R-03 and observe how the critical path moved across updates. MIP 3.3 uses the contemporaneous updates as they are. MIP 3.4 splits each window into progress and plan revision (bifurcated). MIP 3.5 uses updates the analyst has modified or recreated, for example because the originals were never statused or are missing.

Why does MIP 3.5 need a modification register?

Because every change the analyst makes to an update can change the answer. Recording what changed, before and after, under what authority and why lets the other side test whether each change was justified.

Does a windows analysis establish entitlement to a time extension?

No. It measures delay and identifies what drove it in each window. Responsibility, notice and entitlement are contract questions.