Notice to proceed

Owner's written authorization to begin work. Tick full or limited, fill the blanks, sign, and keep the contractor's acknowledgment.

os.construction
Free template
Date of this notice
Delivered by (method)
Project
Contract no. / date
Owner
Contractor

1 · Type of notice

Full notice to proceed: all work under the contractLimited notice to proceed: only the work listed in section 3

2 · Notice

Under the contract named above, you are notified to proceed with the work described in section (all work, or section 3 only for a limited notice).

Date of commencement:  (the date of this notice / the date stated here / days after receipt, as the contract provides)

Contract time: calendar daysworking days

Substantial completion date:   Final completion date:

Liquidated damages: as stated in the contract, $ per day of delay, or none.

Due before work starts or within days: schedule of values, baseline schedule, safety plan, and

Dates above are stated for convenience. If they conflict with the contract, the contract governs. If you disagree with any date, notify the owner in writing within days of receipt.

3 · Limited NTP only: authorized early work

#Scope authorizedCost codeNot-to-exceed ($)
1
2
3
4
Total not-to-exceed

This limited notice authorizes only the work listed above, up to the not-to-exceed total. It does not startstarts contract time. It expires on or when a full notice to proceed is issued, whichever is first.

If no full notice to proceed is issued, the owner will pay for authorized work performed up to the cap, and the contractor will stop work and demobilize as follows:

4 · Signatures

Issued for the owner: name, title, signature, date
Copy to architect / engineer: name, date

5 · Contractor acknowledgment of receipt

Received by: name, title, company
Date and time received / exceptions noted

Before you send it: check the agreement's date-of-commencement clause, the contract time and the LD rate, and confirm bonds, insurance, permits, site access and financing are in place. If they aren't, issue a limited NTP instead of a full one.

Template from os.construction/resources/templates/notice-to-proceed. Free to use and adapt.General information, not legal advice. Your contract documents govern.