Notice to proceed
Owner's written authorization to begin work. Tick full or limited, fill the blanks, sign, and keep the contractor's acknowledgment.
Free template
1 · Type of notice
2 · Notice
Under the contract named above, you are notified to proceed with the work described in section (all work, or section 3 only for a limited notice).
Date of commencement: (the date of this notice / the date stated here / days after receipt, as the contract provides)
Contract time: calendar daysworking days
Substantial completion date: Final completion date:
Liquidated damages: as stated in the contract, $ per day of delay, or none.
Due before work starts or within days: schedule of values, baseline schedule, safety plan, and
Dates above are stated for convenience. If they conflict with the contract, the contract governs. If you disagree with any date, notify the owner in writing within days of receipt.
3 · Limited NTP only: authorized early work
| # | Scope authorized | Cost code | Not-to-exceed ($) |
|---|---|---|---|
| 1 | |||
| 2 | |||
| 3 | |||
| 4 | |||
| Total not-to-exceed |
This limited notice authorizes only the work listed above, up to the not-to-exceed total. It does not startstarts contract time. It expires on or when a full notice to proceed is issued, whichever is first.
If no full notice to proceed is issued, the owner will pay for authorized work performed up to the cap, and the contractor will stop work and demobilize as follows:
4 · Signatures
5 · Contractor acknowledgment of receipt
Before you send it: check the agreement's date-of-commencement clause, the contract time and the LD rate, and confirm bonds, insurance, permits, site access and financing are in place. If they aren't, issue a limited NTP instead of a full one.