Closeout and TCO checklist

From the TCO application and final inspections to the certificate of occupancy, final payment and retainage release. Work it top to bottom.

os.construction
Free template
Project
Permit #
Owner
Architect
Building department
TCO expiry date
Substantial completion date
Final completion target

1 · Plan the TCO and CO

DoneItemOwnerDate
Pre-final meeting held with the building departmentFinal inspection list and outside agencies confirmed in writing.
Contract checked: is a TCO or final CO a condition of substantial completion?If yes, the inspections below are on your critical path.
Each final inspection on the schedule as an activityAllow time for a re-inspection on every one.
Fire alarm acceptance and sprinkler final booked with the fire marshal
Elevator inspection booked with the elevator authorityIf the building has one.
Special inspection final reports and structural observation letters requested
Owner told who applies for the TCO and CO, and what fees, deposits or bonds apply

2 · TCO application

DoneItemOwnerDate
Areas to be occupied marked on a planFloors, tenant spaces or phases.
Life safety complete in those areasFire alarm, sprinklers, exits, exit signs, emergency lighting.
Rated separation and secure barriers between occupied areas and active work
Fire department access, hydrants, addressing and key box in place
Required sign-offs for the occupied areas passedBuilding, fire, electrical, plumbing, mechanical, elevator.
Design professional letters submitted, where required
Open-items list with completion dates attached
TCO received: conditions and expiry date logged and scheduledNote the date to apply for a renewal if the CO will not be ready.
Owner insurance, utilities and security in place for occupied areas

3 · Substantial completion

DoneItemOwnerDate
Contractor punch list walk completedYour own list first, before the architect walks.
Architect / owner punch list received and distributed to subsEach item assigned to one trade with a due date.
Certificate of Substantial Completion executedOften AIA G704. Fixes the date warranties start and LD exposure stops.
Utilities, insurance and security responsibilities transferred to ownerConfirm the transfer date in writing.

4 · Commissioning (Cx)

DoneItemOwnerDate
Test, adjust and balance (TAB) report submitted
Functional performance tests complete and witnessed by the CxA
Cx issues log closed, or deferred and seasonal tests listed with dates
Owner training sessions held and attendance logged
Commissioning report or systems manual delivered

5 · Final inspections and CO

DoneItemOwnerDate
All final inspections passed and sign-offs collected
Outside agency approvals receivedHealth, public works, utilities or zoning, where required.
Final certificate of occupancy issued before the TCO expired
CO copy given to the owner and posted where required

6 · Turnover documents

DoneItemOwnerDate
As-built / record drawings submittedEvery field change and RFI answer reflected.
Operation and maintenance manuals submitted
Warranties and guarantees collected from every tradeStart dates tied to substantial completion unless the contract says otherwise.
Attic stock / spare materials delivered and receipted
Keys, access cards and combinations turned over with a signed receipt
Final punch list items closed and verified

7 · Final payment and retainage

DoneItemOwnerDate
All pending change orders resolved; sub COs match owner COsNothing should still be "pending" at final.
Final subcontractor pay apps received; back-charges settled
Conditional final lien waivers collected from every sub and supplierIncludes lower tiers where your contract or state law requires.
Affidavit of payment and lien releasesOften AIA G706 and G706A, or your state forms.
Consent of surety to final payment obtained (bonded jobs)Often AIA G707.
Final owner pay app with retainage release submitted
Unconditional final lien waivers exchanged once funds clear
Notice of completion recorded, in states that use one
Retainage paid out to subs; warranty-period reminders setFor example an 11-month warranty walk.

Tip: put the TCO expiry on the schedule like a contract milestone, and collect turnover documents from the first pay app, not the last. Retainage is the money most often left on the table at closeout.

Template from os.construction/resources/templates/closeout-checklist. Free to use and adapt.Codes, TCO rules and retainage law vary by jurisdiction. Your contract documents govern.