Quality issues travel. A failed inspection item becomes an observation with an owner; if it is a defect to fix before the owner accepts the work, the observation becomes a punch item.

Each step is its own record, linked to the one before, so you can show where an item came from and who signed it off. The sample project has punch items and observations already; you will build the inspection yourself.

From failed check to closed punch itemInspection item fails, then Observation created, then Converted to punch item, then Ready for review, then Closed. Work not accepted: from Ready for review back to Converted to punch item.Work not acceptedInspection item failsPass, Fail or N/AObservation createdOwner, due date, photosConverted to punch itemLinked back to the observationReady for reviewTrade says it’s fixedClosedFinal approver signs off
  1. Inspection item failsPass, Fail or N/A
  2. Observation createdOwner, due date, photos
  3. Converted to punch itemLinked back to the observation
  4. Ready for reviewTrade says it’s fixedWork not accepted: back to “Converted to punch item”
  5. ClosedFinal approver signs off
From failed check to closed punch item
Text version
  1. Inspection item fails: Pass, Fail or N/A
  2. Observation created: Owner, due date, photos
  3. Converted to punch item: Linked back to the observation
  4. Ready for review: Trade says it’s fixed
  5. Closed: Final approver signs off

Work not accepted: from “Ready for review” back to “Converted to punch item”.

Hands-on · about 10 minutes · sample project

Exercise

  1. Open Inspections, go to Templates and click + New Template. Add one section with three Pass / Fail items, and tick Require photo on fail on one.
  2. Click + Create, pick your template, set a location and create the inspection.
  3. Answer two items Pass and one Fail. On the failed item click Create Observation.
  4. Open the observation, set an assignee and due date, then use Convert to Punch Item in the Escalate panel.
  5. On the punch item, set a location, a punch item manager, a final approver and an assignee.
  6. In the punch list, select the item and use Mark Ready for Review, then Close. Watch the cards at the top change.

14-day free trial. Pricing for paid plans isn't set yet. Everything here runs on the sample project in your own workspace.

Check your work

Tick each step you finished

Progress is saved in this browser only.

Self-check

What happens to an inspection’s responses once it is signed?

They lock. Reopen deletes the signatures, so it has to be signed again.

Can a subcontractor close their own punch item?

No. Assignees mark their part resolved; the manager reviews and the final approver closes.

Are inspection templates shared across projects?

Not today. Templates belong to the project.

Use it on your own job