Project management

Weekly Work Plan

Definition

The set of commitments each trade makes for the coming week in the Last Planner System, drawn from make-ready work in the lookahead and assessed at the end of the week.

Topic: Scheduling · Field operations

Updated

Should, can, will, did in the Last Planner SystemFour narrowing bars. Should is the work the master and phase plans call for. Can is the part of it that is ready because its constraints are cleared. Will is the 18 commitments on the weekly work plan. Did is the 14 completed as promised. Percent plan complete is 14 divided by 18, or 78 percent.SHOULDMaster and phase plansCANReady work in the look-aheadWILL18 weekly commitmentsDID14 completed as promisedPPC = 14 ÷ 18 = 78%
Illustrative week. Only ready work becomes a commitment, and percent plan complete measures what got done against what was promised.

A weekly work plan lists what each trade foreman promises to finish next week. It is built in the weekly coordination meeting from the lookahead, and only from work that is make-ready: its constraints, such as approved submittals, delivered materials and answered RFIs, are cleared. At the end of the week each commitment is marked met or missed, and every miss gets a reason.

The weekly work plan belongs to the Last Planner System, developed by Glenn Ballard and Greg Howell and promoted by the Lean Construction Institute. “Last planner” refers to the person who decides what a crew will do on a given day, usually the foreman.

How it works

The Last Planner System runs from long-range to short-range planning:

  1. Master schedule: milestones and overall sequence. What should happen.
  2. Phase or pull planning: the trades plan each phase backwards from its milestone.
  3. Look-ahead: usually several weeks out. Constraints are identified and cleared so work becomes ready. What can happen.
  4. Weekly work plan: commitments for next week, from ready work only. What will happen.
  5. Learning: at the end of the week, what did happen. Percent plan complete (PPC) and reasons for misses feed back into planning.

A good commitment is specific enough to judge done or not done (“L3 duct rough-in, zones A and B”), sized to what the crew can actually do in the week, in the right sequence, and free of open constraints. Ballard’s work describes these as quality criteria for assignments.

The meeting itself is usually short and runs at the same time each week. Each foreman reports last week’s commitments, gives a reason for any miss, then commits to next week’s work from the ready list.

Worked example

Illustrative: on Thursday the mechanical foreman commits to Level 3 duct rough-in, zones A and B. Zone C is in the lookahead too, but its duct submittal is still open, so it isn’t committed. The next Friday, zone A is done and zone B is missed because the ceiling grid trade was still in the area: the reason is Access.

Across all trades that week, the plan looks like this:

Trade Commitments Completed Misses and reasons
Mechanical 4 3 1 Access
Electrical 5 5 None
Drywall 6 4 1 Prior work, 1 Labour
Plumbing 3 2 1 Materials
Total 18 14 4

PPC = 14 ÷ 18 = 78%. Two of the four misses (Access and Prior work) trace to coordination between trades, so the team adds an area-handover check to the next look-ahead review.

Plan Horizon Built by Contents
Master schedule Whole project Scheduler and PM Logic-linked activities and milestones
Look-ahead Several weeks Superintendent and trades Upcoming work and its constraints
Weekly work plan One week Trade foremen Firm commitments from ready work
Daily plan or huddle One day Foreman and crew Today’s tasks and crew assignments

The weekly plan should still trace back to the critical path. High PPC on non-critical work while critical work slips is a warning sign, not a success.

Why it matters

The weekly work plan is where the master schedule meets the crews. Committing only make-ready work keeps promises realistic, and the end-of-week assessment produces percent plan complete (PPC) and the reasons behind each miss. Over several weeks the reasons show where the system breaks: late design answers, material logistics, trade stacking or labour shortages.

Common mistakes

  • Copying the lookahead into the weekly plan without checking constraints.
  • Letting the scheduler write the commitments instead of the people doing the work.
  • Not recording a reason for a miss, so the same problem repeats.
  • Vague commitments (“work on Level 3”) that can’t be judged complete.
  • Counting partly finished tasks as done, which inflates PPC.
  • Chasing a high PPC by committing to less, which hides capacity and slows the job.

For the step before the weekly plan, see how to build a three-week look-ahead.

For the phase planning step before that, see how to run a pull planning session.

How os.construction handles it

The Schedule Lookahead page shows the weekly work plan for any week beside the constraints lookahead, with a Make-ready column for each commitment. Committing is refused while a commitment has open constraints, unless the override is recorded on the plan. Committed weeks are frozen and only assessed. See Last Planner.

Watch the explainer · 0:49

On the Schedule Doesn't Mean Ready to Build

Read the transcript

Ceiling close-in is on next week's schedule. Does that mean the crew can start? Check what has to happen first.

In this example, the drawings are coordinated and materials are here. But a required inspection is still outstanding. Two green checks don't cancel one blocker.

Turn that blocker into an action: who will arrange the inspection, by when, and what record will prove the prerequisite is cleared?

Verify the prerequisite is satisfied. Then ask the trade to confirm the scope, location, and finish date it can actually promise.

Use the lookahead to make work ready, then use the weekly plan to make clear promises. Explore the planning guides at os dot construction.

FAQ

What is a weekly work plan in construction?

It is the list of tasks each trade foreman commits to completing in the coming week, agreed in a weekly coordination meeting. It is part of the Last Planner System. Only work whose constraints have been cleared goes on the plan, and at the end of the week each commitment is marked complete or not, with a reason for every miss.

How is a weekly work plan different from a look-ahead schedule?

The look-ahead covers the next several weeks and is where constraints get identified and cleared, so work becomes ready. The weekly work plan covers only the next week and contains only work that is already ready, as firm commitments from the people doing it. The look-ahead feeds the weekly plan.

What is should, can, will, did in Last Planner?

It is the shorthand for the planning levels. Should is what the master and phase schedules say needs doing. Can is the subset whose constraints are cleared. Will is what the crews commit to in the weekly work plan. Did is what actually got done, which is measured against will to give percent plan complete.

How do you calculate PPC from a weekly work plan?

Divide the number of commitments completed as promised by the total number of commitments on the plan, and express it as a percentage. A plan with 20 commitments and 16 completed has a PPC of 80%. Partly finished tasks count as not complete.

Who makes the commitments on a weekly work plan?

The last planners: the foremen and crew leads who will direct the work. The general contractor's team facilitates the meeting and tracks constraints, but it shouldn't write commitments on the trades' behalf. A promise from the person doing the work is what makes the plan reliable.