Performance Factor

Definition

A multiplier applied to the budget of remaining work to estimate what it will actually cost: 1, a custom value, 1/CPI or 1/(CPI × SPI).

Topic: Scheduling

Updated

A performance factor (PF) scales the budget of the work that’s left into a forecast of what it will cost. P6 offers it as one of five ETC techniques: ETC equals the remaining cost, or PF × (BAC − EV) with PF = 1, a custom value, 1/CPI, or 1/(CPI × SPI). The estimate at completion is actual cost plus ETC.

Worked example

Illustrative: a $500,000 package has earned $200,000 and cost $250,000, so CPI is 0.80. SPI is 0.90.

  • PF = 1: ETC = $300,000, EAC = $550,000.
  • PF = 1/CPI = 1.25: ETC = $375,000, EAC = $625,000.
  • PF = 1/(CPI × SPI) ≈ 1.39: ETC ≈ $416,667, EAC ≈ $666,667.
  • PF = 1.10 (custom, from the estimator’s judgement): ETC = $330,000, EAC = $580,000.

Why it matters

The same progress gives very different forecasts depending on the factor. A forecast is only as useful as the reason for the factor behind it, so the report should state it.

Common mistakes

  • Applying 1/CPI very early, when a few weeks of costs make CPI volatile.
  • Using a custom factor with no recorded basis.
  • Forgetting that a missing CPI, such as with no actual cost yet, makes 1/CPI undefined.

For the same idea measured in the field, with labor hours and units installed by cost code, see how to track labor productivity.

How os.construction handles it

All five ETC techniques apply to the Planner’s Earned Value columns and the Costs & EVM dashboard, for the project and per WBS. When CPI or SPI can’t be worked out, the factor falls back to 1 and the result says why. See Earned value techniques.

FAQ

How is ETC calculated with a performance factor?

ETC = PF × (BAC − EV), the budget of the work not yet earned multiplied by the factor. EAC is then actual cost plus ETC.

What does PF = 1/CPI assume?

That the remaining work will be done at the same cost efficiency as the work so far. A CPI of 0.8 gives a factor of 1.25, so the remaining budget is forecast to cost 25% more.

When is PF = 1/(CPI × SPI) used?

When both cost overrun and schedule slip are expected to keep affecting the remaining work, for example where being behind drives acceleration costs. It's usually the most pessimistic of the standard factors.