How to track labor productivity: units installed against hours spent

Hours spent only tell you how much labor budget is gone. To know whether the crew is keeping up, compare the hours with the quantity installed: earned hours from the budget unit rate, a productivity index, and a forecast of hours to finish. Here is the method by cost code, with a six-week conduit example and three ways to forecast the rest.

Charley Forey6 min readProject controlsFieldJob costing
On this page
  1. Step 1: Pick the cost codes that matter
  2. Step 2: Set the budget quantities and unit rates from the estimate
  3. Step 3: Code hours to the same cost codes
  4. Step 4: Record quantities installed, with rules of credit
  5. Step 5: Calculate earned hours and the productivity index
  6. Step 6: Forecast hours at completion
  7. Step 7: Talk to the foreman, then feed the forecast
  8. Worked example: branch conduit over six weeks
  9. Common mistakes
  10. How os.construction handles it
  11. FAQ

To track labor productivity, set a budget unit rate for each major labor cost code (budget hours ÷ budget quantity), record hours and quantities installed against the same codes each week, and compare them: earned hours are the quantity installed times the budget unit rate, and earned hours ÷ actual hours is the productivity index. Then forecast the hours to finish from the remaining quantity and a unit rate you can defend.

A labor cost report that only compares hours spent with hours budgeted can’t tell a crew that’s ahead of the work from one that’s behind it. Fifty percent of the hours gone sounds fine until you learn forty percent of the work is done. Quantities installed are the missing half, and once you have them, the forecast stops being a guess. It’s also the field version of the earned value idea behind a performance factor: measure what was earned, not just what was spent.

Step 1: Pick the cost codes that matter

Don’t track every code. Choose the ones that carry most of the labor budget and have a clear unit of measure: linear feet of conduit or pipe, square feet of board or deck, cubic yards placed, fixtures set, devices installed. On most self-perform jobs a handful of codes account for most of the labor risk.

Step 2: Set the budget quantities and unit rates from the estimate

For each tracked code, carry the estimate’s quantity and hours into the budget:

budget unit rate = budget hours ÷ budget quantity

If the estimate was built from production rates, this is that rate. If it wasn’t, now is the time to work it out, before the first timecard. When the quantity changes through a change order, update both the budget quantity and the budget hours, or every number below drifts. How to build a construction estimate covers where those rates come from.

Step 3: Code hours to the same cost codes

Foremen code their crews’ hours daily to the tracked codes, at the same level of detail as the budget. Hours dumped into a general code can’t be compared with anything. If a crew splits its day between two codes, split the hours too; an honest estimate of the split is better than all of them on one line.

Step 4: Record quantities installed, with rules of credit

Each week, record the quantity in place for each tracked code, cut off on the same day as the hours. Quantities in the daily report make the weekly count easier and give you something to check it against.

For work with distinct steps, agree rules of credit up front, so partial work earns partial quantity. For example, a drywall team might credit a square foot as 50% when hung, 80% when taped and 100% when finished. The split is yours to set; what matters is that it’s written down and used the same way every week.

Step 5: Calculate earned hours and the productivity index

earned hours = quantity installed to date × budget unit rate productivity index (PI) = earned hours ÷ actual hours actual unit rate = actual hours ÷ quantity installed

A PI of 1.0 means the crew is on the estimate. Below 1.0 it’s using more hours than the estimate allowed for the work done. Some companies invert the ratio; pick one convention and label it on every report. If you’re used to cost-based earned value, PI is the hours version of CPI.

Look at the week as well as the job to date. The cumulative PI moves slowly; the weekly PI shows what’s happening now.

Step 6: Forecast hours at completion

hours at completion = actual hours to date + remaining quantity × forecast unit rate

The forecast unit rate is a decision, not a formula. Use the budget rate if the cause of the early overrun is behind you, the to-date rate if nothing has changed, or the recent rate if the crew has settled into a steady pace. Write down which one you used and why. Multiply the hours by the burdened labor rate to turn them into cost; the labor burden calculator gives you that rate.

Step 7: Talk to the foreman, then feed the forecast

A low PI is a question, not a verdict. Ask the foreman what’s slowing the crew: access, missing material, rework, design questions, trade stacking, crew size, or a quantity that was simply wrong in the estimate. Some causes can be fixed this week, and some belong in a change event because someone else caused them. Then carry the hours forecast into the cost-to-complete review, so the margin forecast reflects it this month.

Worked example: branch conduit over six weeks

Illustrative numbersA made-up electrical job. Quantities, rates and hours are examples, not industry productivity rates.

An electrical contractor budgets 12,000 linear feet of branch conduit at 1,800 hours, a budget unit rate of 1,800 ÷ 12,000 = 0.15 hours per foot. The burdened labor rate is $62 an hour. After six weeks:

Week Feet installed Hours Unit rate (h/ft) Earned hours Weekly PI
1 500 120 0.240 75.0 0.63
2 800 160 0.200 120.0 0.75
3 950 170 0.179 142.5 0.84
4 1,050 170 0.162 157.5 0.93
5 900 150 0.167 135.0 0.90
6 1,000 150 0.150 150.0 1.00
To date 5,200 920 0.177 780.0 0.85

To date the crew has earned 5,200 × 0.15 = 780 hours for 920 spent, a PI of 780 ÷ 920 = 0.85. By hours, the code looks 920 ÷ 1,800 = 51.1% complete; by quantity it’s 5,200 ÷ 12,000 = 43.3% complete. A report that used hours as progress would overstate this code by almost eight points.

Weekly productivity index for branch conduitSix weekly bars of productivity index against a dashed line at 1.0, the estimate. Week 1 is 0.63, week 2 is 0.75, week 3 is 0.84, week 4 is 0.93, week 5 is 0.90 and week 6 is 1.00. The cumulative index is 0.85.1.0000.630.750.840.930.901.00WK1WK2WK3WK4WK5WK6DASHED LINE: THE ESTIMATE. CUMULATIVE PI 0.85
A slow start, then a crew that has settled in close to the estimate. Illustrative.

The foreman explains the first two weeks: the first floor had the most complicated layout and the crew was waiting on a coordination answer for the corridor ceiling. Since week 4 the crew has run close to the estimate. Three forecasts for the remaining 12,000 − 5,200 = 6,800 feet:

Forecast basis Rate (h/ft) Remaining hours Hours at completion Over budget At $62/h
To-date rate, 920 ÷ 5,200 0.177 1,203 2,123 323 $20,026
Last two weeks, 300 ÷ 1,900 0.158 1,074 1,994 194 $12,028
Budget rate 0.150 1,020 1,940 140 $8,680

The remaining hours use the unrounded rates: 6,800 × (920 ÷ 5,200) = 1,203.1, and 6,800 × (300 ÷ 1,900) = 1,073.7. The dollar column is the rounded hours over budget times $62.

Even the budget-rate forecast is 140 hours over, because the early weeks can’t be earned back. The PM uses the two-week rate, 1,994 hours, $12,028 over the labor budget, and notes why: the cause of the slow start has passed and the crew has run within about 10% of the estimate for three weeks. Part of the early overrun traces to the late coordination answer, so the PM also logs it as a change event to see whether any of it is recoverable.

Common mistakes

  • Using hours spent as percent complete. It hides an overrun until the end.
  • Quantities and hours cut off on different days, which makes the weekly numbers swing for no reason.
  • Hours coded to a catch-all code, so the tracked codes are missing hours.
  • No rules of credit, so partially finished work is counted differently every week.
  • Not updating budget quantity and hours for change orders, which makes the PI drift.
  • Forecasting with the budget rate by habit, when the crew has never achieved it.
  • Treating the number as a verdict on the crew instead of a question about the conditions.
  • Tracking everything, so nobody looks at the few codes that matter.

How os.construction handles it

The Daily Log records manpower as workers and hours by company, cost code and location, and has a Quantities section for work in place with its unit, cost code and location, so hours and quantities are captured on the same codes in the field. Approved timesheets flow into Accounting Payroll, which posts labor and burden to the job by cost code. In the Schedule, an activity’s percent complete can be measured in units, and stored period performance records each period’s actual units, earned value and planned value for every activity. For the field side of the product, see construction daily log software.

FAQ

How do you measure labor productivity in construction?

Divide the labor hours spent on a cost code by the quantity installed, such as hours per linear foot or per square foot, and compare that unit rate with the rate the estimate assumed. Or work out earned hours, the quantity installed times the budget unit rate, and divide them by the actual hours. Above 1.0 the crew is beating the estimate; below 1.0 it's behind.

What are earned hours?

Earned hours are the hours the estimate allowed for the work actually installed: quantity installed times the budget hours per unit. If the estimate allowed 0.15 hours per foot and the crew has installed 5,200 feet, it has earned 780 hours, whatever it actually spent.

How often should productivity be tracked?

Weekly is common for the cost codes that carry most of the labor budget, with quantities and hours cut off on the same day. Daily quantities from the field make the weekly number easier to trust. Monthly is usually too late to change anything on a short activity.

Why not just use percent of hours spent as percent complete?

Because hours spent measure input, not output. If a crew has used 51% of its hours but installed 43% of the quantity, cost-based percent complete says the work is further along than it is, and the overrun only shows up near the end.

How do you forecast labor hours to complete?

Multiply the remaining quantity by the unit rate you expect for the rest of the work. That might be the budget rate if the cause of the overrun is fixed, the to-date rate if nothing has changed, or the recent rate if the crew has settled in. Add the actual hours to date to get hours at completion, and write down which rate you used and why.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Keep readingAll articles →
Field

How to track construction permits, conditions and inspections so nothing lapses

A permit number on a spreadsheet isn't permit tracking. Here is how to keep a permit register, turn every permit condition into an owned task with a date, tie inspections to the schedule, watch the expiration rules that actually apply, and close permits out cleanly, with a worked register.

5 min read

Project controls

Earned value vs percent complete: one measures progress, the other tells you what it means

Percent complete says how much of the work is done. Earned value turns that progress into the budgeted value of the work done, so it can be compared with the plan and with what was spent. Here is how the two relate, when to use each, a worked example and the mistakes that make every job look on budget.

5 min read

Schedule

How to build a three-week look-ahead schedule the field will actually use

The master schedule says what has to happen. The three-week look-ahead says who does it, where, and what has to be cleared first. Here is how to pull it from the master, break it down to crew level, screen every activity for constraints, get commitments from the trades, and roll it forward each week, with a worked example.

6 min read

Open file