Units percent complete measures progress by resource effort: the actual units spent divided by the units expected at completion. In P6 it’s one of three percent complete types, beside duration and physical. It sums labor and nonlabor assignments and leaves material out.
Worked example
Illustrative: an activity has a carpentry crew budgeted at 400 hours and an excavator at 100 hours. By the data date the crew has spent 180 hours with 220 remaining, and the excavator 70 with 30 remaining. Units percent complete is (180 + 70) ÷ (400 + 100) = 50%. If the scheduler enters 60% instead, each assignment’s actual and remaining units are re-spread to 60% and 40% of its at-completion units. The remaining duration stays where the scheduler set it.
Why it matters
For effort-driven work, units progress ties the schedule to timesheets or quantities, and under the activity percent complete earned value technique it drives earned value. It can also mislead: spending half the hours doesn’t mean half the work is done if productivity is poor.
Common mistakes
- Expecting units progress to shorten the remaining duration automatically.
- Using units progress with an unreliable hours estimate, so the percent reflects spending rather than work done.
- Forgetting that material assignments don’t count.
How os.construction handles it
Units percent complete is read from XER and P6 XML, kept with each activity alongside the assignment totals it was measured against, and written back on export. A new value re-spreads the assignments’ units and holds the remaining duration, as P6 does. See Activity details and P6 fields.
FAQ
How is units percent complete calculated?
Actual units divided by at-completion units (actual plus remaining), summed over the activity's labor and nonlabor assignments. Material assignments aren't included.
Does entering units percent complete change the remaining duration?
No. In P6 the scheduler sets the remaining duration or an expected finish. Entering units progress re-spreads the assignments' actual and remaining units instead.
When should I use units rather than duration or physical percent complete?
When progress is best measured by resource effort spent, such as labor-heavy work tracked from timesheets, and the units estimate is reliable.