Field Mode (Offline Sync)

Definition

A way to keep a schedule on a phone, record progress on site without signal, and sync the updates as one new version when the connection returns.

Topic: Field operations

Updated

Field mode keeps a project’s schedule on a phone or tablet so a superintendent can use it where there’s no signal: below grade, inside a steel structure, or on a rural site. Progress recorded there is held in an offline queue on the device and synced to the shared schedule once the connection returns.

Why it matters

Progress recorded from memory at the end of the day is late and less accurate. Recording it at the activity, when it happens, gives the scheduler better actual dates. Offline sync makes that possible on sites with dead zones, but it brings a new risk: the office may change the same activity in the meantime. A sound sync never overwrites someone else’s change without asking.

Worked example

Illustrative: on Tuesday morning the superintendent marks Level 2 deck pour started and sets it to 40% complete, two floors below grade with no signal. Meanwhile the scheduler saves version 18, setting the same activity’s remaining duration to 3 days. At lunch the phone reconnects. The percent complete merges without a question; the remaining duration was changed on both sides, so the superintendent sees was 5 · yours 4 · saved 3 and chooses. The result saves as version 19, recalculated, and records that it came from the field.

Common mistakes

  • Waiting until you’re on site to keep the project offline. The copy has to be stored while you still have signal.
  • Handing a device to a colleague with updates still queued. Sync first.
  • Treating the stored dates as current. Nothing is recalculated offline; dates update on sync.

How os.construction handles it

Schedule › Field mode keeps the activities, their last calculated dates, the three-week lookahead and your layout on the device, per user and project. Offline you can mark work started or finished and set percent complete and remaining duration. A sync goes through the Planner’s versioned save, and every conflicting field needs an explicit choice. The copy is cleared on sign-out, on a user switch or when access is lost. See Field mode (offline).

FAQ

What happens if someone changes the schedule while I'm offline?

Your updates are replayed onto the newer version. Fields the other person didn't touch merge on their own; a field you both changed is shown with both values, and you choose which to keep before anything syncs.

Is the offline copy secure?

It's limited to what you can open online and is cleared on sign-out or when you lose access, but it sits in the browser's storage unencrypted by the app. Protect the device with encryption and a screen lock.