Cash flow on a construction job: why profitable jobs run out of money

A job can earn a healthy margin and still drain your bank account for months. Profit is an accounting result; cash is timing. Here's how the pay app cycle, retainage and payment terms open a cash gap on every job, and how to see it coming.

Charley Forey5 min readCash flowBillingAccounting
On this page
  1. Where the gap comes from
  2. An example job
  3. What makes the gap wider
  4. What makes it narrower
  5. Questions to ask at bid time
  6. Forecast it, don’t discover it
  7. What we’re building

Contractors don’t usually go under because their jobs lose money. They go under because the money arrives too late. A company with a strong backlog and healthy margins can still miss payroll if three big jobs hit their cash low point in the same month.

Profit and cash measure different things. Profit is what the job earns over its life. Cash is when the dollars actually move. On a construction job, those two lines can be months apart.

Where the gap comes from

Every job has the same basic timing problem: you pay for the work before the owner pays you for it.

  • You pay labor weekly. Payroll goes out every Friday, from the first week of the job.
  • Suppliers and subs want paid on terms. Material on 30 days, subs on the next pay cycle, sometimes sooner if you want to keep a good sub.
  • You bill monthly, in arrears. The pay application covers work through a cutoff date, often the 25th. Then it’s reviewed, maybe revised, certified by the architect, and processed by the owner and sometimes a lender. Getting paid 30 to 60 days after the work is done is normal; longer is common.
  • Retainage holds back a slice of every payment. Often 5 to 10%, held until substantial or final completion. On a long job, that’s a large amount of earned money sitting with the owner.

Your own pay-when-paid or retainage terms with subs soften the gap, which is why sub agreements usually mirror the prime contract. But labor, materials, equipment and general conditions don’t wait.

An example job

Illustrative numbersA made-up $1.2M job with a 12% margin, simplified to show the shape. 35% of each month’s cost is paid that month (payroll), the rest the following month. Each pay app is collected two months after the work, less 10% retainage. Retainage is collected at the end, after closeout. Sub retainage is ignored to keep it simple.
Month Cost incurred Billed Cash out Cash in Cumulative cash
1 $100K $114K $35K $0 −$35K
2 $250K $284K $153K $0 −$188K
3 $300K $341K $268K $102K −$353K
4 $250K $284K $283K $256K −$380K
5 $156K $177K $217K $307K −$290K
6 $101K $256K −$136K
7 $160K +$24K
8 $120K +$144K

The job earns $144,000 on $1.2M. A good job. But for six straight months it’s cash negative, and at its worst point in month 4 the company has $380,000 of its own money in it. That’s 2.6 times the job’s entire profit, financed by your bank account or your line of credit.

$0−$380K PEAK+$144K PROFITM1M2M3M5M6M7M8M4
Profitable job, negative cash for six months. Illustrative.

Now imagine five of these jobs, started a month apart. Their troughs overlap. That’s how a contractor with a full backlog and good margins ends up drawing down the line to make payroll.

What makes the gap wider

  • Slow pay apps. Every week the pay app goes out late is a week added to the gap. A pay app kicked back for a missing lien waiver or an unapproved line can push collection a full cycle.
  • Unbilled change orders. Approved change work you’ve already paid for but can’t bill until it’s on the schedule of values. Every month a change sits unbilled, you’re financing the owner.
  • Back-loaded billing. A schedule of values that lags your cost curve keeps you underbilled, which is the same thing as funding the work yourself.
  • Stored materials you can’t bill. Big material buys paid on delivery, where the contract doesn’t allow billing for stored materials or requires documentation you don’t have yet.
  • Slow closeout. Retainage is the last cash in. Every month closeout drags is a month that profit sits with the owner.

What makes it narrower

  • Bill on time, every time. The single biggest lever. A clean pay app submitted on the cutoff date is worth more than any negotiation.
  • Get approved changes onto the next pay app. Set it as a rule, then check it every cycle.
  • Negotiate the schedule of values. Mobilization, general conditions and early-trade lines that track your real cost curve. Within reason, a modest front-load is common.
  • Mirror the prime contract downstream. Sub payment and retainage terms that line up with how and when you get paid.
  • Close out like it matters. Because the profit is in the retainage.
The weekly questionFor every job, ask: how much of our own cash is in this job today, and when does that peak? Sum it across jobs. If the total peak is close to your line of credit, you know before the bank does.

Questions to ask at bid time

Cash is easier to protect before the contract is signed than after. Before you commit to a job, ask: what are the owner’s payment terms, and does the owner have a track record of meeting them? Is there a lender in the payment chain, adding a review step? What’s the retainage rate, does it reduce at a milestone, and when is it released? Can you bill for stored materials? How much of your cost is self-performed labor, which you pay weekly, versus subcontracted work on terms that mirror yours? The answers don’t change the margin. They change how much of your own cash the margin will cost.

Forecast it, don’t discover it

A cash forecast doesn’t need to be fancy. For each job: remaining cost by month and when it gets paid, remaining billing by month and when it gets collected, retainage and when it’s released. Sum across jobs, add overhead, and you have a 13-week or six-month view of where the company’s cash is going. Our cash flow calculator builds that curve for a single job, and the retainage calculator shows how much is being held. If you would rather keep it in a spreadsheet, the construction cash flow projection template for Excel does the same month by month, with live formulas and an S-curve chart.

The hard part is keeping it current. Billing dates, payment terms, approved change orders and committed costs all live in different places, so the forecast is a spreadsheet rebuilt once a month and wrong by the time it’s finished. For more on why billing lags, see over billing vs under billing and retainage, lien waivers and pay apps on one record.

What we’re building

In os.construction, the contract, the schedule of values, commitments, payment terms and the pay app history are designed to live on one record, so a job’s cash curve can be projected from the data you already keep rather than rebuilt by hand. The contract, SOV, commitments and pay app history are live in the app. Accounting already forecasts company cash 13 weeks or 12 months ahead from open AR, retainage, unbilled contract value, AP, commitments and payroll, with scenarios and forecast vs actual (cash forecasting). Cost-loaded cash curves for each job are planned. If you’re running cash on a spreadsheet and a gut feeling, start a free trial.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Keep readingAll articles →
Billing

How to bill stored materials on a pay application, and move them to installed

Stored materials let you bill for equipment and material that is bought and delivered but not yet installed. Check the contract first, get off-site storage approved in advance, send the backup with the bill, put the amount in the stored materials column, and move it to work completed when it goes in so it is never billed twice. Here is each step with a two-month worked example.

7 min read

Cash flow

How to build a 13-week cash flow forecast for a construction company

A 13-week cash forecast lists every receipt and payment the company expects, week by week, starting from the cash actually in the bank. Date receipts by when each owner really pays, date payments by payroll, terms and pay-when-paid, set a minimum balance, and roll it forward every week against what happened. Here is each step and a worked 13-week example with a low week.

7 min read

Cash flow

How to build a construction cash flow projection: from the cost curve to the month you're lowest

A job's cash flow projection moves every dollar of billing and cost to the month it's actually paid. Spread cost by month, bill it, delay the receipts by the owner's payment terms and retainage, time each kind of cost by its own terms, then run the cumulative total to find the peak cash need. Here is each step and a worked eight-month example.