Contractors don’t usually go under because their jobs lose money. They go under because the money arrives too late. A company with a strong backlog and healthy margins can still miss payroll if three big jobs hit their cash low point in the same month.
Profit and cash measure different things. Profit is what the job earns over its life. Cash is when the dollars actually move. On a construction job, those two lines can be months apart.
Where the gap comes from
Every job has the same basic timing problem: you pay for the work before the owner pays you for it.
- You pay labor weekly. Payroll goes out every Friday, from the first week of the job.
- Suppliers and subs want paid on terms. Material on 30 days, subs on the next pay cycle, sometimes sooner if you want to keep a good sub.
- You bill monthly, in arrears. The pay application covers work through a cutoff date, often the 25th. Then it’s reviewed, maybe revised, certified by the architect, and processed by the owner and sometimes a lender. Getting paid 30 to 60 days after the work is done is normal; longer is common.
- Retainage holds back a slice of every payment. Often 5 to 10%, held until substantial or final completion. On a long job, that’s a large amount of earned money sitting with the owner.
Your own pay-when-paid or retainage terms with subs soften the gap, which is why sub agreements usually mirror the prime contract. But labor, materials, equipment and general conditions don’t wait.
An example job
| Month | Cost incurred | Billed | Cash out | Cash in | Cumulative cash |
|---|---|---|---|---|---|
| 1 | $100K | $114K | $35K | $0 | −$35K |
| 2 | $250K | $284K | $153K | $0 | −$188K |
| 3 | $300K | $341K | $268K | $102K | −$353K |
| 4 | $250K | $284K | $283K | $256K | −$380K |
| 5 | $156K | $177K | $217K | $307K | −$290K |
| 6 | $101K | $256K | −$136K | ||
| 7 | $160K | +$24K | |||
| 8 | $120K | +$144K |
The job earns $144,000 on $1.2M. A good job. But for six straight months it’s cash negative, and at its worst point in month 4 the company has $380,000 of its own money in it. That’s 2.6 times the job’s entire profit, financed by your bank account or your line of credit.
Now imagine five of these jobs, started a month apart. Their troughs overlap. That’s how a contractor with a full backlog and good margins ends up drawing down the line to make payroll.
What makes the gap wider
- Slow pay apps. Every week the pay app goes out late is a week added to the gap. A pay app kicked back for a missing lien waiver or an unapproved line can push collection a full cycle.
- Unbilled change orders. Approved change work you’ve already paid for but can’t bill until it’s on the schedule of values. Every month a change sits unbilled, you’re financing the owner.
- Back-loaded billing. A schedule of values that lags your cost curve keeps you underbilled, which is the same thing as funding the work yourself.
- Stored materials you can’t bill. Big material buys paid on delivery, where the contract doesn’t allow billing for stored materials or requires documentation you don’t have yet.
- Slow closeout. Retainage is the last cash in. Every month closeout drags is a month that profit sits with the owner.
What makes it narrower
- Bill on time, every time. The single biggest lever. A clean pay app submitted on the cutoff date is worth more than any negotiation.
- Get approved changes onto the next pay app. Set it as a rule, then check it every cycle.
- Negotiate the schedule of values. Mobilization, general conditions and early-trade lines that track your real cost curve. Within reason, a modest front-load is common.
- Mirror the prime contract downstream. Sub payment and retainage terms that line up with how and when you get paid.
- Close out like it matters. Because the profit is in the retainage.
Questions to ask at bid time
Cash is easier to protect before the contract is signed than after. Before you commit to a job, ask: what are the owner’s payment terms, and does the owner have a track record of meeting them? Is there a lender in the payment chain, adding a review step? What’s the retainage rate, does it reduce at a milestone, and when is it released? Can you bill for stored materials? How much of your cost is self-performed labor, which you pay weekly, versus subcontracted work on terms that mirror yours? The answers don’t change the margin. They change how much of your own cash the margin will cost.
Forecast it, don’t discover it
A cash forecast doesn’t need to be fancy. For each job: remaining cost by month and when it gets paid, remaining billing by month and when it gets collected, retainage and when it’s released. Sum across jobs, add overhead, and you have a 13-week or six-month view of where the company’s cash is going. Our cash flow calculator builds that curve for a single job, and the retainage calculator shows how much is being held. If you would rather keep it in a spreadsheet, the construction cash flow projection template for Excel does the same month by month, with live formulas and an S-curve chart.
The hard part is keeping it current. Billing dates, payment terms, approved change orders and committed costs all live in different places, so the forecast is a spreadsheet rebuilt once a month and wrong by the time it’s finished. For more on why billing lags, see over billing vs under billing and retainage, lien waivers and pay apps on one record.
What we’re building
In os.construction, the contract, the schedule of values, commitments, payment terms and the pay app history are designed to live on one record, so a job’s cash curve can be projected from the data you already keep rather than rebuilt by hand. The contract, SOV, commitments and pay app history are live in the app. Accounting already forecasts company cash 13 weeks or 12 months ahead from open AR, retainage, unbilled contract value, AP, commitments and payroll, with scenarios and forecast vs actual (cash forecasting). Cost-loaded cash curves for each job are planned. If you’re running cash on a spreadsheet and a gut feeling, start a free trial.