From incident report to the OSHA 300 log
Most jobsite injuries never reach the OSHA 300 log, and the ones that do are often classified late or counted wrong. Follow four injuries on one job from the incident report to the log, and see which ones belong on it and why.
A case goes on the 300 log when it's work-related, new and serious enough
Under 29 CFR 1904.7, a work-related injury or illness is recordable if it results in death, days away from work, restricted work or transfer to another job, medical treatment beyond first aid, loss of consciousness, or a significant injury or illness diagnosed by a physician or other licensed health care professional. Everything else (a bandage, an ice pack, a tetanus shot) is first aid and stays off the log. Each recordable case gets one line, classified by its most serious outcome, with days away and restricted days counted on that line.
Six steps from the event to the log
The first three happen on the day. Classification can wait for the clinic note, but OSHA gives you seven calendar days from learning of a recordable case to enter it (1904.29(b)(3)). Counting days goes on until the worker is back to full duty.
- 01EventInjury, near miss, release or damage
- 02ReportIncident saved the same day
- 03FactsInjury, witnesses, treatment
- 04ClassifyRecordable? Which class?
- 05Count daysAway and restricted, until back
- 06LogOne row on the OSHA 300 log
The test, in the order you ask it
Stop at the first "yes" below the first two questions. That answer is also the case's class on the log.
First aid or medical treatment?
This is where most classification arguments happen. OSHA's first aid list (1904.7(b)(5)(ii)) is closed: anything not on it is medical treatment.
| First aid: not recordable on its own | Medical treatment: recordable |
|---|---|
| Non-prescription medicine at non-prescription strength | Prescription medicine, or OTC medicine at prescription strength |
| Cleaning a wound, bandages, butterfly bandages, Steri-Strips | Stitches, staples, surgical glue |
| Hot or cold packs, elastic wraps, non-rigid supports | Rigid splints or casts used to immobilize |
| Removing a splinter, or a foreign body from the eye by irrigation or swab | Removing a foreign body from the eye by other means |
| Tetanus shot | Other vaccines, such as rabies or hepatitis B |
| Diagnostic X-ray or exam only | Physical therapy or chiropractic treatment |
Which ones reach the log
Four incidents on one project. Same kind of injury in the first two, different answers.
| Incident | What happened | Case Classification | On the 300 log | Days away | Days restricted |
|---|---|---|---|---|---|
| INC-031Laborer | Cut on rebar tie wire, cleaned and bandaged on site | First Aid Only | No | 0 | 0 |
| INC-034Carpenter | Cut closed with 4 stitches at the clinic, full duty next day | Other Recordable Case | Yes | 0 | 0 |
| INC-038Electrician | Sprained wrist, light duty for 6 days | Job Transfer or Restriction | Yes | 0 | 6 |
| INC-041Ironworker | Fall from ladder, off work 12 days, then 5 days light duty | Days Away From Work | Yes | 12 | 5 |
INC-031 and INC-034 are both cuts. The bandage is first aid; the stitches are medical treatment, so INC-034 is recordable even though the carpenter didn't miss a shift. INC-041 had both days away and light duty: the class is the most serious outcome, Days Away From Work, and both day counts go on its line.
Counting the days
- Count calendar days, including weekends and days the worker wouldn't have been scheduled, not the day of the injury itself (1904.7(b)(3) and (b)(4)).
- Count from the day a doctor or other licensed professional recommends it, even if the worker comes in anyway.
- You can stop counting days away at 180.
- Update the counts when the worker returns. A case that started as restricted work and later lost days moves to Days Away From Work.
Whose log is it on a multi-employer site?
The employer who supervises the worker day to day records the case (1904.31). For a GC that usually means your own employees and any temporary workers you supervise. A subcontractor's employee normally goes on the sub's own log, even when it happened on your job. Many GCs still record sub incidents in their project system for site safety, so keep the two lists straight.
TRIR and DART from the same four cases
Owners and prequalification forms ask for rates, not counts. Both use the hours worked by your own employees and normalize to 200,000 hours, roughly 100 full-time workers for a year.
TRIR = recordable cases × 200,000 ÷ hours = 3 × 200,000 ÷ 412,000 = 1.46
DART = (days-away + restricted/transfer cases) × 200,000 ÷ hours = 2 × 200,000 ÷ 412,000 = 0.97
One extra stitched cut changes the TRIR by about 0.49 on this many hours. On a small company's hours, a single case moves the rate a lot, which is why classifying first aid correctly matters.
Where each step lives in the app
- Report: Tools → Incidents → New Incident with title, event date (or "time of occurrence is unknown"), location, description. Save as Draft while you gather facts.
- Facts: injuries (person, company, body part, affliction, work activity, treated in ER, hospitalized overnight, work days absent, restricted and transferred), witness statements and attachments on the incident.
- Fix: corrective actions with an assignee, due date and Open, In Progress or Closed status.
- Classify: the Case Classification field: Death, Days Away From Work, Job Transfer or Restriction, Other Recordable Case, First Aid Only or Not Recordable. New incidents start as Not Recordable.
- Log: OSHA 300 Log lists every incident with one of the four recordable classes: case number, employee, job title, date, class, days away, days restricted, and the case and day totals.
The log reads the Case Classification, not the "This incident is recordable" checkbox. If the day fields on the incident are blank, it adds up the days from the injuries. The four cases above would show 3 cases, 12 days away and 11 days restricted.
Not today: exporting the log, the Form 300A annual summary, filtering the log by calendar year or establishment, masking privacy cases, and calculating TRIR or DART on the log page. The log shows only incidents the viewer can read, so private incidents are missing for people without access. Treat it as a project check on your company log.
Sources
- 29 CFR 1904.7: General recording criteria
- 29 CFR 1904.29: Forms (300, 300A, 301, privacy cases)
- 29 CFR 1904.31: Covered employees
- 29 CFR 1904.32: Annual summary (300A posting, February 1 to April 30)
Keep going
Keep exploring
Related across os.construction
- BlogSnagging, variations, retention: a US-UK construction term mapA snagging list is a punch list, a variation order is a change order and retention is retainage. A full US-UK crosswalk of construction terms, with the contract differences that matter: JCT and NEC vs AIA, practical vs substantial completion, and Canadian holdback.
- ExplainerBid, Performance and Payment BondsConstruction bonds explained: the three-party surety relationship, a bond's life from bid to closeout, bid bond withdrawal rules, typical penal sums, the Miller Act and how to make a payment bond claim.
- GlossaryCertificate of Insurance (COI)A one-page summary, usually on an ACORD 25 form, that shows a contractor's insurance coverages, limits and policy dates.
- GlossaryDesign-Bid-BuildThe traditional delivery method: the owner hires a designer to complete the drawings, bids them to contractors, then signs a separate construction contract.
- BlogHow to run a preconstruction meeting, with a sample agendaThe preconstruction meeting is the last chance to agree how the job will run before anyone is on site under pressure. Here is who should attend, a sample agenda covering scope, schedule, submittals, RFIs, changes, payment, safety and site logistics, how to write it up, and a worked example of a subcontractor precon.
- DocsImporting from your current stackBring project records into Migration and establish company books through reviewed Accounting imports for master data, open AP/AR, opening balances, journals and payroll YTD.
Sample project included
Try this workflow on the sample project
Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.
Want this on live job data?
Incidents and the OSHA 300 log page are live in os.construction. The log page has no export, Form 300A or year filter today.