Construction lessons in a minute · 0:47

Twenty Doors Arrived. How Many Are Installed?

Reconcile delivered material with installed quantity and stock without counting the delivery as completed installation.

An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.

Published · Illustrative examples · Watch on YouTube

Video transcript

Twenty doors arrived today. Does that mean twenty doors are installed? Look at where the material actually went.

In this example, eight were installed and twelve remain in storage. The delivery count is twenty. The installed count is eight.

Keep the same unit and location on both records so the numbers can be compared. Count returns, damage, or other movements separately if they occur.

A pallet on site is inventory, not completed installation. And installation still needs whatever checks your project requires.

Record delivery and work in place as different facts. Find the daily-log guide at os dot construction.